The Scottish Parliament - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

The Scottish Parliament

Description:

The Scottish Parliament Starts on next page The Scottish Parliament The Scottish Parliament The Scottish Parliament The Scottish Parliament The Scottish Parliament ... – PowerPoint PPT presentation

Number of Views:551
Avg rating:3.0/5.0
Slides: 49
Provided by: ceilidhch
Category:

less

Transcript and Presenter's Notes

Title: The Scottish Parliament


1
The Scottish Parliament
  • Starts on next page

2
The Scottish Parliament
3
The Scottish Parliament
4
The Scottish Parliament
September 2000
5
The Scottish Parliament
6
The Scottish Parliament
7
The Scottish Parliament
Holyrood Report, Fraser Chapter 8 page 97
8
The Scottish Parliament
9
The Scottish Parliament
10
The Scottish Parliament
11
The Scottish Parliament
12
The Scottish Parliament
Scottish Parliament Project Organisation
Structure 2000
Multi Headed Client, Fraser Report Chapter 12
page 194
13
(No Transcript)
14
The Scottish Parliament
15
The Scottish Parliament
16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
The Scottish Parliament
20
The Scottish Parliament
21
The Scottish Parliament
22
The Scottish Parliament
23
The Scottish Parliament
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
The Scottish Parliament
28
The Scottish Parliament
  • Other Parliamentary buildings
  • http//www.scottish.parliament.uk/business/resear
    ch/briefings-03/sb03-52.pdf

29
The Scottish Parliament
STANDARD PROJECT MANAGEMENT TECHNIQUES
(adapted from Meredith et al, 2004 and Fraser,
2004)
30
The Scottish Parliament
(adapted from Meredith et al, 2004 and Fraser,
2004)
31
The Scottish Parliament
  • This is a good site
  • http//www.scottish.parliament.uk/vli/
    holyrood/inquiry/sp205-00.htm
  • Lists everything

32
The Scottish Parliament
  • http//www.scottish.parliament.uk/business/researc
    h/pdf_res_notes/rn01-64.pdf

Mr Davidson drew a number of conclusions in his
report including the following it must be
noted that in costing terms the Spencely Report
indicated a realistic price range expectation of
195 Million to 230Million. This was at a stage
when some of the design difficulties were not
fully designed through. The conclusion from this
is that the motion put to and passed by the
Scottish Parliament, known as the Jackson
Motion, which was for a fixed cash sum at
current prices of 195 Million, was somewhat
optimistic and, in light of the complexity of the
tender and control process inherited from the
previous Scottish Office Administration, naïve
for such a complicated and indeed unique design.
33
The Scottish Parliament
  • http//www.scottish.parliament.uk/business/committ
    ees/historic/audit/reports-00/aur00-06-03.htmana0
    1
  • 28 SEPTEMBER 2000.
  • At the Audit Committee meeting on Tuesday, 26
    September, Muir Russell agreed to provide notes
    on a number of issues that were touched on during
    the evidence taking session on the Auditor
    General for Scotland's Report on the new Scottish
    Parliament Building.
  • I thought it would be helpful to put in writing
    the areas on which the Committee is expecting to
    receive clarification. These are
  • Details of the person specification and
    recruitment method adopted for the replacement
    project manager

34
The Scottish Parliament
  • RESPONSE
  • Appointment of Project Manager
  • As Dr Gibbons and I told the Committee, we were
    able to minimise the gap following the
    resignation of the former project manager because
    the project team was clear about the type of
    person and experience needed for project manager
    in the circumstances of this project and a
    suitably experienced person was available to
    transfer to this role. He was at that time
    project manager on the interim Parliament project
    (the Mound), performing successfully in that
    role, so he was a known quantity.
  • His appointment to that post followed a decision
    to establish separate project management for the
    interim Parliament project, to ensure its
    successful delivery and to enable the Holyrood
    project team to concentrate on the main project
    itself. He was appointed after discussion with a
    number of project management companies on how
    best to secure the capability to move the interim
    Parliament project forward quickly, and was
    seconded from Project Management International
    Plc, of which he was and remains an employee,
    with reimbursement made to the company

