AMS 02 THERMAL CONTROL SYSTEM Status report - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

AMS 02 THERMAL CONTROL SYSTEM Status report

Description:

Main radiators MID BRACKETS. AMS 02 TIM. CERN, 2nd April 2003. AMS 02 Thermal Control ... Goal = get the inputs and release issue 5 of Thermal ICD by Mid May 2003 ... – PowerPoint PPT presentation

Number of Views:90
Avg rating:3.0/5.0
Slides: 36
Provided by: marcom8
Category:

less

Transcript and Presenter's Notes

Title: AMS 02 THERMAL CONTROL SYSTEM Status report


1
AMS 02 THERMAL CONTROL SYSTEMStatus report
2
OPEN ISSUES FROM THE JANUARY TIM1) TRACKER
RADIATOR2) ZENITH RADIATOR
3
(No Transcript)
4
Flat Radiator (1.6 m2) Jan 2003
WAKE
RAM
5
Flat Radiator (78 area)
WAKE
RAM
6
Flat Radiator (78 area)
7
TRACKER RADIATORCDR BASELINE (78 area)
8
Tracker radiators for CDR
  • Area1.26 m2
  • Mass2 X (13 Kg 5.5 Kg for the brackets)
  • 2 condensers per radiator
  • Tracker nominal dissipation 144 W (was 192 W)
  • Nominal mass flow rate 3 g/s
  • Pre-heating power 50 W

9
Curved Radiators
WAKE
RAM
10
Curved Radiator
11
Beta 0-2-101_hot
12
Beta 75-15-20-15_hot
13
Zenith radiator
14
CRYOS radiator 4.8 sq(m)
CRYOS radiator 4.1 sq(m)
15
Zenith radiator

16
6 Samples
17
Radiator Position Relative to AMS02 Coordinate
System (Position is presently 1613,3 mm. Should
be 1600 mm)
18
MAIN RADIATORS
19
Main radiators MID BRACKETS
20
Softer mount larger enforced
displacements Stiffer mount
smaller enforced displacements
21
MID BRACKET CDR
  • Current design shows negative margins
  • Updated FEM model was sent to LMSO to generate
    new I/F displacements (current loads are based on
    out-of-date model and could be too cconservative)
  • Direct attachment to the crates columns under
    evaluation

22
(No Transcript)
23
MID BRACKET CDR
  • Current design shows negative margins
  • Updated model was sent to LMSO to generate new
    I/F displacements (current approach too
    conservative)
  • Direct attachment to the crates columns

24
Heat Transfer Areas between CRATES and Face Sheet
WAKE
RAM
25
Heat Pipe Layout CRATES RAM Radiator
26
Heat Pipe Layout CRATES WAKE Radiator
27
RECOMMENDATIONS
  • To improve the thermal perfomance of the
    radiators vertical heat pipes will be considered.
  • This choice is partially affecting the
    possibility to test the system on ground
  • hottest levels will not be tested in
    Thermal-Vacuum test

28
TURNING ON AMS (activation sequence)ANDHEATERS
29
Heaters architecture
WAKE
RAM
Zone heaters 7
Zone heaters 4
Zone heaters 1
Tracker Radiator
Feed A
Main Radiator
Zone heaters 8
Zone heaters 5
Zone heaters 2
Feed B
PDB
Available heater line
Rich/Ecal Radiator
Zone heaters 9
Zone heaters 3
Zone heaters 6
30
AMS installation on the ISS
  • AMS is removed from Shuttle cargo bay by a
    robotic arm.
  • During the transfer phase to the ISS, it will be
    powered (1800 W available) through the robotic
    arm grapple fixture
  • As soon as it gets installed on the ISS, the
    following activation steps are foreseen

31
Heaters Operational Sequence(PDB heaters and
Zone heaters)ON THE ISS
  • Start assumption we are at -40C
  • 1) PDB heater ON
  • 2) When T(PDB)gt-25C
  • gt PDB ON (assumption 150W dissipated for
    heaters feeding)
  • gt Zone Heaters ON

32
Tot900W
33
Tot900W
34
Tot1800W
35
Tot1800W
36
Operational heaters
  • DEDICATED HEATERS LINE (fed at 120V DC) are
    currently foreseen for some subdetectors
  • TRD GAS BOX
  • 6 W 50 W
  • TTCS
  • 100 W
  • CAB?
  • LOWER TOF?

37
Does anybody else need heaters?
  • This is the right time to ask for!

38
Who is responsible for MLI?
  • CGS
  • Radiators backside (Tracker, RAM, WAKE, RE)
  • Cryocoolers
  • LMSO/NASA
  • Vacuum case (external side, flanges, upper and
    lower skirts)
  • Tracker upper and lower Tracker group
  • TRD lateral
  • RICH Mirror
  • ECAL bottom
  • RWTH Aachen
  • TRD-zenith radiator
  • Below TOF
  • INFN BO
  • RICH-ECAL

39
Thermal ICD
  • New issue of the Thermal ICD needs urgently
    inputs from the following people

A.Woering- M.Capell- M.Pohl- B.Verlaat- A.Posada
J.Ulbricht- R.Henning- L.DeFranchis- G.Viertel
W.Wallraff- P.Nemeth- P.Trampus- HPVonGunten
C.GargiuloG.Laurenti- J.L.Issler
  • Goal get the inputs and release issue 5 of
    Thermal ICD by Mid May 2003
  • If on the list you will be contacted

40
Schedule
  • Thermal CDR September 2003
  • STA manufacturing start November 2003

41
BACKUP SLIDES
42
Weight update
43
Thermal control structure mass budget(total
was 310.9 since January 2002)
44
Radiator Section with Main Dimensions
45
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com