Title: TRD Status Report
1TRD Status Report
LHCC Comprehensive Review, 20-21 March 2006,
Johannes P. Wessels Univ. of Muenster
Project leader Johanna Stachel,
HeidelbergDeputy project leader Peter
Braun-Munzinger, GSITechnical Coordinator
Johannes P. Wessels, Münster
- brief overview
- chamber production
- status
- super module
- insertion tests
- design
- integration of services
- services
- electronics
- PASA - pre-amplifier
- TRAP - digital chip
- system integration MCM readout boards
- detector control system
- summary
- milestones
2Transition Radiation Detector (TRD)
- Purpose
- electron ID in central barrel pgt1 GeV/c
- fast trigger for high momentum particles
- Parameters
- 540 modules -gt 760m2 (50 funded)
- length 7m
- anticipated X/X0 15
- 28 m3 Xe/CO2 (8515)
- 1.2 million channels
- Institutions
- Athens, Bucharest, Darmstadt, JINR,
Frankfurt, GSI, PI Heidelberg, KIP Heidelberg,
Cologne, Karlsruhe, Kaiserslautern, Münster, Worms
3Chamber Production
- stable production at 4 sites (Bucharest, Dubna,
GSI, Heidelberg) - Frankfurt ramping up production - started in fall
2005 - since decision for Layer 0 swift procurement and
production (completed for first super module) - noticed problem with insufficient surface
resistivity of AW106 glue after curing (large
dark current)traced back to change in the
manufacturing process of the gluecorrective
action additional cleaning step with ethanol
after curing
4Leakage Current Path
backpanel
pad
anode plane
cathode plane
drift space
glue
TRD radiator
5Surface Resistivity
Chr. Schmidt, GSI
6ROC production status
C. Adler, Heidelberg
Status 25.2.06 Bucharest Dubna Frankfurt GSI Heidelberg Sum
taped  2 2 5 5 14
tested taped 2 Â Â 13 2 17
glued (under testing) 1 2 Â 1 2 6
tested glued 36 33 Â 40 21 130
to be repaired  5  3 2 10
Sum 167(10) 62(66) of TRD
since Christmas 40 additional chambers
completed global production rate 6 chambers/week
7TRD rail system in space frame
- self-locking rail system installed, aligned
in SF - different types of rails depending on
position - clearances checked
- final adjustment after SF installation in
magnet (April)
8(No Transcript)
9Super Module Production Status
V. Chepurnov, JINR B. Windelband, HD, W.
Verhoeven, MS
-gt all pieces finished for first super module -gt
first assembly of super module mechanics
successful in February 06
10First Super Module Assembly
11Mounting L0 Chamber
12Full Length Assembly
13Super Module Service Sides
A-side
gas cooling
C-side
LV power detector control high voltage
readout fiberspre-trigger boxDCS power
14Super Module Installation
15SM and Manipulator
16SM Insertion into Manipulator
Manipulator adaptedto final super
moduledimensions
Insertion test at CERN scheduled for April/May
06progress according to schedule
17Bus Bar Layout
Chr. Lippmann, GSI K. Oyama, HD
- capacitors added
- design successfully tested
- producer identified
- order for first 2 SM placed
18Cooling
A. Marin, GSI B. Windelband, HD
- 65x10x2mm manifolds under construction for first
layers - directly mounted on bus bars
- delivery of all pipes for 50 TRD, 65x8x1mm end
of April
- cooling plant construction well under way
- commissioning will follow installation of first
super module(September)
Cooling pipes
19Layout of cooling meanders
N. Heine, MS A. Marin, GSI
readout chamber
readout board
cooling pathon MCMs maximized 90mm
DCS
ORI
detectorcontrolsystem
optical readoutinterface
20Production of cooling meanders
- thermal contact epoxy loaded with Al powder
(plate-meander) - Thermaglue - heat conducting silicone between
plate and MCM - tools ready for production (8/RoB)
- material in hand for 1st super module
- 20 of meanders finished
- manufacturer identified
- material on order for 50 TRD
-
21Temperature Distributions
?T20 K
temperature profile for differentload
conditions on 2 ROBs all sensors exhibit
similarprofile
22Gas System
C. Garabatos GSI R. Stadler, HD
- production and commissioning schedule fixed with
gas working group (contingent on delays in other
systems) - on-detector pipe layout finalized
