Title: Thermal control status
1Thermal control status
2Do you remember Chiara (Pini)?
3Nicola (Born in Milano Jan 8th 2006) and Chiara
are fine!!
4(No Transcript)
5Thermal Working Group meeting Milano, 14-16
December 2005
- TCS Mass saving
- HV brick testing
- Star tracker test
- MLI optimization
- CAB TCS
- TTCS
- accumulator
6(No Transcript)
7(No Transcript)
8ASSUMPTIONS, REMARKS
9MLI optimization
- Out of 35 blankets
- 4 have been eliminated
- For 1 thickness changed from 20 to 10 layers
- For 22 thickness changed from 20 to 7 layers
- For 7 thickness changed from 20 to 1 layer
- Fixation
- 17 blankets lacing
- 18 blankets pins (heavier) are needed
-10.6 Kg
10MLI characteristics
11(No Transcript)
12PROPOSED REDUCTION STATUS
13(No Transcript)
14PROPOSED REDUCTION STATUSAccepted
15(No Transcript)
16(No Transcript)
17(No Transcript)
18Cryocoolers and LHP
19Thermal Design Ideas of Cryocooler
- Redundancy Design
- Failure cases on China satellite(FY-1C)
- 6 LHP were applied in the thermal control
system on FY-1 - One of them was failed just after launching
- Another one was failed 24 months later.
- Restart by cooling the reservior, but failed
again after one week. - Failure cases on ICESAT(USA)
- 2003.2----launched,2 LHP
- 2003.9----The LHP on electronics showed some
temperature spikes and then stop
running---RESTARTED - 2004.4----Temperature spikes appeared again
but under control till 2004.9
20Thermal Design Ideas of Cryocooler
- Using mini-heat pipes to uniform temperature of
the cryocooler shell.
21TTCS
22REALISTIC MASS SAVING
23Total saving
- STARTING FROM 43.8 Kg overweight
- 7.5 Kg beams
- 1.5 Kg Vacuum case Silvered teflon
- 10.6 Kg MLI (less layers, optimized fixation
points) - - 18.4 Kg (realistic saving)
- 20 Kg (TOTAL SAVING)
24Continuing effort
- Integrated analysis (survey)
- Deatiled design of MLI
- Precise determination of TTCS saving
25(No Transcript)
26(No Transcript)
27Testing
28Subdetectors ready for testing
- Star Tracker
- E R HV bricks
- Lower Tof
29Star Tracker Qualification Tests
- Scheduled from 6th to 18th February 2006
- Status
- Test Procedure delivered by C. Gargiulo
- Comments sent back, OK
- Facility (SERMS Terni) Ready
- Test Set Up
- Flange with feedthrough ready
- MLI will be delivered by CGS to SERMS next Monday
- Contact person
- Corrado Gargiulo (INFN ROMA)
30Star Tracker QM
31HV bricks Qualification Test
- RICH HV brick (valid also for ECAL HV brick )
- Scheduled 1st March 2006
- Status
- Test Procedure prepared on the basis of CGS Test
Specification - Second issue (after yesterday meeting) to come
next week - Facility Terni (TBC)
- Contact person
- Eduardo Cortina (CIEMAT)
32(No Transcript)
33HV Bricks Test Levels
8 cycles 4 cycles
34HV bricks
TRP Temperature Reference Point
35Lower Tof Acceptance Test
- Schedule April/May 2006
- Status
- Test Procedure Ready
- Facility (Terni) ready at the end of February 06
(Delivery date of the flange) - Contact person
- Federico Palmonari (INFN - BO)
36Terni (SERMS) Facility
TV Chamber
37Terni TV Chamber
- Chamber dimensions 2100 x 2100 mm
- Pressure range 1000 mbar to 3x10-5 mbar (10-7
mbar reached during commissioning) - Temperature range -70C 125 C
- Temperature gradient 1 C/minute
- Temperature stability /- 1 degree
- 3 cold plates (mounted on the inner side of the
front door) - lower mm 500x1820 FOR STAR TRACKER
- mid mm 500x1970
- high mm 500x1550
38ESA Large Space Simulator(LSS)Thermal Model
- M. Cova, GM Xin, W. Du, Z. Zhao
39LSS Thermal model
- LSS TMM will be used for test predictions
- ESA translated LSS model from ESARAD (EU) to
TRASYS (US, 1980) - TRASYS model was delivered Jan 2006
- CGS/SDU translated TRASYS to Thermal Desktop (US,
2000) - Translation includes running a set of test cases
40LSS GMM
41LSS thermo-optical properties
42(No Transcript)
43TRANSLATION CHECK
- To begin the model debugging we have calculated
internal view factors, to be submitted to ESA for
comparison - The plan is to have the first analysis results of
AMS inside the LSS in April 2006. - Main decision shall we use solar beam or not?
