Title: TRD Gas System CDR Report
1TRD Gas System CDR Report
- Reyco Henning
- MIT
- May, 2003
2Outline
- Functional Overview of TRD Gas System
- Mechanical Structure and Layout
- Components
- Functional Testing and Schedule
3TRD Gas System
Box S
Manifolds
TRD 300 Liters
Box C
Xe 1550psia
Mixing Vessel 200 psia
17.6-20.4psia
CO2 940 psia
Schematic Arrangement of the AMS-TRD gas
system. All pressures are given at 25 C.
4Xe
Box S Diagram
VG1a
RVG1a-2800psi
Ground Equipment
V17a
F3a
V1a
Va
V3a
V2a
F2a
O1a
Xe Bottle 1550psia
P2a
F1a
60cc
30cc
V10a
V4a
O2a
P1a
V20a
Burst Disc
RV3-300psi
O2b
V4b
V20b
V10b
D Vessel (Mix)
F1b
CO2 Bottle 940psia
O1b
Vb
V3b
V2b
30cc
F2b
15cc
V1b
F3b
P2b
V17b
P1b
Ground Equipment
RVG1b-1200psi
VG1b
CO2
5TRD Gas System Box C
6TRD Gas System Manifold
VMnA
VMnB
VMnC
VMnD
TRD Segment n
From Gas System
To Gas System
430 cu. in (7 liters)
PMnB
PMnA
- TRD segment
- There are a total of 41 segments fed in parallel
from the manifold. - Manifolds are mounted on the TRD octagon and are
mechanically separate from the gas supply and gas
circulation systems.
7TRD Gas SystemMechanical Overview
- Box S and Box C are mounted on wake port side
- Manifolds are mounted on the TRD Octagon
- Design for Gas System has been stabilized
- Layout from MIT.
- Finite Element Calculation and Modal Analysis for
Box S from INFNRome. - Vibration Tests of Engineering Versions for
Mission Success
8TRD Gas Supply Mounted to USS-02
Xe vessel
Mixing valves MV197
CO2 vessel
9Fittings and Connections
- All tubes in the TRD gas system are 1/8, 1/4 or
1/2 outer diameter stainless steel tubes. - Connections are made with welded joints (as an
alternate sealed fittings will be used). Welding
as per MSFC-SPEC-560A (D. Rybicki). - Connections between the gas manifolds and the TRD
segments are made with 1 mm inner diameter
stainless steel tubing and metal connectors.
10FEA and Margins of Safety
- Performed my INFN-Rome
- Document enclosed in datapack
- Continuously updated
- Key Results
- First Mode 70.8Hz
- Positive Margins of Safety
Mechanical Analysis Doc.
11FEA Results (new)
First Mode 70.8Hz
Second Mode 81.4Hz
12Vibration Test of Engineering Version of Box
SMission Success
- Verify significant structural natural
frequencies. - Verify gas system functionality under vibration
environment. - Determine dynamical environment for the tanks by
dynamic response. - Performed at ENEA at Cassacia, Italy, March,
2003. - Detailed results in datapack
- Analysis ongoing
13Vibration Tests
- For All Axes
- Sine sweep test (0.25 G from 10-300 Hz, scan rate
2 oct/min) . - Random vibration test to the levels defined in
(MWL). - Sine sweep test to verify that there is no change
when compared to the first sine sweep test.
14Test Fixture
Test fixture mat. Fe 360 weight 95 kg
Box S
Shaker Slip table
15Characterization of Test Fixture
First relevant freq. at main beam 530 Hz
163 Axis Vibration Tests
Y axis
X axis
Z axis
17Preliminary Vibration Test Frequency Responses
30
25
20
70 Hz
15
Amplitude
10
5
180
90
Phase
0
-90
-180
20
50
100
200
Frequency Hz
FRF Acc. Responce X/ Excitation X
30
25
81,8 Hz
20
Amplitude
15
10
5
180
90
Phase
0
-90
-180
20
50
100
200
Frequency Hz
FRF Acc. Response Y/ Excitation Y
18Vibration Test Results
- Validates structural design All structures can
endure dynamical environment applied. - Verifies FEA analysis First natural frequency at
70Hz. Test results in good agreement with
calculation (70.8Hz). - Validates functionality of the gas system
Circuit and valves system checked before and
after every random vibration test. - Analysis ongoing.
