Title: AGS RSVP Review
1- AGS RSVP Review
- 4-5 November 2004
- Management Issues
- Philip Pile
- Collider-Accelerator Department
- 4 Feb 2004
2NSF-DOE MOU
- NSF-DOE MOU signed 22 July 2004
- Defines roles of NSF and DOE
- Defines RSVP organization
- Project Management Plan (PMP) to follow
- A RSVP Project Director responsibility with BNL
management assistance - Approval by Joint Oversight Group
- Non-DOE contractor work at AGS will be defined in
a forthcoming MOU for AGS experimental work - RSVP activities will not unfavorably impact RHIC
research activities as determined by the DOE
3NSF-DOE MOU (cont)
- Joint Oversight Group role
- Representatives from NSF and DOE
- Concur on all MOUs among RSVP partners
- Provide programmatic guidance
- Meets at least quarterly
- To evaluate status
- Provide policy actions
- Laboratory Oversight Group role
- Chaired by BNL HENP ALD (Tom Kirk)
- Consists of experts
- Provide general support to RSVP Project Director
- Provide project reviews upon request
4NSF-DOE MOU (cont)
- Integrated Project Management Team
- Established by NSF Division of Physics
- Facilitate interactions of RSVP project Office
with BNL - Consists of K0PI0, MECO, AGS project managers,
DOE Area Office and others from BNL - BNL HENP ALD
- Responsible for overall on-site integration
function and other laboratory-project connections - Will take reasonable actions to insure success of
the project goals - Concurrence of the Project Director is required
through a process to be defined in the PMP
5NSF-DOE MOU (cont)
- NSF Division of Physics
- Responsible for annual project reviews
- Will be invited to all relevant DOE reviews as
observers - DOE Office of Nuclear Physics and Office of High
Energy Physics - Will be invited to all relevant DOE reviews as
observers
6RSVP Project Organization
JOINT OVERSIGHT GROUP NSF DOE NP
DOE HEP NSERC
RSVP PROJECT DIRECTOR and DEPUTY W. Willis, J.
Kotcher
AGS WBS 1.4 P. Pile/A. Pendzick
MECO WBS 1.3 M. Hebert
KOPIO WBS 1.2 M. Marx
1.4.4 MECO D. Phillips
1.4.1 AGS Booster K. Brown
1.4.2 Switchyard A. Pendzick
1.4.5 Project Office
1.4.3 K0PI0 C. Pearson
7Management during construction
- Work is defined by yearly MOUs between the AGS
project, RSVP Project office and experiments. - Matrix RHIC and new hires to support RSVP
construction - RHIC priority will be maintained
- Conflicts will be handled with goal to not
seriously impact established RSVP milestones
overtime, second shiftetc.
8Management during construction
- Communications Meetings
- RSVP representatives will be invited to
participate in our usual Monday Division Staff
Meeting where the weeks Division work plan is
discussed - Plan to continue weekly RSVP specific meetings
(these began in July 2004), including relevant
Department personnel and representatives from the
experiments, to discuss management issues,
technical progress, schedule and cost issues
throughout the life of the project. Other
invitees include representatives from the RSVP
Project Office and the DOE Brookhaven Area
Office.
9Management during beam development and operations
phase
- Matrix RHIC and new hires to support RSVP beam
development - RHIC priority will be maintained
- RHIC beam development periods generally will not
allow RSVP operation -- were generally able to
plan these periods well in advance - 100 hours per week is the goal for RSVP
operations during RHIC stores - RSVP Operation during RHIC shutdown periods
allowed if impact on RHIC work is acceptable
10RSVP Operations Support
- ESFD operational crews (CAS Watch) are maintained
on a 24 hr basis, 7 days a week during RHIC
operations and shutdowns to provide - Safety surveillance of C-AD experimental areas
and equipment - General support for experiment and accelerator
operations - This crew, appropriately augmented, will provide
operations support for RHIC and RSVP
11 Experiment Communications Meetings the RHIC
approach
- Year Round
- Monday ESF Division Staff Meeting -
discussion with experiments and C-AD department
management personnel re work planned for the
week. Chaired by P. Pile. - During RHIC Operations
- Monday Schedule Meeting between RHIC experiment
representatives, RHIC run coordinator, and C-AD
Experiment and Accelerator Division Heads and
Scheduling Physicist to discuss/fix the schedule
for the upcoming week. Chaired by the Scheduling
Physicist - Tuesday "Time Meeting" of BNL personnel (key
engineers, physicists, MCR operations personnel,
C-AD management, Associate Lab Director for
HENP, experimenters and others are held during
RHIC operations to discuss schedule of collider
operations (as well as AGS fixed target
operations, if applicable), luminosity issues,
any special problems operations personnel or
experimenters may have etc. Chaired by the
Scheduling Physicist. - Wednesday RHIC Machine/Detector Planning
Meeting with experiments, attended by ALD for
HE NP, C-AD Department head, C-AD Division
heads, RCF representative, experiment
spokespersons and others. Chaired by P. Pile - Daily (as needed) RHIC Machine Status
Accelerator Physicist Meeting -
accomplishments/problems of previous 24 hrs, plan
for next 24 hrs, experiment representatives
welcomed. Chaired by Accelerator Run Coordinator
12Management of RSVP Operations Communications
Meetings
- These meetings are expected to continue into the
RSVP era - The plan is to integrate key RSVP personnel into
RHIC planning meetings so they become a
participant in the scheduling and priority
setting process - As usual, RHIC operations needs will take
priority over RSVP
13An Interagency C-AD project example
The NSRL Project
- MOU between NASA and DOE
- DOE BAO provided oversight for both NASA and DOE
- Joint NASA and DOE Lehman reviews
- BNL, DOE, NASA JSC and Headquarters close
cooperation - NASA agreed to apply DOE rules for structuring,
reporting etc. - WBS structure
- Schedule
- ARR
- Procedures
14The NSRL Project
- The NASA and DOE interagency project, was a major
success. On schedule and below budget. - The RSVP NSF and DOE interagency project should
result in the same level of success.
15Final Comments
- C-AD has had 50 years of experience with
management, construction and operation of fixed
target experiments - RSVP construction and operations will take full
advantage of this previous experience. - RSVP construction is not out of the ordinary.
16Supplemental information
17(No Transcript)