Title: TPC Status Report


1
TPC Status Report
Project leader Peter Braun-Munzinger, GSI
Darmstadt Deputy project leader Johanna
Stachel, Heidelberg Technical coordinator
Peter Glässel, Heidelberg
2
Outline
  • Summary of Pre-commissioning
  • OROC 00 exchange
  • Noise study
  • Last round of FEE testing
  • TPC/TRD heat screen
  • Transport of TPC
  • Insertion of TPC into SF
  • Commissioning
  • Activities parallel to ITS installation
  • Final commissioning in situ

3
OROC exchange
  • Broken anode wire in OROC 00
  • Clearly caused by melting
  • It is still unclear, how this can happen
  • Studies with a test sector in preparation
  • Mounting tool modified
  • longer lever due to presence of SSW
  • Complicated procedure, it required
  • Removing FEE and frames of full sector
  • Exchange of feet of FEE frames of neighboring
    sectors by smaller versions to allow removal of
    sealing bars
  • Remove pt1000 sensors on ROC body
  • Yellow platform in modified setup (cope with
    I-bars)
  • Exchange itself without any problems

4
Sealing bars close to FEE frames
  • Removal of bars conflicts with feet of FEE frames
  • Feet exchanged by modified ones

5
ROC exchange
310 mm more
6
OROC A00 exchange
7
Optimizing OROC Noise
  • OROC corners were known to show higher noise,
    typically up to 5 ADC cts with the grounding
    scheme as tested in the lab.
  • In the lab never tested with all FEC installed
  • IROCs dont show corner noise
  • Study optimizing the grounding scheme on one
    sector
  • New scheme
  • 18 thicker grounding cables in the OROC edges
  • 8 cables omitted in center
  • noise reduced to center value for random signals
  • Test of this optimized scheme on another sector
  • Implementation in a 2-day heroic effort of
    Lucianos team

8
Original grounding scheme
Pedestal Measurments noise
9
Original grounding scheme
Optimization of the ground scheme
10
New grounding scheme, all signals in phase
Optimization of the ground scheme
  • thicker ground cable (6mm copper braid) on
  • rp6, FECs 0, 1, 2, 3, 8, 9, 10, 11, 16, 17, 18,
    19
  • rp5, FECs 0, 1, 18, 19
  • rp4, FECs 0, 19
  • no ground cable on
  • rp6, FECs 4, 5, 6, 7, 12, 13, 14, 15

11
New grounding scheme4 signal groups with 90 deg
phase shift
Optimization of the readout scheme
12
IROC/OROC noise comparison
Noise of the whole sector final ground and
optimized readout
13
TPC/TRD heat screen installed
  • Except for some panel at bottom for ITS entry

14
Getting the TPC travel-ready
  • Last leak tests on cooling system (ROC, FEE, SSW
    covers, inner heat screen
  • Last cabling items
  • Last dry test of FEE of all sectors after
    closing with cover (lt10 min without cooling)
  • Store cables on TPC (DDL and pulser cables are
    quite long) to allow moving out of DF
  • Packaging
  • Heating and temperature monitoring system
  • Acceleration monitoring (Michael Guinchard).
  • Disconnect from gas system, purge from CO2 / N2
    bottle
  • Ready before Christmas

15
Transport to UX2
  • Complicated for two reasons
  • Allowed deformation of the DF lt3mm
  • Two TPC feet kept floating on hydraulic jacks to
    ensure NO deformation of TPC
  • Limit of movement TPC vs SSW 3mm (FEE cables to
    ROC)
  • Lowering onto four posts always with coupled
    hydraulics
  • Clearance of DF to ground on crane in SXL2 not
    sufficient for trailer ? intermediate position on
    ground with hydraulics for lifting to trailer
    height
  • DF deforms easily if not supported level ? manual
    corrections during trailer transport

16
Trailer transport SXL2 to SX2
17
Trailer transport SXL2 to SX2
18
Descend to the cavern
  • 2 hours for descent

19
TPC insertion into SF
40 cm to IP
  • Test-drive with TPC to IP
  • Align TPC, SF, ITS rail sys at IP
  • Back to parking position
  • Window of about 2 weeks
  • Check alignment SSW vs TPC
  • Re-test all FEE (all sectors)
  • Installation of beam line and ITS

at IP
20
Inside heat screen on ITS platform
21
Activities during ITS installation
  • Installation and tests with DCS
  • power supplies (LV, HV)
  • Gate pulsers
  • Calibration pulsers
  • Cooling system (testing with 2 dummy sectors in
    situ)
  • Prepare 100 kV cable

22
Commissioning in situ
  • After ITS installation end (scheduled for
    24.5.07)
  • Starting on C-side
  • Connect C-side services to Back frame
  • Re-commission gas system (temporary services on
    A-side)
  • ACORDE and laser triggers
  • Connect 100 kV drift HV
  • Commissioning A-side has to wait for Miniframe
    (Jul 07)

23
Summary
  • TPC in good shape before transport
  • Transport to UX2?
  • Insertion into SF ?
  • ITS installation next
  • Access for TPC tests before ITS arrives
  • Preparations for commissioning in situ started
  • On schedule

24
-- Spares --
25
TPC/TRD heat screen