44LSS Radks
45(No Transcript)
46- LHP EM Testing Definition of Test Set-up
- S. Zinna (UNIBG) Y. QU (SDU)
- M. Molina (CGS) G.M.XIN (SDU)
47Contents
- Introduction
- Status of design
- Boundary Conditions
- Insulation design
- Working Fluid Selection
- Refrigerator
- Conclusion
48Introduction
LHP-System
Temperature Requirements Min. turn-on and oper
- 10C (TBC) Max. oper
40C Min. non-oper and
survival - 40C Max. non-oper and survival
40C Dissipation heat lift Minimum 60
3 Watts/ Cryocooler Nominal 100 5 Watts/
Cryocooler Maximum 150 8 Watts/ Cryocooler
49Ground Test of LHP EM
- A LHP EM is planned to be delivered to SDU, and a
ground test will be performed there. - This presentation shows the preliminary thermal
design of the chamber, built last year.
50Cooperating with CGS, Mr. S. Zinna (phD
candidate from Bergamo University - Italy) is
working on the chamber design together with
people in SDU (China) since November 2005. A
meeting was held in Milano, Jan 17th, 2006 .
51General Idea
Heat insulating layer
Interlayer
52Boundary Conditions
- In the present thermal chamber design, three
different operating temperatures are considered.
5399 of average case will be covered by using case
3 (-90 ?) 88 of average case for case 2 (-60
?) 60 of average case for case1 (-30 ?)
54Heat Insulating Layer
- A heat insulating layer around thermal chamber is
needed to reduce the heat leak from the ambient
environment, which could be as high as gt12000 W
when Tamb28?, Twall-60?. - Therefore, an insulating layer made of Armaflex
is analyzed.
55Working Fluid Selection
- Based the temperature range, properties and cost
of fluid, the R141b was selected to be the
working fluid in the present design, and it is
possible to maintain the full temperature range
proposed.
Propylene Glycol is analyzed also but only
possible for a limited range. (case 1 and part of
case 2)
56Refrigerator
- To compensate the heat leak from outside and heat
dissipation from LHP EM, a refrigerator system is
needed to circulate the working fluid and cool it
down to the required temperature.
- For all the cases, a refrigerator having a
cooling capability of 2000W_at_-90 ? is needed.
Considering a smaller range (case1 and case 2),
1500W _at_-60 ? is needed.
57Conclusion
- The preliminary design of test facility for LHP
EM is finished - Calculation based on R141b as the working fluid.
- Insulation around the thermal chamber designed,
to prevent the heat leak from ambient
environment. - The refrigerator system having a high cooling
capability is needed for the required temperature
range. - Still, more efforts needed
- Refinement of calculation.
- Dry air system design.
- Start procurement of components. (May, 2006)
- Target date for chamber ready (Dec 21st, 2006)
58(No Transcript)
59120V Heaters progress report- SSRMS / PVGF
power requirements- Cryo-cooler heater fault-on
analysis
60AMS-02 power requirement
- SSRMS / PVGF power requirements this is the
critical step!
61Provided by T.Urban
62SSRMS power budget (AMS-02)
63Is AMS-02 compliant to the SSRMS power
requirement ?
64- SSRMS / PVGF power requirements
- are defined in different terms in two
- separate paragraphs in SSP 57003.
- SPP 57003 Attached Payload Interface
Requirements Document Revision A August 5,
2002 - SPP 42004 Mobile Servicing System (MSS) to
User (Generic) Interface Control Document Part
I Revision H October 31, 2003
65AMS-02 current drain shall not exceed 16.7amps
all along the voltage range
66 3.7.6.2 EBCS AVIONICS PACKAGE POWER
- A. The payload shall route the PVGF cable to the
EBCS Avionics Package and provide connections as
indicated in SSP 57004, Figure 3.7.21. The
Avionics Package uses power from the PVGF and
also routes payload power from the PVGF to the
payload, up to 1800 Watts if necessary. - External Berthing Camera System
67Remarks
- The current drain can range from 0 to 16.7amps
all along the voltage range (107.5V to 126V) - The maximum payload power calculated as VmaxImax
turns to be 2104W - 2104W gt 1800W (allowed)
- If we consider voltage drop thru line, the
maximum input voltage to be used is lower but
still not enough to meet the 1800W
68Updates by T.Urban (Jan 31st, 2006)
- T.Urban has officialy communicated that the 1800W
requirement is no longer applicable. - WHAT DOES IT MEAN FOR AMS (AND HEATERS DESIGN)?
69- 16.7amps current requirement is met (all along
the voltage range) and AMS 120V heater design is
definetively approved
70Cryo-cooler heater fault-on analysis
- Scope to define if the cryo LHP heater is safety
critical
71Cryo Fault heater analysis assumptions
- 1 LHP working (1 LHP failed)
- Cryo-cooler running at the maximum power, namely
150W - Heater stuck-on when supplied at the maximum
voltage, namely 43W - Hottest environment
- Overall power dissipation 150W 8W 43W 201W
72Analysis performed by G.M.Xin
73Cryo-cooler fault heater analysis results
- The saturation temperature of the LHP is 30C
- The corresponding saturation pressure is 13bar
- The Burst safety factor must be at least 4
- Burst pressure will be provided by CAST
- shall be at least 52 bar
74(No Transcript)
75(No Transcript)
76(No Transcript)
77(No Transcript)
78(No Transcript)