Title: AMO Instrument Schedule


1
AMO Instrument Schedule
  • Stefan Moeller XES Manager
  • June 30, 2009

2
LCLS Layout
0
100m
AMO hutch 1
200m
300m
Front End
400m
Undulator
Near Hall
FEL Diagnostics Offset mirrors
X-Ray Tunnel
Far Hall
3
NEH Hutches 1 and 2
Available March 2010
Available August 2009
4
Hutch 1
  • AMO is enclosed in hutch 1
  • PPS, laser, equipment doors
  • No access mode
  • Remote control from separate Control Room
  • 3 beam lines
  • AMO, SXR, hard x-ray
  • Shielded wall penetration
  • Laser room above with laser beam transport into
    AMO hutch
  • Enclosed laser table
  • Incoupling mirrors into AMO beamline
  • Exhaust system separate for each hutch
  • Vacuum pumps located in hutch
  • Water cooled electronic racks
  • Overhead Crane

5
Hutch 1 layout
6
LCLS AMO Instrument
  • Scientific Goals
  • Investigate multiphoton and high-field x-ray
    processes in atoms, molecules and clusters
  • Study time-resolved phenomena in atoms, molecules
    and clusters using ultrafast x-rays

7
AMO Instrument
  • The AMO instrument has four distinct vacuum
    chambers with different functions

8
HFP Chamber X-Section
  • Gas jet, 5 eTOFs, ion TOF

5 x ETOF
Interaction Region
X-ray beam
Gas jet
Ion TOF (3 options)
9
Diagnostics Chamber
  • Rest of the diagnostics chamber

10
NEH Laser
DIAGNOSTIC SUITE -Spectrometer -Autocorrelator -Fr
og -Beam Analyzer -Power Meters -Oscilloscopes
10
11
Safety Review Process
  • Presentation of AMO instrument to SOC
  • Oct 2006
  • Safety Committees
  • Earthquake
  • Electrical
  • ESH
  • Fire Marshall
  • Hoisting and Rigging
  • Radiation Safety
  • ALARA
  • Laser Safety
  • Hazardous Experimental Equipment (HEEC)
  • Presentations and reviews with SOC committees
    during design and installation

12
Earthquake Safety
  • Seismic Analysis of Anchors
  • signed off by Professional Civil Engineer 4/09
  • Seismic Analysis of Instrument tables
  • Reviewed, ready to be signed

13
Electrical Safety
  • Developed comprehensive device list with Controls
    group
  • Most device are UL listed
  • Not listed devices go through EEIP
  • Devices built in house -gt EEIP
  • No devices require separate administrative or
    engineering controls
  • Device list is complete
  • Plan to present to SME next week

14
Fire Safety
  • Fire Marshall
  • Hutch layout was presented
  • Egress requirements were reviewed
  • PPS doors have been reviewed
  • Recommendations are being implemented
  • Hutch maximum occupancy defined

15
Hoisting and Rigging
  • AMO HR document was reviewed by SME
  • Special lifting fixtures require certification
  • Lifting procedures are being written with list of
    authorized personnel
  • Documents to be submitted for approval
  • Overhead crane has been approved

16
Radiation Physics
  • Ongoing meetings and reviews with RP
  • Shielding requirements
  • Beam intercepting components
  • Ray trace and beam containment
  • Operational modes
  • Recent RSC review last week
  • Approval is pending on one minor analysis

17
Laser Safety
  • Project was reviewed and documented in several
    memos
  • Initial SOP has been approved
  • Further steps are outlined in Memo
  • On schedule to complete

18
HEEC
  • Project was presented to SME in March 09
  • Details of gas sources in the NEH are being
    worked out
  • Performed Safety envelope calculations
  • Recommendations are being reviewed in regards to
    experimental requirements
  • Completion expected within next week

19
AMO Schedule
  • Installation nearly complete
  • IRR July 15
  • First light July 31
  • Start commissioning Aug- Sept
  • First User run Sept 15th

20
Summary
  • AMO instrument is on track to being completed for
    IRR July 15
  • Safety officers have been informed and consulted
  • Recommendation are being implemented
  • Documentation is nearly completed