Title: AGS RSVP Weekly Meeting


1
AGS RSVP Weekly Meeting10 Feb 2005
  • Agenda
  • Project Office - Guidance etc.. (Pile)
  • First cut at schedule for AGS/Booster work
    (Mahler)
  • Overall WBS 1.4 Schedule - status and how we get
    to a full resource loaded schedule (Pendzick)
  • WBS status reports - ...(Mahler (for Brown),
    Pendzick,Pearson,Phillips)
  • cost books
  • progress toward updating (cost-cut) project files
  • what's left to cost scrub
  • when will spreadsheets be updated
  • Impacts of cost cutting on experiments -
    (Lazarus, Meng)
  • Useful Links
  • RSVP Project http//rsvp.bnl.gov
  • C-AD AGS Project Office http//www.c-ad.bnl.gov
    /esfd/RSVP/RSVP_AGS_WBS.htm

2
Present NSF Guidance (from FY2006 Presidential
Budget Request)
construction
preops/ops
3
RSVP Project Office Present Guidance
  • The RSVP Project Office is assembling an April
    Baseline Review.
  • Baselining Pre-Review (held by Project Office)
    week of April 4
  • RSVP Baselining Review (held by NSF) week of
    April 25
  • The usual backup material - cost books, C/TDR's,
    etc. - will be needed to review.
  • Project costs will have to be reported in
    escalated dollars
  • The importance of this review to the success of
    the RSVP project cannot be overemphasized!!!
  • Tom Kirk has volunteered to help review costs,
    contingencies etc between now and April plans
    to focus on one subsystem at a time beginning
    with K0PI0 subsystems

4
WBS 1.4 Cost-Cutting Exercise, as of 3 Feb
5
WBS 1.4 Cost-Cutting Exercise, as of 3 Feb
  • This is it for now.
  • The plan
  • Translate these rough cost reductions into
    scrubbed cost estimates
  • Update project and spreadsheet files
  • Do this by 23 Feb (lt 2 weeks from now!),
  • Consider further cuts if necessary

6
WBS 1.4 Cost-Cutting Exercise, as of 3 Feb
  • Anything left in our plan that cannot be
    justified as
  • Necessary to not compromise RHIC operations
  • Necessary to insure compliance with laboratory
    environmental protection guidelines
  • Part of the core requirements for RSVP
    experiments (i.e. cant do experiment without it)
  • Necessary to bring the AGS back to FY2002 beam
    intensities
  • Necessary to insure CFI effort goes forward
  • Should be candidates for further cuts!!

7
How we get to base line in April
  • 16 Feb (Wed next week)
  • Master Resource Loaded Schedule - First pass at
    how WBS 1.4 work is spread over 5 years FY06-10
    (what gets done, when and cost per year, rough
    estimate of personnel requirements) Al will
    discuss this at Kotchers Wednesday meeting with
    RSVP project managers
  • 17 Feb (Thu next week)
  • Cost Scrubbing complete,
  • continue to work on completion of subsystem RLSs
  • send subsystem excel spreadsheet updates to
    Darlene as you complete RLSs

8
How we get to base line in April
  • 23 Feb (Wed) 2 weeks from now
  • All subsystem resource loaded schedules complete
    (with excel spreadsheets updates to Darlene)
  • Begin (continue?) entry into ACCESS data base
    (Darlene)
  • WBS dictionaries complete to lowest level
  • Are further cuts necessary?
  • 2 Mar (Wed) 3 weeks from now
  • Second pass at Master Resource Loaded Schedule,
    modified as per guidance from RSVP Project Office
    and experiments, complete with input from
    subsystems project files

9
How we get to base line in April
  • 9 March (Wed) 4 weeks from now
  • Cost Books assembled and ready for review
  • AGS/Booster (Brown)
  • Mechanical (Mahler)
  • Electrical (Lambiase)
  • MECO AGS Modifications (Brown)
  • K0PI0 AGS Modifications (Brown)
  • Switchyard (Pendzick)
  • K0PI0 (Pearson)
  • MECO (Phillips)
  • Common to all WBS elements
  • Controls (Barton)
  • Security (Williams)
  • Instrumentation (Gassner)
  • All information should be to Darlene for entry
    into the Access Data Base

10
How we get to base line in April
  • 16 Mar (Wed) (Changed from 23 Mar at Kotchers
    request)
  • Draft TDR subsystem input due (Pile, editor) -
    (Word or simple text)
  • Introduction and AGS Project Office (Pile)
  • AGS/Booster and Switchyard (Brown)
  • K0PI0 (Lazarus)
  • MECO (Brown beam line/Meng all else)
  • 23 Mar (Wed)
  • Draft PMP and PEP (Pile) however, need RSVP
    Project Office guidance

11
Misc
  • RSVP Project Office Account Number 88542
  • 250K in supplemental funds has been promised
  • The K0PI0 funds have arrived, accounts were setup
    and then closed Continue to use above account
    88542
  • An RSVP All Hands Meeting (Willis and Kotcher)
    will preempt this meeting next week same time
    same place all are invited so please attend
    (Ill be away next week)

12
Supplemental/Archive
13
RSVP Project Office Present Guidance (no
change from last week)
  • All projects have been asked to design to cost,
    according to the following guidelines (burdened
    FY05)
  • KOPIO - 55M
  • MECO magnet - 56M
  • MECO - 24M
  • AGS - 40M
  • Project Office - 20M
  • These numbers include contingency, which should
    be constructed according to the Lockheed
    guidelines as posted on the RSVP web site.
  • The Project Office will make any needed
    adjustments in the overall contingency.
  • The RSVP Project Office is assembling an April
    Baseline Review.
  • The usual backup material - cost books, C/TDR's,
    etc. - will be needed to review.
  • Project costs will have to be reported in
    escalated dollars