Linac Coherent Light Source Status Overview - PowerPoint PPT Presentation

1 / 46
About This Presentation
Title:

Linac Coherent Light Source Status Overview

Description:

Linac Coherent Light Source Status Overview – PowerPoint PPT presentation

Number of Views:47
Avg rating:3.0/5.0
Slides: 47
Provided by: hel85
Category:

less

Transcript and Presenter's Notes

Title: Linac Coherent Light Source Status Overview


1
Linac Coherent Light SourceStatus Overview
  • John N. Galayda
  • Director of LCLS Construction

2
Construction 26 complete Contingency 29 of
Estimate to Complete
3
PROJECT INJURY EXPERIENCE TO DATE
Lost Time Injury Rate
  • SubContractors
  • 39 K Hours worked (05/31/2006))
  • Zero Injuries
  • LCLS Collaboration
  • 518 K Hours worked (05/31/2006)
  • Shoulder back strain
  • 24 Days Worked Without Injuries (05/11/2006)

Note Injury rates based on 200 K hours (100 man
years) of effort.
4
LCLS Project Organization (Mar06)
  • Feb06 Lehman committee recommended strengthening
    Project Office
  • APD Engr
  • APD Civil
  • Procurement
  • Continued strengthening of Conv Facilities
  • LCLS PMOG functioning

5
Injector and Linac
  • Injector 61 complete
  • Gun fabrication at SLAC- Hot test in ASTA bunker,
    August
  • Laser delivery in July 2006
  • Linac BC-1
  • Articulated vacuum chamber received
  • installation in Fall shutdown
  • Injector installation schedule runs into
    2006/2007 shutdown
  • Shutdown schedule 21 August 2006 to 5 January
    2007
  • In-tunnel work (BC-1) must have priority
  • Pursue all prudent means to speed schedule and
    preemptively mitigate schedule problems
  • Add design staff
  • Off-site fabrication, sources for rigging etc.
  • Commissioning start January 2007
  • Commissioning applications software will be
    rudimentary at start

6
Installation Schedule
6 MeV
250 MeV
4.30 GeV
13.6 GeV
135 MeV
Linac-X L 0.6 m
Linac-0 L 6 m
rf gun
L0-a,b
Linac-1 L ?9 m
Linac-2 L ?330 m
Linac-3 L ?550 m
25-1a 30-8c
21-3b 24-6d
...existing linac
21-1 b,c,d
undulator L 130 m
X
BC2 L ?22 m
BC1 L ?6 m
Wall region
DL2 L 275 m
Injector, 2006 down
Linac, 2007 down
SLAC linac tunnel
research yard
7
Status of Gun Fabrication and Testing
  • Gun machining and brazing in progress
  • Gun will be furnace baked after final tuning
  • Final braze of power splitter complete
  • Gun solenoid received, magnetic measurement plan
    completed
  • Test plan reviewed
  • Mechanical design of gun solenoid supports
    approved

Gun Solenoids
Dual Feed Full-Cell
8
Gun Fabrication in Progress
Cathode Plate (rear)
Dual-Feed Waveguide
Cathode Cell
Cathode Cell
Dual-Feed Full Cell
9
Readying Components for 2006 Down
Gun Solenoid
Injector Quadrupoles Shortened
Accelerator Sections
10
Commissioning
Begins after all components have previously been
installed, aligned, connected, and verified by
installers
  • Commissioning
  • Pre-Beam Checkout
  • Final component verification, made mostly in
    tunnel by system physicist (e.g., polarities,
    motion-control, etc.)
  • Systems validation (e.g., power supplies,
    software applications, etc.)
  • Beam Commissioning
  • Component and system verification/calibration
    with beam (hardware and software e.g., BPM
    tests)
  • Optimization of beam transport and tuning (e.g.,
    steering)
  • Characterization of beam quality (e.g., emittance
    meas.)

11
Commissioning Plans - Preparation
  • Plan development assigned to each system team
  • Drive Laser (White, Gilevich)
  • Gun Injector (Dowell, Limborg, Schmerge)
  • Linac (Emma, Wu)
  • Undulator (Nuhn, Welch)
  • FEL (Welch, Nuhn)
  • XTOD/XES (Arthur, Möller, Stefan, Tompkins)
  • Each developed an MS-Project file detailing both
    schedule and strategy
  • Goal was to force early development of tuning
    strategy (what to measure, what to tune, in what
    order simulations encouraged now)
  • Files now merged into master file and time-frame
    locked to project schedule (thanks to Jim Welch)

