Title: Thermal Control System Status Report
1Thermal Control System Status Report
- J. Burger, H. Hofer,
- L. Cheng, M. Molina
2AMS02 Thermal System
- J. Burger Introduction (Organization, Quality
Control and Schedule) - L. Q. Wang Shandong University Responsibilities
- M. Molina Technical Update
3AMS02 Thermal Organization
AMS Overall Thermal System Coordinators ETH H.
Hofer, MIT J. Burger, SDU L. Cheng, NSPO J.R.
Tsai CGS M. Molina, OHB R. Schlitt
Subsystem Thermal Organized by Subsystem
Coordinators
AMS Collaboration Spokesman S.C.C. Ting
Electronics M. Capell CGS M. Molina NSPO J.R. Tsai
TRD S. Schael, K. Lübelsmeyer OHB R. Schlitt
Magnet Cryocoolers H. Hofer GSC S. Breon
RICH G. Laurenti CGS G. Sardo
Subdetector Thermal Groups
Tracker R. Battiston, M. Pohl NLR M. Brouwer
J. van Es NIKHEF B. Verlaat Zhongshan U. Z. He
TRD Gas System U. Becker LMSO C. Clark CGS M.
Molina
ECAL F. Cervelli CGS M. Cova
ToF G. Laurenti CGS C. Vettore
Thermal Subsystem Safety and Interface to ISS and
STS Organized by subsystem coordinators and
reviewed every three months by NASA MMO at KSC,
JSC or CERN
NASA MMO LMSO C. Clark USS2, Vacuum Case And
Safety
NASA MMO Mission Manager S. Porter
4AMS Overall Thermal Control System Organization
PM H. Hofer (ETH-Z) Technical Responsibles J.
Burger (MIT) L. Cheng (SDU) J.R. Tsai (NSPO)
AMS Experiment
Thermal Contractor Carlo Gavazzi Space
5 OHB System, Bremen Design and Manufacturing
6QUALITY ASSURANCE / PRODUCT ASSURANCE
- For cost reasons, we have included a limited set
of quality assurance documentaion in the contract
with CGS, which is sufficient to assure us of the
safety and reliability of the thermal control
system
7(No Transcript)
8(No Transcript)
9AMS-02 Thermal testing
10Structural tests
- An STA of the radiatorscrates will be delivered
to LMSO/NASA for static and modal testing.
11SDU visit to CGS-Milano26th April 2004
- Prof. CHENG Lin
- Prof. LI Kang
12(No Transcript)
13(No Transcript)
14Areas of collaboration between SDU and CGS
- Presented by Prof. L. Q. WANG
- Shandong University
15Thermal activities
- Wenjing DU and Gongming XIN have come to CERN for
a three-year period. - They will translate the Thermal Mathematical
Model of the Large Solar Simulator (provided by
ESA in ESATAN format) to the standard format for
AMS thermal modelling SINDA. - Together with CGS they will develop test plans
and test predictions for the AMS Thermal-Vacuum
test.
16(No Transcript)
17Mechanical design
- A mechanical engineer, starting Fall 2004, will
support the design of - Structural Test Article (making simpler the
original Radiators crates design) - Together with CGS
- Support Stand for Thermal Vacuum Test at ESTEC
- Together with R. Becker
18STA manufacturing
- In order to test the data exchange between CGS
and SDU, a 3-D CAD model of an upper bracket of
the radiators has been sent to SDU in various
formats. - Manufacturing drawings have been sent as well
19MAIN RADIATOR UPPER BRACKETS
UPPER BRACKET
20- First specimen of the upper bracket is delivered
to CGS for dimensional and tolerances control. - Next step will be getting certified Alumimum
alloy bare material for building a flight-like
bracket.
21Loop Heat Pipe Life Test
- SDU will perform a long-duration test of the LHP
with one quarter of the Zenith radiator. - Performances of the LHP will be monitored over a
2 years timeframe.