19Manifold Vibration TestMission Success
Vibration Test Mounting Block
- Tested at RWTH Aachen, Germany, on 7/18/2002
- Six-fold Manifold was vibration Tested
- Along each axis Sine sweep, random vibration
(6.8g rms), sine sweep. - Functional and leak test completed successfully
afterwards
20cm
Manifold
20Magnetic Field at Gas System AcceptableImportant
for Component selection and placement
Xe
Vacuum case
CO2
C
Marotta Valves
21TRD Gas System - Electrical
- Controls to Box S, C and manifolds via USCM
(Universal Slow Control Module), soldering as per
NASA-STD-873.3 w/Change 2 - All inputs, outputs and readouts and electrical
connections have been specified - Electrical simulator for Box S constructed
- Designed,constructed by INFN-Rome
- Vibration, thermal vacuum test with rest of TRD
gas system
22Control Electronics Overview
TRD
Xe CO2 tanks
pump
manifolds
computer USCM
UGBC
UGBS
UGFV
Electronic-control
INFN Roma
Command Monitor Signals
Gas Lines
23Electronics Status
Requirements (power, connectors, pinouts, etc.)
defined.Flight Boards ready summer 2003.
Engineering Electronic Boards ready and tested
Box S Simulator
24TRD Gas System Components
- Box S
- Composite overwrapped pressure vessels (COVP)
manufactured by Arde - High pressure valves, Marotta MV197
- GP-50 pressure sensors
- Box C
- Pumps, KNF NMP 30 KNDC B, brushless, DC diaphragm
- Flip valves, Burkert 6123
25Box S Component List
26Pressure VesselsArde Inc.
- Xe Tank
- Used on ISS in PCU
- Maximum Design Pressure/Maximum Expected
Operating Pressure (MDP)/(MEOP) 3000 psi - Min./Max. design temperature -60 F to 150 F
(-51C to 65C) - Normal Operating Pressure 1550 psi
- Normal Operating Temperature 77 F (25 C)
- Proof test factor 1.5 x MDP
- Minimum burst factor 3.1 x MDP
- Leak Before Burst (LBB)
-
27- Xe Tank (cont)
- Outside diameter 15.37 in.
- Volume 1680 in3
- Tank weight 17 lbs
- Weight of Xenon 109 lbs (max.)
- External load test performed to 8.9 grms at 0.08
g2/Hz all axes - Material is carbon fiber composite over wrapped
stainless steel - Qualification by similarity report Arde EG10330,
N/C, July 6, 2001.
28- CO2 tank
- Maximum Design Pressure/Maximum Expected
Operating Pressure (MDP)/(MEOP) 3200 psig - Min./Max. design temperature -100 F to 300 F
(-73 C to 149 C) - Leak before burst
- Normal Operating Pressure 940 psi
- Normal Operating Temperature 77 F (25 C)
- Proof test factor 1.5 x MDP
- Minimum burst factor 2.125 x MDP
- Qualification by similarity report Arde EG10331,
N/C, July 6, 2001. -
29- CO2 Tank (cont)
- Outside diameter 12.42 in.
- Volume 813 in3
- Tank weight 9.5 lbs
- Weight of CO2 11 lbs (max.)
- External load test performed to
- 8.9 Grms at 0.07 g2/Hz (axial)
- 4.5 Grms at 0.02 g2/Hz (lateral)
- Material is composite over wrapped stainless
steel
30TRD Gas System Components
- Design and Operating Pressures (Cont)
- Mixing Tank
- Cylindrical Pressure Volume
- Maximum Design Pressure/Maximum Expected
Operating Pressure (MDP)/(MEOP) 300 psig - Min./Max. design temperature -100 F to 300 F
(-73 C to 149 C) - Normal Operating Pressure 200 psia
- Normal Operating Temperature 77 F (25 C)
- Proof test factor 2 x MDP
- Minimum burst factor 4.0 x MDP
- 1 Liter Volume
- Manufactured by ARDE (ARDE SKC 13181)
- Fracture and stress report Arde Inc., EG 10348
N/C, Nov. 6, 2001
31CO2 Vessel Prior to Overwrap
Main safety leak before burst
32Marotta MV197
- In Box S ? High Pressure
- Hermetically sealed
- Designed for 170,000 Duty Cycles. We anticipate a
max. of 20,000 duty cycles during AMS-02 mission. - MEOP 3 000psi
- MDP 6 000psi
- Proof 12 000psi
5cm
33MV197 Acceptance Test Records from Marotta
34Box C Components List
352 Pumps
- KNF NMP30 Brushless DC 24 V pump
- Positive displacement - works in microgravity
- Rated for 15,000 hours at full power
- 30,000 hours (3.4 y) at half power
- Weak point- bearings - failure does not break gas
integrity - Two years under test at CERN, MIT -gt works over
-20 to 60 C
36Pumps
- 1.4 l/h across 3 psi gives 3 TRD volumes/day
- Tested in magnetic field, OK up to 500 G
- Enclosed in Volume to maintain integrity, reduce
wear
37Prototype gas system
Mission Success (Functional, 500 automated
mixing cycles)
Monitors
Box C
Box S
38Box S Commercial UnitVibration and Functional
Tests
Daily volume
39Component testing
- Marotta valves acceptance test complete
- Pumps
- on going long duration test, low temperature
cycling - successful vibration test Aachen
- Magnetic field ? Acceptable.