35
The Scottish Parliament
  • http//www.parliament.uk/commons/lib/research/note
    s/snpc-03357.pdf
  • Lord Fraser highlighted in the Holyrood Inquiry
    that
  • the 40 million figure could never have been a
    realistic estimate for anything other than most
    basic of new Parliament buildings. However, what
    can be stated clearly is that at the time 40
    million was included in the White Paper, there
    was no clear understanding whether that was a
    total cost including professional fees or only a
    construction cost. It was certainly not explained
    to the Scottish public what the figure

36
The Scottish Parliament
  • The Auditor General Report of 2004 made the
    following conclusions
  • Spillage
  • The main cause of the 20 months delay to the
    project since September 2000 was the
  • production of detailed design variations and the
    late supply of information during the
  • construction process.
  • Cost Increases
  • The main reasons for construction cost increases
    after 2000 were design development
  • and delay in the construction process. The design
    development was entirely related to
  • realising the detail of the building and aspects
    such as the quality of finish and the
  • palette of materials that were used, in
    accordance with the clients requirements.
  • Project management and control
  • Although it is likely that a high quality
    building is being delivered, the time and cost
  • objectives have not been met. The same quality
    could have been achieved for less if
  • the whole design and construction process had
    been better executed.

37
The Scottish Parliament
  • Summary of the Holyrood Inquirys Conclusions
    and
  • Recommendations
  • The Holyrood Inquiry was published in September
    2004 by Lord Fraser.
  • One of the principal conclusions found in the
    Holyrood Inquiry was that whenever there was a
    conflict between quality and cost, quality was
    preferred.
  • Lord Fraser further concluded that since Donald
    Dewar was determined in building a new parliament
    for Scotland as soon as possible, the timetable
    dictated the high risk and fast track
    procurement route.
  • In regards to the procurement method adopted,
    there was an inadequate level of evaluation or
    understanding of the construction management
    route subsequently ministers were not informed
    of all the risks involved.

38
The Scottish Parliament
  • The Origins of the 40 million Figure
  • The evidence before the Inquiry is reasonably
    clear that
  • this figure originally came from Mr Wyllie. On
    10 June 1997 he
  • minuted Mrs Doig with his costing of the option
    of onstructing
  • a new building on a greenfield site. Assuming a
    building with
  • an area of 15,000m² gross (11,250m² net a net
    to gross ratio
  • 25) including 1,000m² for the Chamber, 3,000m²
    for
  • Committees and Ministers and 11,000m² for the
    remainder, he
  • put forward figures in the order of 35-40
    million.His
  • minute made it clear that the figures included
    professional
  • fees, fit out, furniture and VAT although the
    position in this
  • respect contrasts with his written recognition in
    which he said
  • that his figures had excluded site works, fit
    out, professional
  • fees and VAT. In a further minute of the same
    date to Dr
  • Gibbons he elaborated on that range of figures as
  • follows

Holyrood Report, Fraser, Chapter 3 Page 23
39
The Scottish Parliament
  • http//www.scottish.parliament.uk/vli/holyrood/inq
    uiry/sp205-11.htm1
  • Was a Pause Recommended?
  • Within the Spencely Report there is no specific
    recommendation for a two month pause in the
    Project to enable a costed design to be achieved.
    However, in evidence Mr Spencely explained that
    the eight week pause was implicit within
    paragraph 5.4 of his Report
  • It is clearly imperative that the Brief is
    frozen now and that the Design Team proceeds
    immediately to produce a Scheme Design including
    a cost plan to a Brief and a budget approved by
    the client, so that approval may be given to
    proceed with the Project by 8 June 2000.
  • There has been some uncertainty amongst witnesses
    as to whether SPCB members were aware that Mr
    Spencely was recommending a pause. During a
    discussion of the Reports findings at the SPCB
    meeting on 28 March, Dr Gibbons advised that
    "Detailed design and construction would continue
    to run in parallel and there was no reason for a
    pause until 8 June." There is also reference to
    Mr Spencely recommending one option as "the
    cessation of all project activity for a period of
    three months" in the SPCBs report to Parliament,

40
The Scottish Parliament
  • In relation to the functions of his suggested
    "Progressing Group" Mr Spencelys evidence was as
    follows
  • "I expected the Progressing Group to operate as
    the Client receiving reports and
    recommendations "upwards" from the Project
    Sponsor and acting on the latter to accept,
    modify or reject and receiving and sifting
    requests for variations to the Brief "downwards"
    from MSPs and Parliamentary staff all in the
    light of the Budget and the Programme and to
    control Budget expenditure and Programme by
    making the appropriate management decisions".

