Title: AGS RSVP Weekly Meeting
1AGS RSVP Weekly Meeting10 Feb 2005
- Agenda
- Project Office - Guidance etc.. (Pile)
- First cut at schedule for AGS/Booster work
(Mahler) - Overall WBS 1.4 Schedule - status and how we get
to a full resource loaded schedule (Pendzick) - WBS status reports - ...(Mahler (for Brown),
Pendzick,Pearson,Phillips) - cost books
- progress toward updating (cost-cut) project files
- what's left to cost scrub
- when will spreadsheets be updated
- Impacts of cost cutting on experiments -
(Lazarus, Meng)
- Useful Links
- RSVP Project http//rsvp.bnl.gov
- C-AD AGS Project Office http//www.c-ad.bnl.gov
/esfd/RSVP/RSVP_AGS_WBS.htm
2Present NSF Guidance (from FY2006 Presidential
Budget Request)
construction
preops/ops
3RSVP Project Office Present Guidance
- The RSVP Project Office is assembling an April
Baseline Review. - Baselining Pre-Review (held by Project Office)
week of April 4 - RSVP Baselining Review (held by NSF) week of
April 25 - The usual backup material - cost books, C/TDR's,
etc. - will be needed to review. - Project costs will have to be reported in
escalated dollars - The importance of this review to the success of
the RSVP project cannot be overemphasized!!! - Tom Kirk has volunteered to help review costs,
contingencies etc between now and April plans
to focus on one subsystem at a time beginning
with K0PI0 subsystems
4WBS 1.4 Cost-Cutting Exercise, as of 3 Feb
5WBS 1.4 Cost-Cutting Exercise, as of 3 Feb
- This is it for now.
- The plan
- Translate these rough cost reductions into
scrubbed cost estimates - Update project and spreadsheet files
- Do this by 23 Feb (lt 2 weeks from now!),
- Consider further cuts if necessary
6WBS 1.4 Cost-Cutting Exercise, as of 3 Feb
- Anything left in our plan that cannot be
justified as - Necessary to not compromise RHIC operations
- Necessary to insure compliance with laboratory
environmental protection guidelines - Part of the core requirements for RSVP
experiments (i.e. cant do experiment without it) - Necessary to bring the AGS back to FY2002 beam
intensities - Necessary to insure CFI effort goes forward
- Should be candidates for further cuts!!
7How we get to base line in April
- 16 Feb (Wed next week)
- Master Resource Loaded Schedule - First pass at
how WBS 1.4 work is spread over 5 years FY06-10
(what gets done, when and cost per year, rough
estimate of personnel requirements) Al will
discuss this at Kotchers Wednesday meeting with
RSVP project managers - 17 Feb (Thu next week)
- Cost Scrubbing complete,
- continue to work on completion of subsystem RLSs
- send subsystem excel spreadsheet updates to
Darlene as you complete RLSs
8How we get to base line in April
- 23 Feb (Wed) 2 weeks from now
- All subsystem resource loaded schedules complete
(with excel spreadsheets updates to Darlene) - Begin (continue?) entry into ACCESS data base
(Darlene) - WBS dictionaries complete to lowest level
- Are further cuts necessary?
- 2 Mar (Wed) 3 weeks from now
- Second pass at Master Resource Loaded Schedule,
modified as per guidance from RSVP Project Office
and experiments, complete with input from
subsystems project files
9How we get to base line in April
- 9 March (Wed) 4 weeks from now
- Cost Books assembled and ready for review
- AGS/Booster (Brown)
- Mechanical (Mahler)
- Electrical (Lambiase)
- MECO AGS Modifications (Brown)
- K0PI0 AGS Modifications (Brown)
- Switchyard (Pendzick)
- K0PI0 (Pearson)
- MECO (Phillips)
- Common to all WBS elements
- Controls (Barton)
- Security (Williams)
- Instrumentation (Gassner)
- All information should be to Darlene for entry
into the Access Data Base
10How we get to base line in April
- 16 Mar (Wed) (Changed from 23 Mar at Kotchers
request) - Draft TDR subsystem input due (Pile, editor) -
(Word or simple text) - Introduction and AGS Project Office (Pile)
- AGS/Booster and Switchyard (Brown)
- K0PI0 (Lazarus)
- MECO (Brown beam line/Meng all else)
- 23 Mar (Wed)
- Draft PMP and PEP (Pile) however, need RSVP
Project Office guidance
11Misc
- RSVP Project Office Account Number 88542
- 250K in supplemental funds has been promised
- The K0PI0 funds have arrived, accounts were setup
and then closed Continue to use above account
88542 - An RSVP All Hands Meeting (Willis and Kotcher)
will preempt this meeting next week same time
same place all are invited so please attend
(Ill be away next week)
12Supplemental/Archive
13RSVP Project Office Present Guidance (no
change from last week)
- All projects have been asked to design to cost,
according to the following guidelines (burdened
FY05) - KOPIO - 55M
- MECO magnet - 56M
- MECO - 24M
- AGS - 40M
- Project Office - 20M
- These numbers include contingency, which should
be constructed according to the Lockheed
guidelines as posted on the RSVP web site. - The Project Office will make any needed
adjustments in the overall contingency. - The RSVP Project Office is assembling an April
Baseline Review. - The usual backup material - cost books, C/TDR's,
etc. - will be needed to review. - Project costs will have to be reported in
escalated dollars