Title: BNLAGS RSVP Upgrades Project WBS 1'4 Breakout Session
1BNL/AGS RSVP Upgrades ProjectWBS 1.4 Breakout
Session
- Rare Symmetry Violating Processes
- Preliminary Baseline Review
- Brookhaven National Laboratory
- 6-8 April 2005
- Phil Pile
2AGS Complex
NSRL
to RHIC
K0PI0
Linac
MECO
AGS
Booster
HITL
C-AD Admin
3AGS RSVP Project Office
4WBS 1.4 Materials Labor
5WBS 1.4 costs
6WBS 1.4 Work
40 FTEs per year
7Basis of cost estimates
- Level 3 sub-system managers are responsible for
cost estimates and schedules for their work - Bottoms-up approach to cost and scheduling
- The physicist or engineer responsible for the
work estimated the cost and developed the
schedule this individual holds the Cost Book
and Project file WBS 1.4 has 10 cost books and
40 individual project files - Schedules were developed consistent with target
milestones determined by experiment needs
(tempered with reality) - Contingency was estimated using the Lockheed
formalism (levels and weights) - Costs were scrubbed at least once by peer group
C-AD engineers/physicists - Individual fully-loaded project files are linked
to a Master Project file. Costs, schedule and
personnel requirements etc presented at this
review came from this file.
8Basis of cost estimates
- The WBS 1.4 Cost Books
- RF Systems
- Alex Zaltsman
- WBS 1.4.1 AGS/Booster
- Mechanical
- George Mahler (Joe Tuozzolo, Chien Pai and Mike
Mapes will substitute) - WBS 1.4.1 AGS/Booster
- Switchyard (WBS 1.4.2)
- Al Pendzick
- KOPIO (WBS 1.4.3)
- Charlie Pearson
- KOPIO Electrical
- Bob Lambiase
- WBS 1.4.1.5.1 (AGS Booster Kickers A10)
9Basis of cost estimates
- The WBS 1.4 Cost Books (cont)
- Security
- Neville Williams
- WBS 1.4.2 (Switchyard), 1.4.3 (K0PI0), 1.4.4
(MECO) - Instrumentation
- Dave Gassner
- WBS 1.4.1 (AGS/Booster), 1.4.2 (Switchyard),
1.4.3 (K0PI0), 1.4.4 (MECO) - Electrical
- Bob Lambiase
- WBS 1.4.1 (AGS/Booster)
- Controls
- Don Barton
- WBS 1.4.1 (AGS/Booster), 1.4.2 (Switchyard),
1.4.3 (K0PI0), 1.4.4 (MECO) - MECO (WBS 1.4.4)
- Dave Phillips
-
10Supplemental Material
11WBS 1.4 Dictionary L3 Summary
12Experiment construction milestones
RSVP Beam Development Possible
K0PI0 Engr/Physics Run
13Machine construction milestones
RSVP Beam Development Possible
K0PI0 Engr/Physics Run
14RSVP Operations Cost
- RSVP Specific Considerations Cost basis
- Since the RHIC program does not support any
manpower for AGS experiments all experimental
area manpower support will be billed to the NSF
consisting of - a base manpower level that supports the
extraction system, switchyard transport, primary
proton transport and the primary target area
(common to both RSVP experiments) - Incremental manpower for each experiment
15Operations Cost Basis
- RSVP Specific Considerations
- RSVP manpower is matrixed into the
Collider-Accelerator Department staff - Main control room operations is sufficient to
cover SEB operations during RHIC collision
operations except for an incremental effort to
support the SEB extraction system - RSVP support personnel will come from the present
C-AD staff together with new hires - C-AD RSVP support personnel will retain RHIC
responsibilities at a reduced level - When a conflict between RHIC and RSVP support
arises, RHIC support will win in all cases that
could impact RHIC operations - Material costs are based on actual costs of AGS
operations in support of HEP and NP fixed target
experiments (late 1990s). Full costs are
recovered if running outside RHIC operations,
otherwise the costs are incremental to RHIC
operations. - Pre-Operations are similarly handled but with
reduced costs due to reduced indirect charges
(part of construction project) and limited
operation (equipment development/testing).
16(No Transcript)
17(No Transcript)
18(No Transcript)
19RSVP Personnel Costs - Common
20RSVP Personnel Costs Exp. Specific
21MECO Cryo Ops and Maint Cost Est
22MECO Primary Beam Power Estimate
23K0PI0 Primary Beam Power Estimate
24K0PI0 Neutral Beam Power Estimate
25RSVP Pre-Operations Costs
26RSVP Pre-Operations Costs
27RSVP Pre-Operations Costs
28RSVP Pre-Operations Costs
29RSVP DD Costs(work in progress)
- The DD plan for RSVP is to restore the AGS floor
to the pre-RSVP condition within a reasonable
number of years after the end of experiment
operations - It is recognized that the experiments will
generate significant amount of beam activated
components that will have to be disposed of and a
2-3 year cool-down period will be required
before DD can begin - The slow beam transport will decommissioned
starting at the point where it leaves the
switchyard shielding to the RSVP targets - All commonly reused valuable equipment such as
magnets will be stored except for equipment
specific to the RSVP experiments, these will
be considered radioactive waste
30RSVP DD Costs(work in progress)
- The cost of removing and disposing of the
experiments will be included - Shielding under 5mr will be left in building 912
- All concrete floor areas over 5mr will be removed
and replaced, but no radioactive soil remediated - Power and water modifications for RSVP will be
removed except where considered an upgrade to
existing utilities -
- The AGS and Booster will remain operational for
RHIC when RSVP is complete so the only DD
envisioned will be for those components added
specifically for RSVP and not required for future
operation - It is anticipated that incremental DD costs will
be assessed yearly over the length of the planned
operation of the RSVP project, by a panel
appointed by the DOE and NSF, with funds placed
in a suitable escrow account
31K0PI0 DD Cost Estimate (work in progress)
(Ks)
These cost estimates have NOT been reviewed and
are presented for general guidance only!
Labor disposal cost
Total
32MECO DD Cost Estimate (work in progress)
(Ks)
These cost estimates have NOT been reviewed and
are presented for general guidance only!
Labor disposal cost
Total
33DD Costs Roll-up
These cost estimates have NOT been reviewed and
are presented for general guidance only!
The below costs are in millions of FY 2003
dollars, fully burdened Experiment Estimated
DD Cost K0PI0 5.3 MECO 5.3 Contin
gency 2.7 Total Estimated Cost 13.3