Title: The Scottish Parliament
1The Scottish Parliament
2The Scottish Parliament
3The Scottish Parliament
4The Scottish Parliament
September 2000
5The Scottish Parliament
6The Scottish Parliament
7The Scottish Parliament
Holyrood Report, Fraser Chapter 8 page 97
8The Scottish Parliament
9The Scottish Parliament
10The Scottish Parliament
11The Scottish Parliament
12The Scottish Parliament
Scottish Parliament Project Organisation
Structure 2000
Multi Headed Client, Fraser Report Chapter 12
page 194
13(No Transcript)
14The Scottish Parliament
15The Scottish Parliament
16(No Transcript)
17(No Transcript)
18(No Transcript)
19The Scottish Parliament
20The Scottish Parliament
21The Scottish Parliament
22The Scottish Parliament
23The Scottish Parliament
24(No Transcript)
25(No Transcript)
26(No Transcript)
27The Scottish Parliament
28The Scottish Parliament
- Other Parliamentary buildings
- http//www.scottish.parliament.uk/business/resear
ch/briefings-03/sb03-52.pdf
29The Scottish Parliament
STANDARD PROJECT MANAGEMENT TECHNIQUES
(adapted from Meredith et al, 2004 and Fraser,
2004)
30The Scottish Parliament
(adapted from Meredith et al, 2004 and Fraser,
2004)
31The Scottish Parliament
- This is a good site
- http//www.scottish.parliament.uk/vli/
holyrood/inquiry/sp205-00.htm - Lists everything
32The Scottish Parliament
- http//www.scottish.parliament.uk/business/researc
h/pdf_res_notes/rn01-64.pdf
Mr Davidson drew a number of conclusions in his
report including the following it must be
noted that in costing terms the Spencely Report
indicated a realistic price range expectation of
195 Million to 230Million. This was at a stage
when some of the design difficulties were not
fully designed through. The conclusion from this
is that the motion put to and passed by the
Scottish Parliament, known as the Jackson
Motion, which was for a fixed cash sum at
current prices of 195 Million, was somewhat
optimistic and, in light of the complexity of the
tender and control process inherited from the
previous Scottish Office Administration, naïve
for such a complicated and indeed unique design.
33The Scottish Parliament
- http//www.scottish.parliament.uk/business/committ
ees/historic/audit/reports-00/aur00-06-03.htmana0
1 - 28 SEPTEMBER 2000.
- At the Audit Committee meeting on Tuesday, 26
September, Muir Russell agreed to provide notes
on a number of issues that were touched on during
the evidence taking session on the Auditor
General for Scotland's Report on the new Scottish
Parliament Building. - I thought it would be helpful to put in writing
the areas on which the Committee is expecting to
receive clarification. These are - Details of the person specification and
recruitment method adopted for the replacement
project manager
34The Scottish Parliament
- RESPONSE
- Appointment of Project Manager
- As Dr Gibbons and I told the Committee, we were
able to minimise the gap following the
resignation of the former project manager because
the project team was clear about the type of
person and experience needed for project manager
in the circumstances of this project and a
suitably experienced person was available to
transfer to this role. He was at that time
project manager on the interim Parliament project
(the Mound), performing successfully in that
role, so he was a known quantity. - His appointment to that post followed a decision
to establish separate project management for the
interim Parliament project, to ensure its
successful delivery and to enable the Holyrood
project team to concentrate on the main project
itself. He was appointed after discussion with a
number of project management companies on how
best to secure the capability to move the interim
Parliament project forward quickly, and was
seconded from Project Management International
Plc, of which he was and remains an employee,
with reimbursement made to the company
35The Scottish Parliament
- http//www.parliament.uk/commons/lib/research/note
s/snpc-03357.pdf - Lord Fraser highlighted in the Holyrood Inquiry
that - the 40 million figure could never have been a
realistic estimate for anything other than most
basic of new Parliament buildings. However, what
can be stated clearly is that at the time 40
million was included in the White Paper, there
was no clear understanding whether that was a
total cost including professional fees or only a
construction cost. It was certainly not explained
to the Scottish public what the figure
36The Scottish Parliament
- The Auditor General Report of 2004 made the
following conclusions - Spillage
- The main cause of the 20 months delay to the
project since September 2000 was the - production of detailed design variations and the
late supply of information during the - construction process.
