Title: AGS RSVP Weekly Meeting


1
AGS RSVP Weekly Meeting, 30 Sep 2004
  • P. Pile comments
  • First pass at AGS/Booster modifications schedule
    and "final" costs (K. Brown)
  • Critical look at power supply controls (PSI type
    modifications) issues (mainly cost!) (J.
    Sandberg)
  • Other subsystems status reports
  • 1 page list of things left to do to complete
    cost and schedule estimate with expected
    completion dates - (A. Pendzick, K. Brown, C.
    Pearson, D. Phillips)
  • Useful Links
  • RSVP Project Office http//rsvp.bnl.gov/Project
    _Office/Estimates/RSVPEstimates.htm
  • C-AD AGS Project Office http//server.c-ad.bnl.
    gov/esfd/RSVP/RSVP_AGS_WBS.htm

2
Roadmap to the AGS WBS Review
  • 30 Sep
  • spreadsheets "complete" - i.e. no blank entries,
    first pass at WBS dictionaries
  • First pass at AGS/Booster modifications schedule,
    "final" costs (Kevin)
  • Critical look at power supply controls (PSI type
    modifications) issues (mainly cost!) (Jon S.)
  • 7 Oct
  • First look at ACCESS data base (Darlene)
  • Booster AGS/Switchyard/MECO and K0PI0 resource
    loaded schedules - discussion of what's left to
    be done (Kevin,Al,Charlie,Dave)
  • Beam Development Plan revisited (Ahrens)
  • 14 Oct
  • AGS RSVP resource loaded schedule - what's left
    to be done (Al)
  • Critical look at weak spots by each wbs section
    leader
  • Review agenda set (assumes charge is delivered
    1st week in Oct)
  • 21 Oct
  • beam development plan (Ahrens)
  • Beam development operations costs (Phil)
  • AGS RSVP "final" resource loaded schedule (Al)

3
RSVP Beam Development Costs based on Jan 04
plan (Lehman Review) with reduced indirects
4
RSVP AGS Cost Status as of 9/29/04
5
(No Transcript)
6
(No Transcript)
7
AGS Review4-5 November 2004 (BNL) - Update
  • CHARGE to be determined
  • Chair Ray Larsen (SLAC)
  • My understanding
  • The review will cover all aspects of the AGS
    WBS
  • Will emphasize AGS/Booster/Switchyard
    modifications that are new to the project
  • i.e. we need to make our case at this review
  • The review will not look at PMPs, PEPs etc,
    or at detailed schedules.
  • Costs will likely be a key issue
    concentrate on the present spreadsheet approach
    and collecting backup material for costs.
  • The schedule needs to be sufficiently
    developed to understand how the
    AGS/Booster/Switchyard work will be incorporated
    into MECO and K0PI0 beam development
  • RSVP Beam development plan and costs will also
    be reviewed
  • More guidance on will be forthcoming

8
Homework (repeat from last meeting)
  • Jon Kotcher is planning to seek additional FY
    2005 funds for the project
  • What else do we need to ask for?
  • I need input from WBS managers, send me statement
    one way or the other by end of day tomorrow!

9
Next Meeting
  • 7 Oct 2004
  • Agenda
  • ACCESS data base (Darlene)
  • Booster AGS/Switchyard/MECO and K0PI0 resource
    loaded schedules - discussion of what's left to
    be done (Kevin,Al,Charlie,Dave)
  • Beam Development Plan revisited (Ahrens)