Ingen bildrubrik - PowerPoint PPT Presentation

1 / 47
About This Presentation
Title:

Ingen bildrubrik

Description:

Blackout in Sweden and Eastern Part of Denmark 2003-09-23 Sture Lindahl 2003-10-05 Industrial Electrical Engineering and Automation sture.lindahl_at_iea.lth.se – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 48
Provided by: iea89
Category:

less

Transcript and Presenter's Notes

Title: Ingen bildrubrik


1
Blackout in Sweden andEastern Part of
Denmark2003-09-23
Sture Lindahl 2003-10-05 Industrial Electrical
Engineering and Automation sture.lindahl_at_iea.lth.s
e
2
The Nordel System
3
The Affected Region
4
Outage Cost
  • Interrupted power ?? 5 000 MW
  • Average outage time ?? 4 hours
  • Outage cost ?? 50 SEK/kWh
  • Total outage cost ?? 1000 MSEK

5
Consumption in Sweden
  • Before outage ? 15 000 MW
  • Winter peak 25 000 - 27 000 MW
  • Section-4 power flow 2 200 MW

6
Situation before Disturbance
7
Generation Outages
Gx
G1 G2
G1, G2 G3
G1 G2
8
Transmission Outages
9
The First Event (1230)
  • The nuclear unit Oskarshamn G3 was ramped down
    from 1 135 MW to zero because of a problem with a
    valve in the feed-water system.
  • The ramping down of Oskarshamn G3 was initiated
    manually
  • The reduction of power took about one minute

10
The First Event (1230)
G3
11
The System Frequency
12
The System Frequency
13
The Second Event (1235)
  • A disconnector in the 400 kV substation Horred
    failed (reason unknown) and caused a two-phase
    fault
  • Correct clearing of the fault was initiated from
    the busbar protection
  • The circuit breakers operated correctly

14
R
R
R
T
Varmgång
Bilaga 3
15
Damaged Disconnector
16
Damaged Disconnector
17
The Second Event (1235)
Busbar Fault
18
The Second Event (1235)
19
Voltage Level
20
Voltage Level
21
Voltage Level
22
Voltage Level
23
Power Flow
24
Power Flow
25
Power Flow
26
Power Flow
27
Tap Changers
28
Tap Changers
29
Tap Changers
30
(No Transcript)
31
The System Frequency
32
The System Frequency
33
What we saw of the black-out
  • Voltages and frequency recorded on 23 September
    2003 at Chalmers
  • (Math Bollen, 24-9-2003)

34
First a few words about the measurements. These
measurements were obtained by two different
instruments at two different locations in our
building. a Medcal monitor connected to the
wall-outlet in my office (single phase). This
monitor records min, mean and max every minute.
Upon triggering a two-cycle sample of the
waveform is obtained. a Unipower monitor
connected to the main busbar in our
laboratory (three phases). This monitor records
min, mean and max every minute. Upon triggering
a 2.5-second record of the rms voltages is
stored. The clocks of the two monitors are not
synchronous. The main voltage dip (1235
according to SvK) had the following time
stamps Medcal 124106 Unipower 123111
35
0.5-cycle rms voltages during and after the main
dip
oscillation points to instability!
normal dip due to two-phase-to-ground fault
time stamp 123111
Unipower
36
rms voltages six seconds later
cause of dips is unclear.
time stamp 123117
Unipower
37
frequency recordings during the whole afternoon
the three curves show maximum, minimum and
average over each 1-minute period
the main disturbance around 1230
minor disturbance around 1800
MedCal
38
This shows the frequency variations during the
first disturbance in more detail
the main dip was recorded here
loss of South Sweden
frequency remains high due to loss of load
loss of Oskarhamn 3
loss of Ringhals 34
MedCal
39
Recordings from Odensala
40
Voltage Restoration
  • The 400 kV network was essentially restored after
    1 hour

41
Genopretningen minut for minut
  • 12.38 Elkraft System forbereder at sætte spænding
    på hele højspændingsnettet
  • 13.20 Elkraft System venter på, at Kyndbyværket
    starter
  • 13.41 Vi får tilladelse til at koble os til
    Sverige men kun med et meget lille forbrug
    (max. 200 MW)
  • 13.46 Østdanmark kobler til Sverige.
    Højspændingsnettet er i gang

42
Genopretningen minut for minut
  • 13.54 Elkraft System giver tilladelse til, at en
    del af forbrugerne får strøm igen
  • Københavns Energi kan tilkoble forbrugere
    svarende til 50 MW
  • NESA kan tilkoble forbrugere svarende til 50 MW
  • SEAS kan tilkoble forbrugere svarende til 25 MW
  • NVE kan tilkoble forbrugere svarende til 25 MW

43
Genopretningen minut for minut
  • 14.15 Første kraftværksblok kører igen
    (Kyndbyværket)
  • 14.16 Svenska Kraftnät melder, at vi kun må
    trække 100 MW fra Sverige
  • 14.31 Asnæsværket blok 5 forsøger at starte, men
    kan ikke. Asnæsværket blok 2 forsøges herefter
    startet
  • 14.53 Stigsnæsværket blok 2 havarerer ved opstart
  • 14.57 Gasturbine på Masnedø kommer i gang (55 MW)

44
Genopretningen minut for minut
  • 15.00 Københavns Energi får lov at give ekstra 10
    procent af forbrugerne strøm
  • 15.22 Gasturbine på Kyndbyværket kommer i gang
  • 15.25 Yderligere 10 procent af forbrugerne hos
    SEAS tilkobles
  • 15.29 Endnu en gasturbine på Kyndbyværket kommer
    i gang
  • 16.42 Københavns Energi får tilladelse til at
    give DSBs fjerntog strøm

45
Genopretningen minut for minut
  • 16.57 Systemet er stabilt nok, til at
    vindmøllerne gradvist kan tilkobles
  • 18.18 En dieselgenerator på Kyndbyværket sætter
    ud
  • 18.25 Asnæsværket blok 2 kommer i gang
  • 18.33 Asnæsværket blok 5 havarerer ved opstart og
    er ikke kommet i gang endnu
  • 19.05 NVE, NESA, KE og SEAS får tilladelse til at
    tilkoble resten af forbrugerne

46
Conclusion
  • Outage of 20 of Sweden
  • Outage of 50 of Denmark
  • Voltage restoration time 1 hour
  • Load restoration was depending on start-up time
    of generating units
  • Outage cost about 1 000 MSEK

47
Additional Information
  • http//www.elkraft-system.dk/elkraft/dk/Nyheder.ns
    f
  • http//www.svk.se/
  • http//www.abebooks.com/
Write a Comment
User Comments (0)
About PowerShow.com