Title: Mestrado em Inform
1On the Bene?ts of Planning and Grouping Software
Maintenance Requests
Gladston Aparecido Junio (PUC Minas, Brazil)
Marcelo Malta (PUC Minas, Brazil) Humberto
Mossri (PUC Minas, Brazil) Humberto Marques-Neto
(PUC Minas, Brazil) Marco Tulio Valente (UFMG,
Brazil)
CSMR Oldenburg, Germany, March 2011
2Motivation
- Policies for scheduling maintenance requests
- Continuous requests implemented as quick as
possible - Periodic requests packaged in larger projects
- In theory, the benefits of periodic policies are
widely known - Several statistical models have been proposed
- Example Banker et. al (30 of cost reduction)
- Do such gains happen in real organizations?
- Theoretical models have not been validated by
field studies
3In this Talk
- Define a simple process called PASM for
handling maintenance requests as projects - PASM Process for Grouping Maintenance Requests
- Propose a methodology to evaluate maintenance
policies - Evaluate the gains achieved by the PASM process
in a real software development organization
4PASM
- Three phases
- Registration
- Grouping
- Processing
51st Phase Registration
- Pre-defined time frame for registration
- Typical requests are buffered
- Users can specify that a request is urgent
- If ratified by the process manager
- Request goes directly to implementation
- No waiting-costs
62nd Phase Grouping
- No rigid guidelines for grouping
- Two forces size and cohesion
- Size
- Compatible with the production capacity
- Should not imply in waiting costs that users
will not tolerate - Cohesion
- Requests of a project should be functionally
coherent
73rd Phase Processing
- PASM does not fix a development method
8Characterization Methodoly
9Characterization Methodology
- How to evaluate the gains achieved by PASM in a
real setting? - Adapted a methodology proposed to understand the
behavior of web users - Central idea Software Maintenance Request Model
Graph - Nodes states of each request
- Edges transition between such states
10Software Maintenance Request Model Graph
11Metrics
- QueueTime WaitTime ServiceTime
- Service Time
- PlanningTime AnalysisTime
- ImplementationTime ValidationTime
- DeploymentTime
12Methodology
- Classify the requests in the following groups
- Before PASM, Urgent
- Before PASM, Project
- After PASM, Urgent
- After PASM, Project
- For each request in each of the previous groups
- Generate the SMRMG
- Generate a vector with the previous metrics
- For the vectors in each group
- Apply a clustering algorithm (k-means)
13Goal with Clustering
- Discover the characteristics of the typical
projects - Before PASM
- After PASM
- Evaluate the positive and negative effects of the
PASM adoption on such projects - Discover the characteristics of typical urgent
requests - Before PASM
- After PASM
- Evaluate the positive and negative effects of the
PASM adoption on such requests
14Evaluation
- We have evaluated the PASM process at DATAPUC
- DATAPUC IT Department of PUC Minas
- 34 developers
- 40 systems, 4 MLOC
- Until October 2008
- (most) maintenance requests handled on demand, in
a continuous way. - Starting on November 2008
- DATAPUC has moved to the PASM process
15PASM _at_ DATAPUC
- Registering Phase first 10 days of each month
- Grouping next 20 days
- Requests are evaluated and grouped in projects
- Cycle is repeated in the next month
16Data Source
- Same sequence of months
- Before PASM February-October 2008
- After PASM February-October 2009
Requests Before PASM (2008) After PASM (2009)
Urgents 1051 953
Projects 22 62
17Results Maintenance Projects
18Maintenance Projects Clusters
Metrics 2008 2008 2009 2009
Metrics Cluster 1(19 proj.) Cluster 2(3 proj.) Cluster 1(52 proj.) Cluster 2(10 proj.)
QueueTime 185,00 771,87 245,04 694,91
WaitTime 12,16 17,50 26,85 11,95
ServiceTime 172,84 754,37 218,19 682,97
AnalysisTime 31,51 7,48 48,71 141,61
PlanningTime 6,34 5,02 3,66 64,61
ImplementationTime 74,63 348,27 50,39 122,56
StandByTime 0,00 0,00 0,20 0,00
ValidationTime 39,34 377,46 94,19 249,70
DeploymentTime 21,01 16,14 21,04 104,49
- ImplementationTime - 32
- ImplementationTime / ServiceTime
- 2008 43
- 2009 23
- ValidationTime 139
- ValidationTime / ServiceTime
- 2008 22
- 2009 43
- AnalysisTime 54
- AnalysisTime / ServiceTime
- 2008 18
- 2009 22
19Maintenance Projects SMRMG Probabilities
20Maintenance Projects Summary
- More projects
- Before PASM 22 projects
- After PASM 62 projects
- Dominant development task
- Before PASM implementation (43)
- After PASM validation (43)
21Results Urgent Requests
22Urgent Requests SMRMG
23Typical Urgent Requests
Metrics Cluster 2 - 2008(651 req) Cluster 5 - 2009(383 req)
QueueTime 16,79 12,82
WaitTime 2,80 3,22
ServiceTime 13,98 9,60
AnalysisTime 4,46 2,45
ImplementationTime 7,02 3,94
StandByTime 2,50 3,21
ValidationTime 0,00 0,00
DeploymentTime 0,00 0,00
- ImplementationTime / ServiceTime
- 2008 50
- 2009 41
24Complex, Error-Prone, Urgent Request
Metrics Cluster 5 - 2008(222 req.) Cluster 2 - 2009(212 req.)
QueueTime 25,82 26,51
WaitTime 3,56 3,05
ServiceTime 22,26 23,46
AnalysisTime 8,33 3,23
ImplementationTime 2,28 4,27
StandByTime 1,02 2,07
ValidationTime 10,63 13,89
DeploymentTime 0,00 0,00
- ValidationTime / ServiceTime
- 2008 48
- 2009 59
25Urgent Requests Summary
- QueueTime, after PASM
- Typical requests - 4 hours
- Complex requests 1 hour (more time to
validation)
26Conclusions
27Contributions
- PASM Process for grouping maintenance requests
- Lightweighted process
- Three phases registration, grouping, processing
- Methodology to evaluate maintenance policies,
based on - Software Maintenance Request Model Graph
- Clustering techniques
- Classical queue model metrics
- Field study to evaluate the benefits achieved by
PASM
28Benefits
- More requests handled as projects
- Side-effects
- More time dedicated to analysis and validation
- Less time dedicated to implementation
- Urgent maintenance requests
- Handled in less time
28
29Further Work
- Promote and evaluate the PASMs adoption by other
organizations - Assess the internal and external quality of the
software released under PASM guidelines
29