Title: X-ray Overview


1
X-ray Overview
John Arthur LCLS Photon Systems Manager
  • XTOD current status
  • XES current status
  • Schedule to first experiments
  • Coordination with LUSI
  • Transition from project to facility
  • Beyond the LCLS baseline

2
Status in June 2008
  • XTOD is assembling instruments at LLNL
  • All mirrors have been ordered
  • Soft X-ray mirrors arriving meet figure spec
  • XES is working on final designs
  • Stoppers and doors are being built
  • 2d detector plan is updated prototype under test
    at Cornell, SLAC working on packaging and
    interface to DAQ

3
XTOD
4
X-ray front end
  • Front end X-ray optics being assembled at LLNL
  • Optics/diagnostics through preliminary or final
    design review

5 mm collimator
Soft X-Ray Offset mirror system
Hard x-ray Monochromator (K Spectrometer)
Gas Detector
Solid Attenuator
Direct Imager
Pulse Energy Thermal Detector
Slit
Hard X-Ray Offset mirror system
Gas Attenuator
e-
Gas Detector
Start of Experimental Hutches
Muon Shield
5
FEE Diagnostic Hardware Status
  • Fixed Mask / Slit
  • In house, Integrated testing
  • Attenuator
  • Under assembly
  • Gas Detectors
  • In house/integrating
  • Thermal Sensor
  • Vessel on order
  • Sensors in fabrication
  • Direct imager
  • Vessel on order
  • Cameras, scintillators, filters in house
  • K monochromator in final design
  • Pop-in Monitors in design
  • Controls
  • 4 of 5 FY08 FEE racks complete
  • FEE Vacuum Rack gt75
  • 98 of all other controls h/w received

6
The first SOMS mirror meets its specification for
long spatial period flatness
  • Total budget for long scale curvature is lt 20 nm
    tangential, lt 5 nm sagittal
  • - limits intensity asymmetry due to reflections
    to lt 10
  • Allocation to fabrication errors was 10 nm
    tangential, 4 nm sagittal
  • - contour plot shows SOMS 1 meets this
    requirement

Contour plot with 10x175 mm2 mask
9nm
Color map of 250x50 mm2 SOMS 1 figure
Figure, nm
0
Sagittal axis, mm
Tangential axis, mm
10
0
175
See detailed figure budget in ESD 1.5-122,
HOMS SOMS Opto-mechanical Design
7
Integrated EPICS control system under development
8
X-ray Endstation Systems
NEH nearly ready for occupants
9
XES Status June 08
  • AMO Instrument final design phase
  • Drawings gt60 complete
  • All ESDs are completed
  • Controls PDR 4/08
  • AMO Preliminary Hazard Analysis Document being
    finalized
  • Long-lead procurements starting
  • Mechanical Systems
  • PPS stoppers and hutch doors in fabrication
  • Ready for installation in 7/09
  • XES laser system
  • PRDs for Laser system and LSS completed
  • ESD for Laser transport controls 3/08
  • PDR for laser and transport system May 21
  • Quotes are in hand for tables and laser
    components
  • Laser SOP reviewed by LSO and LSC May 6
  • Installation
  • Cable plant are being designed, contracts are
    being placed

10
AMO Instrument
John Bozek jdbozek_at_slac.stanford.edu
11
AMO Schedule
  • Begin long lead procurements 5/08
  • Final Design complete 8/08
  • Procurements 10/08
  • Start Receiving hardware 12/08
  • Receive XES Laser 3/09
  • Install Laser 4-6/09
  • AMO Assembly and test 12/08 -- 4/09
  • Install AMO (phase 1) in hutch 5/09 6/09
  • Test AMO 7/09
  • Final readiness test 7/09
  • 1st x-rays to AMO instrument 7/09
  • AMO Phase 2 installed by 11/09
  • ? No float in schedule for early science in 7/09

12
Cornell 2D Detector
  • LDAC Review in May 08 showed good progress
  • Demonstrated a working bump-bonded detector
  • Detailed testing of chip is continuing
  • Go-forward plan is being reviewed
  • Integration with SLAC DAQ system
  • Mechanical packaging will be done at SLAC
  • Coordinated with CXI
  • Received bump bonded chip at SLAC in May 08
  • Delivery of Final Detector at SLAC in Spring 2009

13
Detector Mechanical Design Concept
Light shroud (cover removed)
Cooling coil
  • Quadrant board
  • Combines 16 ASICs
  • 1 FPGA/quadrant
  • Double detector package
  • 4 ASICs
  • 2 pixel array detectors

Martin Nordby, Matt Swift PPA Mech. Eng.
14
LCLS Installation and Commissioning Time-Line
First Light in FEE
FEH Hutch BO
First Light in FEH
PPS Cert. LTU/Dump
LTU/Und/Dump Install
CD-4 (7/31/2010)
X-Rays in NEH
FEE/NEH Install
FEH Install
PEP-II run ends
now
J
F
M
A
M
J
J
A
S
D
J
F
M
A
M
J
J
A
S
O
N
D
J
F
M
A
M
J
J
O
N
A
A
M
2008 2009
2010
Down
PPS
LTU/Und Comm.
Re-commission Inj/BC2 to SL2
NEH Operations/ Commissioning
Linac/BC2 Commissioning
FEE Comm.
April 18, 2008
15
Coordination with LUSI
  • Photon Systems working closely with LUSI
  • Both managed by J. Galayda
  • Close proximity in Bldg 280
  • Shared engineering/design resources
  • Interface Working Group meets bi-weekly
  • Formal relationship set by Interface Control
    Documents

16
Transition from Project to Facility
  • Responsibility for operation of LCLS instruments
    and LCLS X-ray science lies with the Experimental
    Facilities Division (XFD)
  • Head, responsible for User outreach Jochen
    Schneider
  • Deputy, responsible for LCLS science Jerry
    Hastings
  • Responsible for User operations John Arthur

Group includes Photon Systems and LUSI staff
(about 20 today) Growing quickly but thoughtfully
(hiring now)
17
Beyond the initial LCLS configuration
  • Policy for outside groups which propose to add
    instrumentation to the LCLS facility
  • Must offer a significant addition of general
    utility to LCLS
  • Must get support of LCLS (with evaluation by SAC)
  • Then group and LCLS negotiate with funding
    agencies
  • Then group and LCLS decide final layout and
    timeline, sign MOU
  • Some access priority can be negotiated, within
    limits which guarantee plentiful access by
    general users
  • All new instrumentation reverts to LCLS
    ownership/management after early operation

18
First example of addition to LCLS
  • SXR instrument Soft X-ray Materials studies
  • Consortium led by Anders Nilsson (SLAC/Stanford)
    and Wilfried Wurth (CFEL/Univ Hamburg)
  • Institutions Stanford, Univ Hamburg, LBNL, BESSY
  • Monochromatic soft-X-ray line to complement AMO
    line
  • No end station in initial configuration
    (consortium will loan)
  • Fast-track schedule operation in late 2009
  • Status preparing Design Report for LCLS review
    in July
  • If approved, get MOU by September

19
Where to put SXR?
Plan 1, with AMO in Hutch 2
Plan 2, moving AMO to Hutch 1
20
Summary
  • XTOD is building instruments at LLNL XES is in
    final design phase
  • This is a busy time for both groups
  • The schedule to reach early science in July 2009
    is tight, though risks to CD-4 milestones are
    very small
  • LCLS is transitioning from project to facility
  • SXR instrument is first example of a proposal for
    additional capability beyond LCLS baseline