22(No Transcript)
23A short break influence of initial condition and
disturbances
24(No Transcript)
25Temporal periodic oscillation
Typical secondary flow patterns in one period of
temporal periodic oscillation from solution at
Dk 300 on A1-1
26(No Transcript)
27 28AMS TCSTechnical report
29TV/TB test _at_ ESTEC
30 31AMS-02 level TV Test objectives
- Functional performance verification under thermal
vacuum conditions - Magnet charge and discharge phases
- Functional performance at room temperature is
already tested during assembly - Verification that no degradation occurs during
and after test - Verification of the Thermal Control System H/W
performance - heaters power consumption (i.e. duty cycles) and
thermistors/thermostats settings - radiators effective heat rejection capability
- Loop Heat Pipe performance
- Tracker Thermal Control System Performance
- Partial verification/validation of the AMS-02
thermal mathematical model - Verification of the thermal interfaces
- Optical properties validation
- Validation of the (thermal) hardware workmanship
- MLI effective emittance
- Thermal filler
32General thermal test requirements
- AMS-02 shall follow a complete test program,
including - Thermal Vacuum
- Thermal Balance with Solar SimulatorÂ
- Shroud temperature range from -170C to 50C
TBC - Working Pressure 10-5 torr
- Need for a dedicated line for the He venting
33Test sequence - schedule
- Installation and check-out 3 weeks
- Estimated duration of the test 6 weeks
- De-installation and visual inspection 1 week
- Shipment 1 week
- 3 months are allocated in total, 1.5 of which
inside the LSS
34Input needed from ESA to the AMS Collaboration
- Mechanical I/F to the LSS, for appropriate MGSE
design - (DELIVERED 3rd July 2003)
- Thermal LSS model for test prediction
- Support for thermal model use, during test
predictions. - Preparation to start in 2004
35Cryocoolersand Zenith Radiator
36LHP Zenith radiator system
37- Zenith Radiator- sandwich layout
- face sheet 1 t1,8mm Al core t10mm Rohacell
51WF - face sheet 2 t0,3mm Al
-
38TYPICAL ORBIT, SILVERED TEFLON
- Beta 25 is the typical orbit for
cryocoolers - It is the orbit that represents the averaged
temperature over the year - Silvered Teflon coating was considered on
radiator to enhance its thermal performance.
39Beta -25 (TYPICAL)
40(No Transcript)
41(No Transcript)
42AMS-02 Thermal analysis
43Launch to Activation SequenceAnalysis
- STS free flying
- AMS-02 in Cargo Bay with STS docked to the ISS
- AMS-02 in Hand-off position with STS docked to
the ISS - AMS-02 on ISS truss
441. STS free flying
452. AMS-02 in Cargo Bay with STS docked to the
ISS
463. AMS-02 in hand-off position with STS docked
to the ISS
474. AMS-02 on ISS truss
48Orbits Analyzed
49Power Profiles
50Heaters
51(No Transcript)
52More heaters needed
- HV Bricks
- E-crate
- ECAL, RICH, LOWER TOF
- TRD
53LTA (Launch-To-Activation)Temperature
distributions
541. STS free flying
55(No Transcript)
56STS free flying
572. AMS-02 in Cargo Bay with STS docked to the
ISS
58(No Transcript)
59AMS in Cargo Bay, STS docked
603. AMS-02 in hand-off position with STS docked
to the ISS
61AMS in Hand-off position (2 hours OFF)
62(No Transcript)
63AMS in Hand-off position (6 hours partially ON)
644. AMS-02 on ISS truss
65(No Transcript)
66Power Outage Scenario
67Configuration
- AMS-02 mounted on the ISS
- AMS-02 power completely OFF
- Initial conditions for the transient
- Steady state solution with AMS-02 powered
68Orbital cases for cooling down
- Worst cold orbit for the detectors
69Results
70(No Transcript)
71(No Transcript)
72HIGH VOLTAGE BRICKS
73The Brick (prototype from INFN -PI)
74Introduction
- 6 Ecal bricks (EHV) mounted on the lower USS
- 4 Rich bricks (RHV) mounted on the lower USS
- 4 Tof bricks (SHV) mounted on the main radiators
75Bricks location and numbering (1/2)
SHV
RAM
WAKE
2
4
1
3
76Bricks location and numbering (2/2)
RHV EHV
77Temperature requirements
- Operational -20C 60C
- Non operational -40C 70C
Power dissipation
- EHV 6.45 W
- RHV 4.35 W
- SHV 5.8 W
78Preliminary mechanical design
Mechanics weight 1.2 kg ( bolts)
79Exploded views
80Accommodation on lower USS
81Thermal control concept
- Bricks insulated from USS by means of Zirconium
oxide washers - Rationale USS too cold in worst cold cases
- Bricks thermal control by radiation
- White painted aluminum radiator 1.5 mm thick,
