Title: LCLS Photon Systems Status
1LCLS Photon Systems Status
John Arthur SLAC
2LCLS Photon Systems
- Includes LCLS x-ray and laser groups
- X-ray Transport, Optics and Diagnostics (XTOD)
- managed by LLNL (Richard Bionta)
- X-ray Endstation Systems (XES)
- managed by SLAC (Stefan Moeller)
- LCLS Laser Systems
- managed by SLAC (Bill White)
3XTOD Scope
- Transport the x-ray beam, in vacuum, to all the
experimental stations - Condition the x-ray beam, with attenuators and
apertures - Analyze the x-ray beam, with sophisticated
diagnostics
4XES Scope
The X-Ray Endstation Systems group provides
the infrastructure required for experimenters to
make best scientific use of the LCLS radiation
safely
5Laser Group Scope
The Laser group coordinates laser design and
acquisition throughout the LCLS. Lasers will be
used in the electron gun and x-ray experimental
areas, and also possibly for accelerator
diagnostics and alignment.
6LCLS Designs are maturing
- FEE instrumentation at concept review stage
- Conventional facilities at Title 2 stage
7FEE
7 ft Fe
4 ft Fe
3 ft concrete
Mirrors
GAS ATTEN
COLLIM
STOP
STOP
SOLID ATTEN
32 m
8NEH
Hutch 1 9.5x10m
Hutch 2
Hutch 3
Flipper Mirrors
9Entrance 19ft tunnel (450 ft long)
FEH
Fire door
Fire door
15x25ft control cabin
46ft tunnel
6ft
10ft
28x33ft hutch
10ft
29x33ft hutch
36x33ft hutch
10ft
Toilets
19ft tunnel
212ft
10Building up the X-Ray Systems
- XTOD group has about 20 people now
- XES has 1 person and 2 openings
- LUSI has 5 openings now, more soon
- 2 other x-ray related hires at LCLS, 1 opening
11LCLS CE costs are expected to be high
- May will need to cut some scope
- Need to prioritize possible cuts
12Possible Scope Reductions
- Eliminate flipper mirrors (1M)
- Reduce length of x-ray transport tunnel by 10
(20m, 0.5M)
13Reduced scope FEH design
Entrance 14ft tunnel
hutch extended
single beamline
46ft tunnel
28x33ft hutch
29x33ft hutch
36x33ft hutch
30ft transition
20ft tunnel
212ft
14Effects of reductions
- No flipper mirrors beamline shared in FEH
- Shorter tunnel side beams closer to each other
by 10 (1.8m vs 2m)
15Summary
- Major staff increase ongoing
- Experimental needs coming into focus
- Need to consider possible scope cuts to save