41
The Scottish Parliament
  • http//www.scottish.parliament.uk/vli/holyrood/inq
    uiry/sp205-10.htm3
  • In his oral evidence Dr Gibbons, when asked about
    viability at handover, said
  • "From what we know now, it clearly was not."
  • I am bound to conclude that
  • 1. The Brief was not up to date, and did not
    reflect the changes made since November 1998.
  • 2. The Brief did not anticipate the requirements
    of the Parliament with the inevitable result that
    adherence to it would have produced an unsuitable
    building.
  • 3. The budgeted construction cost of 62 million
    was flawed in that
  • a. there was inadequate accounting for risk, and
    the stated budget bore no relationship to a cost
    planb. there had been a failure to fully
    appreciate the complexity of the design andc.
    account had not been taken of considerations of
    blast and security.
  • In short, the Project was not in a viable and
    healthy condition when it was handed over to the
    SPCB on 1 June 1999.

42
The Scottish Parliament
  • http//www.scottish.parliament.uk/vli/holyrood/inq
    uiry/sp205-14.htm12
  • Impact on Overall Cost and Programme
  • 13.77 There is no doubt that by having to focus
    on specific recurring themes in relation to
    Queensberry House, the HPG and the Project Team
    found it difficult to make progress and that
    these issues were discussed at the highest level
    by the First Minister and Presiding Officer to
    try and find a resolution. Crucially, however, it
    is to be noted this did not cause any delay to
    the overall programme, as Queensberry House was
    never on the critical path. At the same time the
    costs of Queensberry House have been
    significantly greater than anticipated at the
    outset.

43
The Scottish Parliament
  • http//www.scottish.parliament.uk/business/committ
    ees/audit/reports-04/grice-auditrep.htm
  • Adequacy of Cost Plan
  • AGSs comments in paragraphs 4.3 4.7 of the
    report reflect a misunderstanding of the purpose
    of the Cost Plan at Stage D. Such a plan is
    needed to translate the Stage D design into
    individual works packages and to estimate the
    value of the works under each package. This
    provides a basis for project management and the
    consultants to compare the values of tenders
    based on the Stage D design. The adequacy of the
    Cost Plan for this purpose is reflected in the
    fact that, on average and after allowing for
    inflation, tenders on which contracts were based
    were within 5 of the Cost Plan Estimate. In view
    of the uncertainties identified in Exhibit 9,
    this could be regarded as a reasonably
    satisfactory result.

44
The Scottish Parliament
  • Really use this web site
  • http//www.audit-scotland.gov.uk/publications/pdf
    /2004/04pf07ag.pdf

45
The Scottish Parliament
46
The Scottish Parliament
47
The Scottish Parliament
48
The Scottish Parliament
  • http//www.scottish.parliament.uk/business/commit
    tees/historic/finance/or-02/fi02-2502.htm
  • Alasdair Morgan I find it difficult to
    understand why the target date has not only
    slipped three to four months since last you gave
    evidence on 8 October, but has become less
    certain rather than more certain.
  • Sarah Davidson The current target date of best
    completion at the end of August, which means that
    everything will have happened to the best
    possible outcome, has the same status as the
    previous date of the end of April.
  • Alasdair Morgan Do you have a worst possible
    outcome date?
  • Sarah Davidson No.
  • Alasdair Morgan What kind of Gantt chart is
    used? Some kind of worst-case scenario must have
    been considered.
  • Robert Brown The object of the exercise is to
    finish the thing as quickly as possiblethat is
    clearly what we are after and the progress group
    is keeping on top of the contractors to try to
    ensure that that happens. However, as we have
    already explained, the business of the glazing
    and blast proofing could have had a dramatic
    effect on the progress of the contract. Had last
    Friday's blast test failed, we would be coming to
    the committee today to report a serious
    situation there are no two ways about that.
    Happily, the blast test was passed. Although we
    have to take account of the fact that the test
    had to happen in the first place, that is part of
    the risk review that is taking place at the
    moment. The major concerns that we would have had
    if the blast test had failed have not
    materialised. We are therefore able to come to
    the committee with good news on that particular
    point because passing the test removes what was
    probably the single biggest risk that remained on
    the contract.
Write a Comment
User Comments (0)
About PowerShow.com