12
Machine Commissioning Plans
  • Schedule developed in MS-Project
  • One file/manager per system
  • Link to milestones and events in Master file

V\LCLS\Group\Commissioning\Commissioning
Schedule\Commissioning_Master.mpp
Injector-BC1
BC2
LTU-und.
install
install
Nov. 07
Dec. 05
Aug. 07
Mar. 08
Dec. 06
Aug. 06
13
SLAC-Wide Effort on LCLS Safety Assessment
Document
14
  • Preparations for Accelerator Readiness Review
  • Integrated with design review process
  • Component and System PDRs and FDRs are being
    conducted following LCLS guidelines.
  • Safety aspects are a normal part of the technical
    requirements.
  • Working to report safety analyses in a uniform
    way to facilitate future assessments.
  • SLAC Citizens Committees participate in the
    review process, following normal SLAC practice.
  • Citizens Committees involvement specified
    through the SLAC Safety Oversight Committee.
  • Need to ensure that all aspects of the project
    are reviewed, and that the completeness is
    presentable in a coherent way.

15
  • Accelerator Readiness Review
  • LCLS ARR for Injector Commissioning will take
    place Sept.- Nov. 2006, once Citizen Committees
    reviews are complete and the SOC is satisfied.
  • Working with the DOE SSO to ensure that the
    review process outlined here will be appropriate.

16
Undulator Systems
  • Undulator production underway
  • Prototype at SLAC for measurement
  • Chamber finish tests underway
  • Single Undulator Tests ongoing
  • RFBPM fabrication test encouraging
  • Undulator Measurements at SLAC
  • MMF startup in August

17
Undulator Systems
  • First Article Delivered to SLAC

18
Photon Beam Systems
  • John Arthur is staffing up
  • Deputy Hal Tompkins
  • X-ray Transport/Optics/Diagnostics
  • XTOD Liaison physicist- Peter Stefan
  • Prototype gas attenuator assembled, vac. tested
  • Design reviews for XRT vacuum, collimators
  • End Station Systems
  • Staffing up- Layout of experiments is settled
    down
  • AMO Liaison physicist John Bozek
  • Detector Liaison physicist - Niels van Bakel

19
X-Ray Transport/Optics/Diagnostics
  • Prototype gas attenuator cell tested at LLNL

20
NEH
AMO
X-ray pump-probe
SXR
soft x-ray line
hard x-ray line
Flipper Mirrors
21
FEH
XPCS
Coherent x-ray imaging
High energy density science
22
Sector 20
  • Beneficial Occupancy 21 April
  • Installation underway in vault
  • tray
  • supports
  • floor

23
Magnet Measurement Facility Beneficial Occupancy
14 April 2006
24
Final Focus Test Beam Cleanout
  • Phase 1 completed 28 April
  • preservation of technical components
  • Phase 2 began 1 May
  • removal of shielding blocks completed 2 June
  • Removal of cabling will be completed 16 June
  • Phase 3
  • Soils preparation for new Beam Transport Hall
  • Completion in July

25
Project Highlights and Key Considerations
  • Conventional Facilities
  • Architectural design _at_ 100
  • Drawings for construction in hand
  • 2- and 3- floor CLOC plans in hand
  • CM evaluating bids
  • Bids for first major packages in hand
  • Second group of bids due 21 June
  • Bid process for CLOC being accelerated

26
Cost Estimates for Civil Construction
  • Project budget based on three estimates of the
    T-II (60) design
  • Jacobs
  • Turner
  • Wightman (tunneling) Davis-Langdon(excl. tunnel
  • WBS unchanged when Jacobs/Turner 100 received
  • Bid process had started- wait/see real bids

27
Results of Estimates
28
Contingency Analysis from 7 February Lehman Review
29
First Bid Group Entire Beam Path
Bid Group 1 represents 68 of total hard cost
of LCLS CF. LCLS WBS Budget for total hard cost
of LCLS CF 67.3M Jacobs/LCLS estimate for
group 1 46M
30
Bid Group 1 Comparison to Turner 100 Estimate
  • Tunneling 194K (1) over estimate
  • Bid based on unit pricing
  • Estimates more transparent
  • Homework paid off
  • Survey, site utilities close to estimate
  • Fire protection 35(215K) above estimate
  • Earthwork 25 (1.2M) over estimate
  • Award these five packages ASAP

