Title: Report to the LCLS Facilities Advisory Committee
1Report to the LCLS Facilities Advisory Committee
Mark Reichanadter LCLS Deputy Project Director
- Project Management Status
- Cost and Schedule Performance
- Funding, Obligations Costs
- Milestones Critical Path
- Procurement Status
- Integration Management
- Risks Mitigations
- Summary
2Review Documentation
- LCLS Project Review information
- http//www-ssrl.slac.stanford.edu/lcls/fac/2008-ju
ne/index.html - Thumb drives of presentations and back-up
documents - Responses to Oct07 FAC Recommendations
- April 2008 Monthly Report
- Current LCLS Risk Registry
- Questions? Contact
- Helen ODonnell X3368, heleno_at_slac.stanford.edu
- Daphne Mitchell X5377, dmitchell_at_slac.stanford.edu
3Project Status
- LCLS reporting against a new Baseline
- Approved by DOE Deputy Secretary in January
- Addresses impacts of the FY07 CR
- TPC 420M (TEC 352M, OPC 68M)
- CD-4 July 2010
- TPC gt78 Complete, TEC gt82 Complete
- Contingency on TEC 21.3M
- 35 on remaining work
- Management Reserve on OPC 9.5M
- 35 on remaining work
- FY08 contingency tight but is being managed
3
4TEC Project Status Summary
- Technical Systems well advanced
- Injector Linac complete through Sector 30
- Undulator components mostly in hand.
- XTOD in procurement phase. XES in final design.
- Turner Construction gt90 Complete
- Powering equipment Tunneling activities
complete. - BO through NEH in June.
- BO through FEH in August.
- SLAC installing technical equipment prior to BO
co-occupancy - LCLS Facilities turned over to Operations
- Injector Facility (w/Drive Laser)
- Linac (w/BC-1, BC-2) through Sector 30
- Magnetic Measurement Facility
4
5LCLS Project Performance (Apr08)
5
6Project Performance (Apr08)
- TPC
- BCWS 304.5M
- BCWP 301.7M
- ACWP 301.4M
- Obligations (cum) 309.6M
- TEC (Line Item)
- Remaining Work (ETC) 60.3M
- 14M is under contract
- Est at Complete (EAC) 332.7M
- EAC includes variances and Pending BCRs
7TEC Remaining Work 60.3M
8LCLS Earned Value Indices
- Not much trend data with the resetting of CPI
SPI.
9LCLS TEC Progress
4.1M uncommitted BA on 24M of planned work
10FY08 Contingency Estimate
Estimate 1.4M draw on contingency through
30Sep08
10
11FY09 CR Impact Mitigation
- TEC base plan exceeds a strict 1/12th monthly CR
allocation 2.6M. - Worst case Delay procurements to match CR BA.
Early science in FY09 is at risk.
Assumes 0 carry-forward
- Preferred solution Request 8.1M in Oct08, with
3.1M in subsequent months. - Award schedule-critical procurements. Adequate
contingency is available to address unexpected
costs. Turner close out scheduled for Dec08.
12DOE (Level 2) Milestone Performance
L2 milestones include 2 months float from early
finish dates
12
13LCLS Schedule
- Critical Path (CP) to CD-4
- Undulator/FEE C.O. install FEL commission
Photons in FEH - Total float 108 working days (5months)
- K-measurement 108 days
- Soft X-ray Mirror System 109 days
- Undulator Girder Assembly 111 days
- Pop-Up Camera System 113 days
- Space Renovation BO 90 days
- Renovation of existing space (low risk).
Construction planned in FY10 but can be advanced
if necessary. - Co-occupancy installation of technical
equipment prior to BO. - Turner activities have priority. Co-mingled work
is proceeding smoothly due to advance planning. - Track Turner EV in LCLS PMCS, site walk
validation, OAC meetings
14LCLS Procurements
- LCLS using co-located procurement group
- 1 Manager
- 2 Buyers (technical components)
- 1 Contract Administrator (A/E, CM/GC contracts)
- 1 Construction Buyer (Davis-Bacon contracts)
- Administer field changes and submittals
- 2 P/T Consultants (price and change negotiations)
- Weekly technical/procurement staff meetings
- Advance procurements monitored via APPs
- DOE increased SLAC authority to 500K
- Starting pre-planning of LUSI procurements.
15Recent Procurements gt100K
- Recent performance on estimating contracted work
has been good. - 11M of large procurements remain (4.5M Space
Renovation, 2.8M D/B FEH Hutches)
16Integration Management
- Integration Management Team (staff of 8)
- Directed by R Boyce
- Meets weekly to review interfaces, resolve gaps,
conflicts - Representation from all LCLS L2 WBS (includes
LUSI) - Monitor installation readiness, planning and
coordination - Design reviews continue to play important role in
advancing design and vetting integrated solutions - Risk Registry now mostly a tactical document
- Punch list managed by System Managers
- Often involves integrated mitigation actions
17LCLS Technical Specifications
- LCLS technical specs flow down from GRD-PRDs
- LUSI beginning to finalize its design specs
- LUSI interface captured in ICDs Interface
Working Group
18Project Management Risks Mitigations
- Safety Particularly construction and
installation - Fully staffed in ESH, construction safety and
oversight (UTRs) - Regular inspections, enforced procedures,
stand-downs, daily tool box meetings - Aligned DOE, SLAC, Turner, Jacobs, Subcontractors
- Cost Contingency
- Perform monthly analysis on EAC and projected
burn rate - Perform semi-annual contingency assessment MC
analysis - Cost Control (Owner-directed changes)
- Regular walk-arounds with IMT and LUSI teams
- Adhere to configuration controls (BCR, FCO and
DCR)
18
19Project Management Risks Mitigations
- Schedule Installation Coordination
- IMT facilitates integration and identify
gaps/conflicts - Weekly install meetings (w/Turner) readiness
reviews - Schedule FY09 Continuing Resolution
- Request 8.1M (5M above CR level) at beginning
of FY09 - Defer less critical work until later in FY09
- Evaluate cost and contingency monthly
- Management Transitions
- Actively manage organizational interfaces
- LCLS-LUSI, transition to Linac Ops, transition to
LCLS Science Program - Project transitions are high priority to DOE and
SLAC - Regular communication and access to key resources
- DOE-BES, DOE-SSO, SLAC Directorate
- System Managers will address their risks and risk
handling plans. - Full lists of active risks and mitigation actions
are LCLS Risk Registry.
20Summary
- LCLS reporting on recently revised baseline
- Overall, earned value making steady progress
- Milestone performance good so far
- Cost and schedule contingencies adequate to
address project risks - Monitor and manage FY08 contingency allocation
- Request 8.1M in Oct08 (5M above CR level) to
maintain schedule to early science - Challenges ahead
- Close out (Turner) construction project
- Simultaneously manage install/commission
activities - Continue LUSI integration and transition to
operations
21End of Presentation