- Flip valves ? under test, Acceptable over
operation range, 0-40C
40GP50 Pressure Sensors
Manufacturer Acceptance Testing
5cm
- Temperature compensated pressure readings
- Three kinds 0-25psi, 0-300psi and 0-3000psi
- 0.15 accuracy for pressure
- Magnetic Susceptibility under Study
41System Test
- Assembled flight system (Box SC) will be
vibration tested according to Structural
Verification Plan (JSC-28792, Rev. B) - Functional test of engineering system with TRD
test beam at end of this year - Thermal vacuum test of flight hardware
42TRD Gas System Operations
- Ground operations
- Flight operations
- Normal data taking
- Normal filling
- Emergency response
- Startup, shutdown
43TRD Ground Operations
- TRD testing
- Verify system operation
- Filling
- Transfer Xe, CO2 from standard 25 l gas bottles
to Box S storage vessels - Recovery
- Transfer Xe from Box S to standard 25 l gas
bottles - Procedures same as PCU - working with AMS Mission
Management to procure existing equipment from
Boeing.
44Box C OperationsNormal on-orbit
45Box S Gas Mixing Procedure
- Mixing Program On Ground and onboard AMS
- Following Sequence
- Start with Known Mixture in D Vessel. Vent D if
mixture unknown. - Fill required partial pressure of CO2
- Fill required partial pressure of Xe.
- Vent to Box C when required.
- - Minimize ground communication
- Prototype system completed 500 mixing cycles
under computer control.
46Box C daily filling procedure
- Shut down CP1.
- Close V8a and V8b.
- Confirm TRD manifolds are open
- Box S opens V4a
- Open V6a.
- Read all pressures every 1 sec
- Box S closes V4a
- Close V6a.
- Wait 5 seconds
- Open V8a.
- Start CP1.
47Box C Off-Nominal Responses
48Box C Startup Sequence
- Confirm V18a, V18b, V6a, V6b, are closed.
- Open V8a, close V8b.
- Power up CO2 analyzer, send initialization
commands - Read all P, T, and query CO2 analyzer.
- Turn on CP1.
- Turn on high voltage to Tube 3 and Tube 4.
- Read all P, T, pump current, and query CO2
analyzer. - Begin normal operations.
49Box C Shutdown Sequence
- Shut down CO2 analyzer.
- If on, shut down MCA.
- Stop HV to Tube 3 and Tube 4.
- If on, stop HV to Tube 1 and Tube 2.
- Stop CP1.
- If on, stop CP2.
- Shut V8a and V8b.
- Confirm V18a, V18b, V6a, V6b all closed.
50Assembly Schedule
- Box C
- Prototype C1B at Aachen
- Prototype C1C at MIT, operations studies
- Design for C2 complete, production to start as
soon as possible - Box S
- Schematic prototype built, 500 cycles
- Electrical dummy built, shipped
- Engineering version complete at CERN Sept. 02
- Flight version from Arde Apr. 03
- Thermal vacuum test Aachen Summer 03
51Box S Assembly
- Arde Corp., Norwood, NJ
- MIL-Q-9858, NHB 5300.4 and ASME Qualified
- Vessels used for PCU and NSTAR space engine
- Construction to start April 2003
52Box C Assembly
- Marotta Corp., Montville, NJ
- Valves, fluid control systems
- Major valve supplier for ISS
53System Test
- Assembled engineering system (Box SC) will be
vibration tested according to SVP-JSC-28792, Rev.
B - Thermal vacuum test at RWTH--Aachen
- Functional test of system in TRD test beam
54Summary
- TRD Gas System design is complete
- Assembly, vibration test of Box S engineering
model successful - Flight version of Box S to be built at Arde
starting April - Engineering and Flight Box C to be built at
Marotta - Combined thermal vacuum test on Hardware
- Engineering version of control electronics
complete and undergoing testing.