Title: Ingen bildrubrik
1Blackout in Sweden andEastern Part of
Denmark2003-09-23
Sture Lindahl 2003-10-05 Industrial Electrical
Engineering and Automation sture.lindahl_at_iea.lth.s
e
2The Nordel System
3The Affected Region
4Outage Cost
- Interrupted power ?? 5 000 MW
- Average outage time ?? 4 hours
- Outage cost ?? 50 SEK/kWh
- Total outage cost ?? 1000 MSEK
5Consumption in Sweden
- Before outage ? 15 000 MW
- Winter peak 25 000 - 27 000 MW
- Section-4 power flow 2 200 MW
6Situation before Disturbance
7Generation Outages
Gx
G1 G2
G1, G2 G3
G1 G2
8Transmission Outages
9The First Event (1230)
- The nuclear unit Oskarshamn G3 was ramped down
from 1 135 MW to zero because of a problem with a
valve in the feed-water system. - The ramping down of Oskarshamn G3 was initiated
manually - The reduction of power took about one minute
10The First Event (1230)
G3
11The System Frequency
12The System Frequency
13The Second Event (1235)
- A disconnector in the 400 kV substation Horred
failed (reason unknown) and caused a two-phase
fault - Correct clearing of the fault was initiated from
the busbar protection - The circuit breakers operated correctly
14R
R
R
T
Varmgång
Bilaga 3
15Damaged Disconnector
16Damaged Disconnector
17The Second Event (1235)
Busbar Fault
18The Second Event (1235)
19Voltage Level
20Voltage Level
21Voltage Level
22Voltage Level
23Power Flow
24Power Flow
25Power Flow
26Power Flow
27Tap Changers
28Tap Changers
29Tap Changers
30(No Transcript)
31The System Frequency
32The System Frequency
33What we saw of the black-out
- Voltages and frequency recorded on 23 September
2003 at Chalmers - (Math Bollen, 24-9-2003)
34First a few words about the measurements. These
measurements were obtained by two different
instruments at two different locations in our
building. a Medcal monitor connected to the
wall-outlet in my office (single phase). This
monitor records min, mean and max every minute.
Upon triggering a two-cycle sample of the
waveform is obtained. a Unipower monitor
connected to the main busbar in our
laboratory (three phases). This monitor records
min, mean and max every minute. Upon triggering
a 2.5-second record of the rms voltages is
stored. The clocks of the two monitors are not
synchronous. The main voltage dip (1235
according to SvK) had the following time
stamps Medcal 124106 Unipower 123111
350.5-cycle rms voltages during and after the main
dip
oscillation points to instability!
normal dip due to two-phase-to-ground fault
time stamp 123111
Unipower
36rms voltages six seconds later
cause of dips is unclear.
time stamp 123117
Unipower
37frequency recordings during the whole afternoon
the three curves show maximum, minimum and
average over each 1-minute period
the main disturbance around 1230
minor disturbance around 1800
MedCal
38This shows the frequency variations during the
first disturbance in more detail
the main dip was recorded here
loss of South Sweden
frequency remains high due to loss of load
loss of Oskarhamn 3
loss of Ringhals 34
MedCal
39Recordings from Odensala
40Voltage Restoration
- The 400 kV network was essentially restored after
1 hour
41Genopretningen minut for minut
- 12.38 Elkraft System forbereder at sætte spænding
på hele højspændingsnettet - 13.20 Elkraft System venter på, at Kyndbyværket
starter - 13.41 Vi får tilladelse til at koble os til
Sverige men kun med et meget lille forbrug
(max. 200 MW) - 13.46 Østdanmark kobler til Sverige.
Højspændingsnettet er i gang
42Genopretningen minut for minut
- 13.54 Elkraft System giver tilladelse til, at en
del af forbrugerne får strøm igen - Københavns Energi kan tilkoble forbrugere
svarende til 50 MW - NESA kan tilkoble forbrugere svarende til 50 MW
- SEAS kan tilkoble forbrugere svarende til 25 MW
- NVE kan tilkoble forbrugere svarende til 25 MW
43Genopretningen minut for minut
- 14.15 Første kraftværksblok kører igen
(Kyndbyværket) - 14.16 Svenska Kraftnät melder, at vi kun må
trække 100 MW fra Sverige - 14.31 Asnæsværket blok 5 forsøger at starte, men
kan ikke. Asnæsværket blok 2 forsøges herefter
startet - 14.53 Stigsnæsværket blok 2 havarerer ved opstart
- 14.57 Gasturbine på Masnedø kommer i gang (55 MW)
44Genopretningen minut for minut
- 15.00 Københavns Energi får lov at give ekstra 10
procent af forbrugerne strøm - 15.22 Gasturbine på Kyndbyværket kommer i gang
- 15.25 Yderligere 10 procent af forbrugerne hos
SEAS tilkobles - 15.29 Endnu en gasturbine på Kyndbyværket kommer
i gang - 16.42 Københavns Energi får tilladelse til at
give DSBs fjerntog strøm
45Genopretningen minut for minut
- 16.57 Systemet er stabilt nok, til at
vindmøllerne gradvist kan tilkobles - 18.18 En dieselgenerator på Kyndbyværket sætter
ud - 18.25 Asnæsværket blok 2 kommer i gang
- 18.33 Asnæsværket blok 5 havarerer ved opstart og
er ikke kommet i gang endnu - 19.05 NVE, NESA, KE og SEAS får tilladelse til at
tilkoble resten af forbrugerne
46Conclusion
- Outage of 20 of Sweden
- Outage of 50 of Denmark
- Voltage restoration time 1 hour
- Load restoration was depending on start-up time
of generating units - Outage cost about 1 000 MSEK
47Additional Information
- http//www.elkraft-system.dk/elkraft/dk/Nyheder.ns
f - http//www.svk.se/
- http//www.abebooks.com/