AGS RSVP Weekly Meeting, 7 Oct 2004. P. Pile comments. ACCESS data base (Darlene) Booster AGS/Switchyard/MECO and K0PI0 spreadsheets and schedules - discussion of ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 7
Provided by: server4
Category:
Tags: ags | rsvp | meeting | pile | weekly

less

Transcript and Presenter's Notes

Title: AGS RSVP Weekly Meeting


1
AGS RSVP Weekly Meeting, 7 Oct 2004
  • P. Pile comments
  • ACCESS data base (Darlene)
  • Booster AGS/Switchyard/MECO and K0PI0
    spreadsheets and schedules - discussion of what's
    left to be done (Kevin, Al, Dave)
  • Beam Development Plan revisited (Leif)
  • Useful Links
  • RSVP Project Office http//rsvp.bnl.gov/Project
    _Office/Estimates/RSVPEstimates.htm
  • C-AD AGS Project Office http//server.c-ad.bnl.
    gov/esfd/RSVP/RSVP_AGS_WBS.htm

2
Roadmap to the AGS WBS Review
  • 30 Sep
  • spreadsheets "complete" - i.e. no blank entries,
    first pass at WBS dictionaries missing
    dictionaries for K0PI0, MECO and Project Office,
    still many blank entries for K0PI0
  • First pass at AGS/Booster modifications schedule,
    "final" costs (Kevin) will be done 14 Oct
  • Critical look at power supply controls (PSI type
    modifications) issues (mainly cost!) (Jon S.) -
    DONE
  • 7 Oct
  • First look at ACCESS data base (Darlene)
  • Booster AGS/Switchyard/MECO and K0PI0
    spreadsheets and schedules - discussion of what's
    left to be done (Kevin,Al,Charlie,Dave)
  • Beam Development Plan revisited (Leif)
  • 14 Oct
  • AGS RSVP Project consolidated construction
    schedule and what's left to be done (Al)
  • Critical look at weak spots by each wbs section
    leader bring laundry list
  • Review agenda set (assumes charge is delivered
    1st week in Oct) Hasnt happened yet!
  • 21 Oct
  • beam development plan (Leif)
  • Beam development operations costs (Phil)
  • AGS RSVP "final" RSVP AGS Infrastructure WBS
    Project schedule (Al)

3
RSVP AGS Cost Status as of 9/29/04
4
RSVP AGS Cost Status as of 10/7/04
5
AGS Review4-5 November 2004 (BNL) Update No
charge or new guidance
  • CHARGE to be determined
  • Chair Ray Larsen (SLAC)
  • My understanding
  • The review will cover all aspects of the AGS
    WBS
  • Will emphasize AGS/Booster/Switchyard
    modifications that are new to the project
  • i.e. we need to make our case at this review
  • The review will not look at PMPs, PEPs etc,
    or at detailed schedules.
  • Costs will likely be a key issue
    concentrate on the present spreadsheet approach
    and collecting backup material for costs.
  • The schedule needs to be sufficiently
    developed to understand how the
    AGS/Booster/Switchyard work will be incorporated
    into MECO and K0PI0 beam development
  • RSVP Beam development plan and costs will also
    be reviewed
  • More guidance on will be forthcoming

6
Next Meeting
  • 14 Oct 2004
  • Agenda
  • AGS RSVP Project consolidated construction
    schedule and what's left to be done (Al)
  • Critical look at weak spots by each wbs section
    leader bring laundry list
  • Review agenda discussion (assumes charge is
    delivered 1st week in Oct) Hasnt happened yet!