Title: TRD Status Report
1TRD Status Report
AMS TIM CERN, 24-Apr-2006
Octagon Integration T. Siedenburg 20min DAQ
Electronics F. Hauler 10min Gas System
Electronics B. Borgia 20min
2Aachen TRD Status Report
- Th. Siedenburg
- AMS TIM
- CERN, 24-Apr-2006
3TRD Octagon Integration (Th.Kirn)
21-APR-2006
I. Özen
4TRD Octagon Integration
21-APR-2006
5TRD Octagon Integration
- All DALLAS temperature sensors tested
- All 82 flight frontend boards installed (UFE)
- HV ground connections installed
- UFE function tests in progress
- Gas-tower interconnection tubes installedTower
to tower finished next week - Gas-group cosmic tests in preparation
- TRD upper plate Installation of inserts
- STA M-Structure machined within specs.Test
mounting in preparation - TRD Rosengitter in preparationGastubing / Dallas
UFE cabeling
6TRD Longterm Test
2 Years
Gastightnessunchanged Gasgainstable
J. Hattenbach
7Final Report on TRD Front End ElectronicsUFE
(Flight Modules)Ch.H. Chung
8358 VA Chips Tests Select 202 Chips
101 Production of 4 Types PCB
Series of Space Qualification Tests
Functional Tests
TVT ? 3D Vibration ? Coating ? TVT
92nd TVT Same as 1st TVT condition
Conformal Coating
10(No Transcript)
11Pedestal RMS
1250 oC
-20 oC
13(No Transcript)
14ALL 101 produced UFEs within specificationsSelect
better UFEs as flight modules
15TRD-UFE (FM) Pedestal Distribution 10 of
full range
16TRD-UFE (FM) Noise RMS Spread 4
17TRD-UFE (FM) Gain RMS Spread 3
25oC
18UFE(FM) Production Finished (Jul. 2005)
Total 101 UFEs (FM 82, FS 19)
Functional Tests Finished (20.07.05)
UFE Space Qualification Tests (Mar.05 Mar. 06)
1st Thermal Vacuum Test 101 (Done w/o
failure) Random Vibration Test 101
(Done w/o failure) Conformal Coating
101 (Done w/o failure) 2nd Thermal Vacuum
Test 101 (Done w/o failure) ? Best 82 FM
selected (Mar. 2006)
UFE Integration Finished (Apr. 2006)
19TRD Gas Manifolds
- Distribute TRD gasflow into 41 segments
- Measure gastightness of individual segments
- Allow isolation of a segment when leaky
- Introduce no additional risk of gas leakage
20Manifolds mounted on Octagon
21OctagonTemperature Swing
30
R,P,Y hottest
OHB TRD Thermal Report 240 days (4 b
periods) eMLI 0.03 Average TRD
Temperaturebetween 35oC and -20oC Depending on
ISS R, P, Y
0
R,P,Y coldest
-20
22Manifold / Flipper Valve Schematics
FVb
FVa
23Improve Manifold Leaktightness
FVb
FVa
24New Manifold Prototype
? Dry mounting of all components? Full function
test? Potting when ok
Alu. Body
Viton Seal
Alu. Cover
25New Manifold Design
26New Manifold Design
Fits inside existing magnetic shielding
Gas connectionswith double-o-ringfront access
27Cold Case Flipper-Valve Operation
Leakage to outside if switched below -8oC
No switching below -15oC
Buerkert 6124
Flipper-Valve Temperature
TVT Tank Vacuum
Viton Bag
28Manifold operation heated switching
Switching in TVT at -25oC ok if valve heated
to 0oC Heating of fully potted 2FV manifold 2 x
2W x 30 min. Gastightness through valves and to
outside ok Heater powerline control (8H8C 40W
each) TBD
SMD 100W
29TRD Integration Schedule
Octagon Integration finished in May
06Rosengitter tubing cabeling Jun - Sep
06Manifold design production Apr - Oct
06Box-S/C EM -gt QM upgrade Apr - Jul
06UG QM Electronics Prod. Test Apr - Oct
06Box-S/C FM Prod. Test Apr - Dec
06TRD Cosmics EM UGcrate _at_ RWTH Nov - Dec
06TRD Cosmics QM UGcrate TBD Jan - Mar
07UG FM Electronics Prod. Test Oct 06 - May
07
30TRD Integration Schedule I
31TRD Integration Schedule II
32TRD Integration Schedule III