31
Bid Group 1 Comparison to Turner 100 Estimate
  • Concrete 6.1M (55) above estimate
  • Only two bids, 2nd bid nearly 10M higher
  • Relatively small number of companies have the
    capability to bid this kind of task (thick
    shielding)
  • Cost of concrete accounts for 500K
  • Bidder claims labor shortage, overtime
    inefficiency, higher qty. rebar than estimated,
    blah blah blah
  • Third quote competitive with lowest bid, but not
    bonded
  • Alternatives for re-bid under consideration
  • No low-risk path to re-bid has been identified
  • 2nd bid problematic
  • Turner team reluctance is evident
  • estimate 3 months to re-bid, 3 months added to
    construction

32
Bid Group 1 Comparison to Turner 100 Estimate
  • HVAC 4.2M (93) over estimate
  • Only 2 bidders, 2nd bid 3.1M higher
  • High effort assumed in bid (gt2X estimate)
  • Electrical 3.5M (48) over estimate
  • Only 2 bidders, 2nd bid very close
  • Cost of materials a factor
  • Labor hours estimate very high (as above)

33
Bid Group 1 Comparison to Turner 100 Estimate
  • Plumbing 2.0M (103) above estimate
  • Only 2 bids
  • Bid breakdown includes 3X estimated labor
  • 2nd bid 0.8M higher

34
Projection for All Awards
35
Actions Taken by LCLS and SLAC
  • Demand bid analysis by Turner, proposal of viable
    re-bid options
  • Appeal to Turners president was necessary
  • Lump-sum bids an accepted practice but details of
    cost estimate are difficult to extract
  • Demand conversion of Turner contract to make
    Turner execution of the CLOC an option for SLAC
  • Bring CLOC options to DOE status review

36
Turner Response
  • Options considered and pursued in parallel
  • Negotiate with responsive bidders
  • Quickly explore value-engineering ideas with goal
    to win back 5M-6M
  • Enlist Jacobs help in fast turn-around of ideas
  • Break-up of Concrete, Mech/Elec/Plumbing tasks to
    attract smaller firms
  • Breakout of retaining walls is straightforward
  • Propose a guaranteed-maximum price approach to
    CLOC

37
LCLS Recommended Path Forward
  • Keep Beam Path (electron beam, undulator hall,
    front end, Near Hall, XR tunnel, Far Hall) moving
    ahead as quickly as possible
  • Award Tunnel, Survey, Site Utilities, Earthwork,
    Fire Protection ASAP
  • Attempt to negotiate with low bidders-
  • Minimum recovery of 2M is expected
  • 6M is high end of realistic-
  • Do not consider re-bid unless strategy is clearly
    developed and believable

38
CLOC
  • Set budget target based on real bid information
  • Bid Group 2 due next week (partial response- 40
    higher than estimate)
  • Three options for acquisition of CLOC
  • Get bids for packages 34 ASAP (August?)
  • Turner considering a guaranteed-maximum price
    (GMP) contract to build the (2-floor) CLOC
  • Proposal from Turner by mid-July
  • Bid the CLOC competitively for results in
    September
  • Prepare for design-build-to-cost, reflecting the
    realities of LCLS budget as of September 2006

39
LCLS Project Options for CLOC
  • Today, options are heavily dependent on how one
    extrapolates from bid group 1
  • Continue targeting a 2-floor CLOC
  • Based on
  • 51 increase over estimate for Packages other
    than tunneling
  • 15 to go forward from award
  • 22 contingency for technical systems ETC
    2007-2009

40
Revised Estimate Based on Bid Package 1
  • For 2-story CLOC, 105.8M at award
  • Based on low bids in bid package 1 and
    proportional (51) growth in follow-on packages

41
Contingency Analysis, 2-Story CLOC
42
Design-to-Cost CLOC
  • Draconian economies required to maintain TEC
  • Delay start of CLOC until Spring 2007
  • Limits financial risk
  • Limits CLOC capability
  • 2-3 labs? severely limited office space
  • Preserves full performance of FEL

43
Design-to-Cost CLOC
Compare to 32.7M estimate contingency for
2-floor CLOC
44
Summary
  • Injector and Bunch Compressor 1 will be ready for
    commissioning in January
  • Preparations for commissioning the injector
  • Address engineering, physics, operations, safety
  • Undulator Systems Coming Together
  • X-Ray Front End design maturing
  • NO COMPROMISE to capability of FEL

45
Summary
  • Facing a very tough decision on CLOC scope
  • Financial impact versus CLOC functionality
  • Civil Construction organized, prepared to start
  • DOE/SLAC/LCLS must rapidly choose a course of
    action for CLOC construction

46
End of Presentation
Write a Comment
User Comments (0)
About PowerShow.com