green in the picture - Side walls (orange in the picture) auxiliary
radiators - Locally applied MLI, depending on the HVbrick
location
82Analysis worst cases
- STS free flying Beta 60, -Z solar inertial
- STS docked B0 and 60, YPR0,0,0
- Transfer B60, YPR0,0,0
- Switch on B0, YPR0,0,0
- Cold operational on ISS B0, YPR0,0,0
- Hot operational on ISS B-75, YPR-15,0,0
- Heaters failure B-75, YPR-15,0,0
- Cooling down (power outage) B 0, YPR0,0,0
83STS free flying
Coldest brick RHV 3 Minimum
temperature -37.7C HEATERS APPLIED 5W
84STS Docked
Coldest brick RHV 3 Minimum
temperature -29.4C HEATERS APPLIED 5W
85Transfer
Coldest brick EHV 5 Minimum
temperature -32.8C HEATERS APPLIED 7W, then 0W
86Switch ON on ISS truss
Coldest brick EHV 4 Minimum
temperature -20.0C (avg.) HEATERS APPLIED 7W
87Cold operational (RHV)
Coldest brick RHV 3 Minimum
temperature -18.9C Nominal dissipation 4.35W
88Cold operational (EHV)
Coldest brick EHV 6 Minimum
temperature -18.0C Nominal dissipation 6.45W
89HOT operational (RHV)
Hottest brick RHV 4 Maximum
temperature 53.8C Nominal dissipation 4.35W
90HOT operational (EHV)
Hottest brick EHV 4 Maximum
temperature 57.9C Nominal dissipation 6.45W
91Cooling down (power off)
Coldest brick EHV 6 Minimum
temperature -35.1C No heaters,No internal
dissipation
92CAB thermal design status
93CONCLUSIONS FROM THE MEETING AT CRISA (30/7/2004)
- CRISA refined Thermal reduced model, providing
one node on the baseplate per module - CAB has a single Thermal interface the
baseplate, to be kept below 50C
94CAB Thermal CONCEPT
3 (TBC) HPs connected to the CAB baseplate and on
the radiative side of the WAKE radiator (6WK-1)
95New reduced model
- Delivered 5 July 2004
- Model debug
- definition of dissipation profile
- ? Integration of debugged model 14 July 2004
- Number of nodes used
- NEW model 19 nodes for each external box side
- OLD model 1 node for each external box side
96CAB RAMP UP power profile
97CAB Thermal NEXT STEPS
- Number of HPs to be defined
- Heat pipes length
- Conceptual Thermal Design will be completed mid
September - When Thermal will be OK
- Structural analysis
- Thermal analysis on CRISA detailed model
98Structural analysis
99Design and test procedure of glued sandwich
inserts.
100Insert Design
101Test Plan
102Shearing Tests Set Up
103Tension Tests Set Up
104Shearing Tests Results
105Tension Test Results
106MAIN RADIATORS FE MODEL
107WAKE RADIATOR
Radiator Panel ROHACELL Al 2024 T81
BOLTS (A286 160 KSI)
Upper bracket (Al 7075 T7351)
XPD (Al 7075 T7351) (FR4)
Mid bracket (Al 7075 T7351)
Links (Al 7075 T7351)
Lower Rod (Al 7075 T7351) (steel)
CRATE (Al 7075 T7351) (FR4)
PDS (Al 7075 T7351) (FR4)
108RAM RADIATOR
Radiator Panel ROHACELL Al 2024 T81
BOLTS (A286 160 KSI)
XPD (Al 7075 T7351) (FR4)
Upper bracket (Al 7075 T7351)
Links (Al 7075 T7351)
Mid bracket (Al 7075 T7351)
CRATE (Al 7075 T7351) (FR4)
Lower Rod (Al 7075 T7351) (steel)
109RAM Radiator mode 1 at 26.64 Hz
110RAM Radiator mode 2 at 34.67 Hz
111Deformation Load case 1023
112Static Analysis
Top bracket plate
Load Case 4032, Layer Z1
Load Case 4032, Layer Z1- detail
MoSu0.07
113Static Analysis
Mid bracket plate
Load Case 4042, Layer Z1
Load Case 4042, Layer Z1 - detail
MoSu0.17
114Static Analysis
Lower bracket plate
Load Case 4012, Layer Z2 - detail
Load Case 4012, Layer Z2
MoSu1.85
115Static Analysis
Crate structure plate
Load Case 4042, Layer Z1 detail
Load Case 4042, Layer Z1
MoSu0.67
116Static Analysis
XPD structure plate
Load Case 4009, Layer Z1 - no lug - detail
MoSu1.91
117Structural analysis closed actions
- Updated analysis using new loads
- Bolt analysis corrected as requested
- Buckling analysis updated
- Fail safe analysis
118(No Transcript)
119Conclusions
- Main Radiator Structure is compliant with the
requirements - The 1st natural frequency of the RAM Radiator is
26.66 Hz - The 1st natural frequency of the WAKE Radiator is
25.76 Hz - All MoS are positive for all applied loads
- The lowest MoS is 0.07 on the top bracket
- Stress verification performed
- Joints verification, both nominal and fail safe
configuration, performed - No buckling is present under applied loads.
- EVA induced loads lead to negative MoS on Zenith
radiator
120IMPORTANT DATA needed for the Delta Thermal CDR
- Tracker Thermal Control System analysis
(RE-)START - CAB mid September
- LOWER TOF Thermal design
- ICD issue 4 End September