Title: AGS RSVP Weekly Meeting
1AGS RSVP Weekly Meeting, 18 Nov 2004
- Agenda
- AGS Review close-out, probable outcome from
AGS review, meco magnet review actions, next
significant events, ACCESS data base status (P.
Pile) - How we get from here to there - fully loaded
Project schedules (A. Pendzick/D. Phillips)
- Useful Links
- RSVP Project http//rsvp.bnl.gov
- C-AD AGS Project Office http//server.c-ad.bnl.
gov/esfd/RSVP/RSVP_AGS_WBS.htm
2AGS WBS Review, 4-5 Nov 2004
- RSVP AGS Review Committee
- R. Larsen, S. Ecklund, J. Seeman, A. Marchionni,
E. Metral, G. McMichael, R. Pasquinelli - Slides to follow are from close-out (R. Larsen)
- Close-out slides are archived on web
- http//server.c-ad.bnl.gov/esfd/RSVP/November2004/
rsvp-presentations.htm
3General Comments
- The Committee was pleased to see the level of
work represented by the presentations, which were
clear and well integrated. - Most detailed planning cost work accomplished
since July 2004. - Some aspects of content need further development.
4Implementation Plan Resource Loaded Schedules
- The implementation plan for Booster, AGS and
Switchyard was well detailed. - The plans for experimental beams and Beam
Development have questions concerning the
experimental interfaces and schedule. - Some resource analysis was shown, but resource
loaded schedules are not yet developed.
5Non-RSVP Elements
- These elements appear to have been identified and
excluded appropriately. - Manpower support for operations requires
integration with the existing RHIC matrix, which
will be augmented with levels of manpower
appropriate to the incremental RSVP levels.
6Technical, Schedule Cost Risks
- The bulk of the Booster, AGS and Switchyard
upgrades are low technical risk. - Achieving higher levels of intensity and cleaner
extinction between pulses through additional RF
magnets are critical to the experiments these
have been modeled but not been demonstrated and
are higher technical risk. - Changes in the experiments may pose additional
technical risks beyond the control of the AGS
team.
7Schedule Risk
- The risks were discussed during various
presentations. - The schedule risks for the bulk of AGS upgrades
appears to be mostly in ramping up to needed
manpower levels and finding appropriate people
for temporary work, esp. engineers. - The start date of 2006 appears aggressive
considering the unknowns of total project cost
and funding. - The Beam Development schedule is a draft and will
be reexamined to attempt to reduce duration from
five to three years. - The overall schedule integrated with the
experiments needs to be developed. - The delivery of critical experimental components
poses risks beyond the control of the AGS Upgrade
team.
8Cost Risk
- Cost risks were not presented as a separate
analysis by the team, but in subsequent
presentations. - The contingency levels of most estimates averaged
less than 25 which indicates high confidence
factor. - This is appropriate for most parts of the AGS
complex since the upgrade includes few technical
uncertainties. - Uncertainties of experiments can pose serious
risk - KOPIO production angle, pit size
- MECO production solenoid, target etc.
- Overall cost growth in estimates is causing
serious concern within the funding agency.
9Cost Growth
- The cost estimate has grown since January 2004 by
30M to a final total of 84M of which 32M is
attributed to Beam Development. - The latter is in reality Pre-Ops as opposed to
construction and did not change since January. - Therefore the construction segment appears to
have more than doubled. - Reasons
- Magnet/PS/controls upgrades to reduce risk to
RHIC - ESH requirements for caps over high-activation
areas - Growth in experimental beams costs
- Addition of Project Office
10Operations Plan, Resource-Loaded Schedule,
Conflicts
- The plan was presented along with an incremental
total manpower analysis. - The resources were averaged and not leveled in
detail. - Conflicts with RHIC requirements have to be
worked out in detail. - Concerns about difficulties of finding skilled
people matrix management. - Potential impacts on costs and schedules.
11Management Plans
- Integration, Communication major factors
- There is recent precedent at BNL for similar
management issues, e.g. SNS and ATLAS. - Lines of authority appear well understood though
inherently complicated by dual lines of authority
up the chain. - Standing management meetings either exist already
or will be set up alongside the current RHIC
management structure. - Operations will be well integrated with RHIC
through liaisons, daily weekly meetings.
12Explore Reductions in Scope, etc.
- This was attempted throughout the meeting
- Delete one of the experiments Unacceptable.