- small reliable bubbler designed and tested
- Sep/Oct 06 - commissioning with Ar
- Nov 06 - commissioning of purifier and membranes
- Dec 06 - closed-loop operation possible
- April 07 - full commissioning with Xe (analysis,
recovery)
23Recovery Plant / Monitoring
- ALEPH recovery plant relocated, needs to be
re-commissioned - compressor unit for recovered gas still to be
designed and produced
drift velocity monitor under test
24PASA Overview
H.-K. Soltveit, HD
PASA productionfinished125,000 chipstested
(almosttwice as many asneeded) yield 99
Microscope
Control area
Chuck, needle card, needle card adapter and wafer
Main PASA tester
25TRAP Overview
- wafers from 2 engineering runs with good yield
( 80) - first production run poor yield ( 30) and
difficult to bond - corner run proposed by foundry
- received back in February ( 50)
- have enough good chips for first super module
- two further production slots reserved in 2006
(prices dropping significantly)
26TRAP Tests (Wafer/MCM)
V. Angelov, F. Ferner, D. Gottschalk, HD
- Power - reject chips with high currents
- Digital part
- Connectivity test using JTAG (MCM only)
- Contact resistances of some signals (wafer only)
- Internal tests using internal CPUs instruction
memories, data memory, configuration
registers, CPU registers, look up tables, digital
filters etc. - Test the readout-tree functionality
- Analog part
- internal pulser of PASA used to test ADCs (MCM
only) - Sine-wave test of 50 of ADCs on wafer (wafer
only) - Reliability test using different digital supply
voltages
MCM tester
needle card of wafer tester
27TRAP Performance
M. Gutfleisch, HD
- performs angle reconstruction
- good agreement with offline tracking
28MCM Production
Th. Blank, FZK
- originally FZ Karlsruhe as sole producer
anticipated - encountered bonding problems (bonder reliability
issues, contacts) - found alternative producer - attractive pricing
(MSC) (ROB producer) - optimized bonding procedure and balling of MCMs
- split contract between FZ Karlsruhe and MSC (50
TRD) - agreement to build 15000 modules at FZK
- 25000 modules at MSC (delivery schedule to be
settled end of March) - current production rate at FZK 800 MCM/wk (gt1
layer/wk) - yield 90 - FZK will complete 25 by April
- MCM production rate sufficient for ROB and SM
production
29ROB Test Setup _at_ HD
J. Mercado. HD
- ROB tests
- power consumption
- SCSN functionality
- internal TRAP
- tests
- IMEM, DBANK, DMEM, DIV, CJP,
- CST, PG, GIO, IRQ, LUT, EBF, Filters, . . .
- network interface test (read-out tree) via SCSN
30ROB Production/Test Status
I. Rusanov. HD Th. Blank, FZK
design finished - Nov 052 qualified offers - Dec
05delivery - Jan/Feb 06contract to be awarded
end of March
Origin Delivery ROB types Items Tested Good
FZK 12/2005 3A, 3B, 4A, 4B 19 all 18
FZK 19.01.2006 1B, 2B, 3A 18 all 16
Dommel 20.01.2006 2B 9 all 9
FZK 27.01.2006 1A 13 all 11
MSC 06.02.2006 1B 10 all 9
FZK 10.02.2006 all types 30 all 24
ROBs ready and tested as of Feb, 28 76 (2
layers) Yield 86
31Electronics Integration
Chr. Lippmann, GSI K. Oyama, D. Emschermann. HD
L0C1 003
- ROCs in various stages of completion
- assembly procedure documented
- knowledge base of errors (missing grounds, etc.)
- workload 2 person days / chamber
- one layer finished
in super module
32Noise Performance
Chr. Lippmann, GSI K. Oyama, I. Rusanov, HD
- Latest measurement ltRMSgt 1.17 LSB1230 e
- stable over many days
- with
- Wiener P.S. for ROBs.
- CERES P.S. for DCS.
- Power bus bar (C.L. type).
33High Voltage Master/Slave System
Athens University
Controls
6-ch. card / top viewauxiliary power supply box
34HV System Status
First system test at HD (Feb 23 - 25)- anode
voltages (2000 V) - 6 channels successfully
tested- stability 50mV- full command access
through CAN (and serial interface)- first PVSS
FSM functions error handling available -
primary HV supplies available for 12 super
modules To do - negative voltages (-3000 V)-
software regulation w/ 16 bit ADC _at_10-15Hz ?
5mV Goal- full test of 1st SM equipment at
HD/KIP (end of May)
35Detector Control System (DCS)
