RSVP - Booster/AGS Status
  • Mechanical Systems status
  • Electrical Systems status
  • Updated/Revised Contingency Factors
  • CFI Costs added. Under Review.

2
Mechanical Systems costs update, without
contingency indirects
  • Booster Magnet Coils - 25,878.
  • Booster Spare F6 66,140.
  • Booster Injection 398,244. (under
    review)
  • Booster Collimator 525,092. (under
    review)
  • AGS Magnet Coils 47,895.
  • New H20 ES (2) 146,998.
  • Spare F10 Septum - 78,776.
  • New F5 (2) 590,525. (under review)
  • Total
    1,670,240.

3
Electrical systems
  • Updated F10 P.S. cost 49,044.
  • For Schedule make P.O. when magnet designs are
    complete. Expect 1 yr for purchase, delivery,
    installation and testing.