BNLAGS RSVP Upgrades Project WBS 1'4 Breakout Session - PowerPoint PPT Presentation

About This Presentation
Title:

BNLAGS RSVP Upgrades Project WBS 1'4 Breakout Session

Description:

K. Brown. WBS 1.4.1. Switchyard. A. Pendzick. WBS 1.4.2. K0PI0. C. ... Charlie Pearson. KOPIO Electrical. Bob Lambiase. WBS 1.4.1.5.1 (AGS Booster Kickers A10) ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 34
Provided by: Steve689
Category:

less

Transcript and Presenter's Notes

Title: BNLAGS RSVP Upgrades Project WBS 1'4 Breakout Session


1
BNL/AGS RSVP Upgrades ProjectWBS 1.4 Breakout
Session
  • Rare Symmetry Violating Processes
  • Preliminary Baseline Review
  • Brookhaven National Laboratory
  • 6-8 April 2005
  • Phil Pile

2
AGS Complex
NSRL
to RHIC
K0PI0
Linac
MECO
AGS
Booster
HITL
C-AD Admin
3
AGS RSVP Project Office
4
WBS 1.4 Materials Labor
5
WBS 1.4 costs
6
WBS 1.4 Work
40 FTEs per year
7
Basis of cost estimates
  • Level 3 sub-system managers are responsible for
    cost estimates and schedules for their work
  • Bottoms-up approach to cost and scheduling
  • The physicist or engineer responsible for the
    work estimated the cost and developed the
    schedule this individual holds the Cost Book
    and Project file WBS 1.4 has 10 cost books and
    40 individual project files
  • Schedules were developed consistent with target
    milestones determined by experiment needs
    (tempered with reality)
  • Contingency was estimated using the Lockheed
    formalism (levels and weights)
  • Costs were scrubbed at least once by peer group
    C-AD engineers/physicists
  • Individual fully-loaded project files are linked
    to a Master Project file. Costs, schedule and
    personnel requirements etc presented at this
    review came from this file.

8
Basis of cost estimates
  • The WBS 1.4 Cost Books 
  • RF Systems
  • Alex Zaltsman
  • WBS 1.4.1 AGS/Booster
  • Mechanical
  • George Mahler (Joe Tuozzolo, Chien Pai and Mike
    Mapes will substitute)
  • WBS 1.4.1 AGS/Booster
  • Switchyard (WBS 1.4.2)
  • Al Pendzick
  • KOPIO (WBS 1.4.3)
  • Charlie Pearson
  • KOPIO Electrical
  • Bob Lambiase
  • WBS 1.4.1.5.1 (AGS Booster Kickers A10)

9
Basis of cost estimates
  • The WBS 1.4 Cost Books (cont)
  • Security
  • Neville Williams
  • WBS 1.4.2 (Switchyard), 1.4.3 (K0PI0), 1.4.4
    (MECO)
  • Instrumentation
  • Dave Gassner
  • WBS 1.4.1 (AGS/Booster), 1.4.2 (Switchyard),
    1.4.3 (K0PI0), 1.4.4 (MECO)
  • Electrical
  • Bob Lambiase
  • WBS 1.4.1 (AGS/Booster)
  • Controls
  • Don Barton
  • WBS 1.4.1 (AGS/Booster), 1.4.2 (Switchyard),
    1.4.3 (K0PI0), 1.4.4 (MECO)
  • MECO (WBS 1.4.4)
  • Dave Phillips

10
Supplemental Material
11
WBS 1.4 Dictionary L3 Summary
12
Experiment construction milestones
RSVP Beam Development Possible
K0PI0 Engr/Physics Run
13
Machine construction milestones
RSVP Beam Development Possible
K0PI0 Engr/Physics Run
14
RSVP Operations Cost
  • RSVP Specific Considerations Cost basis
  • Since the RHIC program does not support any
    manpower for AGS experiments all experimental
    area manpower support will be billed to the NSF
    consisting of
  • a base manpower level that supports the
    extraction system, switchyard transport, primary
    proton transport and the primary target area
    (common to both RSVP experiments)
  • Incremental manpower for each experiment

15
Operations Cost Basis
  • RSVP Specific Considerations
  • RSVP manpower is matrixed into the
    Collider-Accelerator Department staff
  • Main control room operations is sufficient to
    cover SEB operations during RHIC collision
    operations except for an incremental effort to
    support the SEB extraction system
  • RSVP support personnel will come from the present
    C-AD staff together with new hires
  • C-AD RSVP support personnel will retain RHIC
    responsibilities at a reduced level
  • When a conflict between RHIC and RSVP support
    arises, RHIC support will win in all cases that
    could impact RHIC operations
  • Material costs are based on actual costs of AGS
    operations in support of HEP and NP fixed target
    experiments (late 1990s). Full costs are
    recovered if running outside RHIC operations,
    otherwise the costs are incremental to RHIC
    operations.
  • Pre-Operations are similarly handled but with
    reduced costs due to reduced indirect charges
    (part of construction project) and limited
    operation (equipment development/testing).

16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
RSVP Personnel Costs - Common
20
RSVP Personnel Costs Exp. Specific
21
MECO Cryo Ops and Maint Cost Est
22
MECO Primary Beam Power Estimate
23
K0PI0 Primary Beam Power Estimate
24
K0PI0 Neutral Beam Power Estimate
25
RSVP Pre-Operations Costs
26
RSVP Pre-Operations Costs
27
RSVP Pre-Operations Costs
28
RSVP Pre-Operations Costs
29
RSVP DD Costs(work in progress)
  • The DD plan for RSVP is to restore the AGS floor
    to the pre-RSVP condition within a reasonable
    number of years after the end of experiment
    operations
  • It is recognized that the experiments will
    generate significant amount of beam activated
    components that will have to be disposed of and a
    2-3 year cool-down period will be required
    before DD can begin
  • The slow beam transport will decommissioned
    starting at the point where it leaves the
    switchyard shielding to the RSVP targets
  • All commonly reused valuable equipment such as
    magnets will be stored except for equipment
    specific to the RSVP experiments, these will
    be considered radioactive waste

30
RSVP DD Costs(work in progress)
  • The cost of removing and disposing of the
    experiments will be included
  • Shielding under 5mr will be left in building 912
  • All concrete floor areas over 5mr will be removed
    and replaced, but no radioactive soil remediated 
  • Power and water modifications for RSVP will be
    removed except where considered an upgrade to
    existing utilities
  •  
  • The AGS and Booster will remain operational for
    RHIC when RSVP is complete so the only DD
    envisioned will be for those components added
    specifically for RSVP and not required for future
    operation
  • It is anticipated that incremental DD costs will
    be assessed yearly over the length of the planned
    operation of the RSVP project, by a panel
    appointed by the DOE and NSF, with funds placed
    in a suitable escrow account

31
K0PI0 DD Cost Estimate (work in progress)
(Ks)
These cost estimates have NOT been reviewed and
are presented for general guidance only!
Labor disposal cost
Total
32
MECO DD Cost Estimate (work in progress)
(Ks)
These cost estimates have NOT been reviewed and
are presented for general guidance only!
Labor disposal cost
Total
33
DD Costs Roll-up
These cost estimates have NOT been reviewed and
are presented for general guidance only!
  The below costs are in millions of FY 2003
dollars, fully burdened   Experiment Estimated
DD Cost   K0PI0 5.3   MECO 5.3   Contin
gency 2.7   Total Estimated Cost 13.3