D. Gottschalk, K. Schweda, J. Mercado, HD M.
Stockmeier, R. Bramm, GSI
DCS Hardware Link http//www.kip.uni-heidelber
g.de/ti/DCS-Board/current/
- Each DCS board controls eight readout boards
- Monitoring functions
- temperature of MCMs
- currents of MCMs
- Control functions
- voltage regulator shutdown
- MCM configuration
- Clock and Trigger Distribution
- Optical Clock Receiver (TTCrx)
- Ethernet link
- JTAG in and JTAG out
- 8 analog inputs 16 Bit / 10Sps
- 8 Pseudo LVDS Inputs
- 8 Pseudo LVDS Outputs
- 24 Switching Lines
- two 8 Bit Ports (optionally)
- I²C Bus
- two-wire UART
- autonomous power supply
DCS interface functionality
36DCS Status
200 TPC DCS boards delivered by MSC 215 TRD DCS
boards expected end of March rest in April 120
TRD DCS boards programmed and successfully
tested PVSS control chain tested Database access
being worked on
37Optical Sender Status
V. Angelov, HD
- Test setup
- Read-out board
- ? Optical Sender Board
- ? 60m long fiber
- ? dedicated test receiver board
- ? ACEX PCI card software
- Latest test results
- Bit error rates below 10-12 (upper limit)
- Current stock
- 12 Optical Sender Boards built and tested
- components radiation tested - 2 weeks ago
ORI on ROB 3A/B
Optical receiver on the ACEX board
38TRD Trigger
J. DeCuveland, HD
Global Tracking Inside GTU (Global Tracking
Unit) Objective find high momentum
tracks Search for tracklets belonging
together Combine tracklets from all six
layers Reconstruct pt, compare to threshold and
generate trigger Constraintonly approx. 1.5
µs processing time
Charge Cluster to Tracklet Local tracking units
on detector perform linear fits and reject
uninteresting data
Tracklet(32-Bit word) y position
(origin) slope (deflection) z position
(pad-row number) charge
- Trigger decision after 6 µs
- Charge drift and data pre-processing uses most of
the time
39TMU Board Prototype Status
- basic PCB functionality successfully tested
- all supply voltages, oscillators
- configuration flash PROM, FPGA configuration via
JTAG - system monitoring and user I/O via I2C
- SFP module controlling via I2C
- multi-gigabit transceiver (MGT) operation shown
in principle - transmission between two GTU boards working (with
limitations) - known bug in Xilinx Virtex-4 FX60 engineering
sample-1 chips PLLs lose lock, need prototype
with ES4 chips - next to be tested
- SRAM
- CompactPCI interface
- LVDS to backplane
40TMU Design / Simulation
Reconstruction Precision
pt reconstruction precision 2.1
TMU Processing Time
Detection Efficiency
Simulation with Altera FPGA at 40 MHz Final
design using Xilinx Virtex-4 FX at gt 60 MHz
Simulations with AliRoot data, electrons with
pt gt 3 GeV/c
Results depend on multiplicity density dNch/d?
and number of tracklets delivered by detector
41TRD Pre-Trigger System
K. Oyama, R. Schicker, HD
- TRD pre-trigger wakeup signal sent to TRD
MCMs - generated by T0, V0 and TOF
- T0 Timing detector and M.B. trigger
- V0 Vertex detection and pp trigger
- TOF cosmic trigger and low multiplicity
(ultra-peripheral) - timing crucial ? system placed inside L3 magnet
- duplicated for fault tolerance
- functionality of pre-trigger system
- generates coincidence signal of T0, V0 and TOF
detectors - distribution of TTC signal from CTP and into
TRD TTC stream - provides TTC optical signals to 18 TRD
super-modules - generates control signals for FSM in MCMs
42Pre-Trigger Schematics
K. Oyama, HD
43Pre-Trigger Timing/Data Flow
44T0/V0 Pre-Amplifier Module
K. Oyama, PI Electronics Shop, HD
x10 output
x1 feed-through output
final design 55mm x 55mm 3 SMA connectors P0.5
W/ch
power
differential output to TRD pre-trigger system
input from the PMT
30 ps resolution achieved in test beam
experiment high ground and power stability
required circuit contains inductance - still
operational at B0.5 T
45Location of Pre-Trigger Components
inner bar (7m)
A
C
TRD
FEB
FEB
FEB
FEB
FEB
FEB
FEB
FEB
FEB
FEB
T0-C
T0-A
CB-C
CB-A
CB-TOF
TOF signals
46Prototype Control Board
K. Oyama, PI Electronics Shop, HD
all components will be locatedinside L3 volume
(back frame,baby space frame)
DCS board
47Detector Summary
- construction of TRD moving steadily ahead
- 5 sites working on chamber production
- excellent understanding of detector performance
from test beam data (6 NIM publications last
year) - rail system installed in space frame
- final alignment and insertion test (March-May)
- first assembly of super module structure
successful - integration ongoing
- first super module ready for installation in July
- looking forward to funding commitment for 100
inearly 2006
48Electronics Summary
- significant progress in electronics in 2005
- MCM production with good yield
- ROB production with good yield
- industrial producers identified
- full integration on chambers successful
49Milestones
- readout board start of production 07/05 done
- digital chip complete 07/05 production in
batches - MCM complete 11/06 following chip delivery
- readout board complete 12/06 as above
- GTU start production 06/06
- GTU complete 01/07 completed as needed
- chambers 50 complete 12/05 done
- chambers 100 complete 10/06
- start stacking super modules 11/05 done
- ready to install 1 super module 07/06
- start installation 1 super module 08/06
- installation of 2 super modules 03/07