Experiments have been sold as a package. - Defer AGS upgrades Bad strategy poses high risk
to RHIC and would miss existing low activation
window of opportunity in AGS. - Reduce or eliminate Beam Development program
Possible cost reduction of 14M without much
compromise to program, if any, appears feasible.
Team will investigate. - Additional cost reductions should be sought
through scrubbing technical component design
and costs, labor costs, system design
improvements in both AGS and experiments.
13Conclusion
- The Committee is very pleased that a large effort
over the past four months has shown impressive
progress and dividends in the planning process. - We look forward to seeing continued progress in
planning and development, and ultimate success in
securing full funding and staffing. - Thanks to all the presenters for their diligent
efforts in helping meet our Charge. - Keep up the good work!
14Recommendations
Probable Guidance well get from Willis/Kotcher
- Continue refining estimates with Lehman-like
documentation (resource loaded leveled
schedules, cost books etc.) for future review. - Schedule future cost scrubbing reviews of both
AGS and experimental programs. - Continue aggressive cost-reduction plan, such as
design improvements to replacement components,
reducing/eliminating Beam Development program,
beam operations manpower levels etc - Continue identifying, mitigating technical,
schedule and cost risks.
15Preliminary Guidance our plan(subject to
change we have not yet received guidance from
Willis/Kotcher as result of 4-5 Nov AGS Review)
- Continue cost scrubbing and schedule development
- Highest priority to AGS/BOOSTER WBS 1.4.1
- Cost scrubbing, what can we postpone until
operations phase? etc - Schedule in particular a plan to get the
AGS/BOOSTER in shape for high intensity beam
development --- by beginning of 3rd year of
construction? - Beam development plan that fits within constant
effort RHIC budget scenario with 2 beams i.e.
figure on 80 hrs/week and 15 weeks/year - Case 1 Beam development during entire 5 year
construction period - Case 2 Beam development beginning 3rd year of
construction - The construction plan should be developed
consistent with no beam development in first two
years of the project (Case 2 above) - D-line decommissioned
- C-Line available beginning of 3rd year for tests
- theres a risk (small) that we may have to revert
back to the original plan (Case 1).
16Update on MECO Magnet Issues
- Still no formal guidance as result of the 10-11
Oct MECO Magnet Review - A plan to implement some of the panel
recommendations is, however, being developed.
17--DRAFT--
18--DRAFT--
RSVP FY05 Supplemental Request MECO Magnet
19next significant events
Milestone Date Status, Comments
Discussion of Baseline Expectations, Timeline with Experiments September 13 Held
MECO Magnet Review Sun-Tue, Oct 10-12 Held
AGS Review Thu-Fri, Nov 4-5 Held
Internal discussion of resource-loaded schedules (RLS) for all projects Thu, Dec 10? Includes PO, NSF PM, ALD experiments. Anticipate one full day. Date TBF.
Simulations Backgrounds Review Tue-Thu, Jan 11-13 Set, reviewers assembled, held at NYU
Initial review of RLS for all projects Tue-Thu, Jan 18-20 Reviewed by LOG. Dates TBF.
Reviews of other sub-projects Weeks of Jan 24 Feb 21 Series of LOG-based reviews of RSVP sub-systems
Draft versions of PMP, PEP, Conceptual Design Report completed Mon, Feb 14
Operations Review Week of Mar 7
Project startup pre-review Week of Mar 15 Comprehensive preparatory review of full project, proposal
Project startup review Week of Apr 18 Final project startup review, iteration of above. NSF review.
Finalize documentation for May submission to NSF Week of Apr 25
Product submitted to NSF/NSB Mon, May 2
20RSVP AGS Cost Status as of 11/18/04
21- Darlene has information from the latest
spreadsheets (V22) in entered into the ACCESS
data base - Changes to your WBS spreadsheets should go
directly to Darlene - finish your WBS Dictionaries! Enter on same
spreadsheet as costs - Send revised (available cost scrubbing) estimates
by 7 Dec, in time for the 9 Dec Internal
Discussions - Highlight changes for easy recognition and
summarize changes (with date) on the Change
spreadsheet - Darlene will then send spreadsheets to me and a
new version will be published
22Next Meeting
- 2 Dec 2004
- Agenda
- Update on AGS/BOOSTER WBS 1.4.1 cost scrubbing
(Brown) - Update on beam development plan (Leif)
- Status of resource loaded schedules (Pendzick)