- Cost Increases
- The main reasons for construction cost increases
after 2000 were design development - and delay in the construction process. The design
development was entirely related to - realising the detail of the building and aspects
such as the quality of finish and the - palette of materials that were used, in
accordance with the clients requirements. - Project management and control
- Although it is likely that a high quality
building is being delivered, the time and cost - objectives have not been met. The same quality
could have been achieved for less if - the whole design and construction process had
been better executed.
37The Scottish Parliament
- Summary of the Holyrood Inquirys Conclusions
and - Recommendations
- The Holyrood Inquiry was published in September
2004 by Lord Fraser. - One of the principal conclusions found in the
Holyrood Inquiry was that whenever there was a
conflict between quality and cost, quality was
preferred. - Lord Fraser further concluded that since Donald
Dewar was determined in building a new parliament
for Scotland as soon as possible, the timetable
dictated the high risk and fast track
procurement route. - In regards to the procurement method adopted,
there was an inadequate level of evaluation or
understanding of the construction management
route subsequently ministers were not informed
of all the risks involved.
38The Scottish Parliament
- The Origins of the 40 million Figure
- The evidence before the Inquiry is reasonably
clear that - this figure originally came from Mr Wyllie. On
10 June 1997 he - minuted Mrs Doig with his costing of the option
of onstructing - a new building on a greenfield site. Assuming a
building with - an area of 15,000m² gross (11,250m² net a net
to gross ratio - 25) including 1,000m² for the Chamber, 3,000m²
for - Committees and Ministers and 11,000m² for the
remainder, he - put forward figures in the order of 35-40
million.His - minute made it clear that the figures included
professional - fees, fit out, furniture and VAT although the
position in this - respect contrasts with his written recognition in
which he said - that his figures had excluded site works, fit
out, professional - fees and VAT. In a further minute of the same
date to Dr - Gibbons he elaborated on that range of figures as
- follows
Holyrood Report, Fraser, Chapter 3 Page 23
39The Scottish Parliament
- http//www.scottish.parliament.uk/vli/holyrood/inq
uiry/sp205-11.htm1 - Was a Pause Recommended?
- Within the Spencely Report there is no specific
recommendation for a two month pause in the
Project to enable a costed design to be achieved.
However, in evidence Mr Spencely explained that
the eight week pause was implicit within
paragraph 5.4 of his Report - It is clearly imperative that the Brief is
frozen now and that the Design Team proceeds
immediately to produce a Scheme Design including
a cost plan to a Brief and a budget approved by
the client, so that approval may be given to
proceed with the Project by 8 June 2000. - There has been some uncertainty amongst witnesses
as to whether SPCB members were aware that Mr
Spencely was recommending a pause. During a
discussion of the Reports findings at the SPCB
meeting on 28 March, Dr Gibbons advised that
"Detailed design and construction would continue
to run in parallel and there was no reason for a
pause until 8 June." There is also reference to
Mr Spencely recommending one option as "the
cessation of all project activity for a period of
three months" in the SPCBs report to Parliament,
40The Scottish Parliament
- In relation to the functions of his suggested
"Progressing Group" Mr Spencelys evidence was as
follows - "I expected the Progressing Group to operate as
the Client receiving reports and
recommendations "upwards" from the Project
Sponsor and acting on the latter to accept,
modify or reject and receiving and sifting
requests for variations to the Brief "downwards"
from MSPs and Parliamentary staff all in the
light of the Budget and the Programme and to
control Budget expenditure and Programme by
making the appropriate management decisions".
41The Scottish Parliament
- http//www.scottish.parliament.uk/vli/holyrood/inq
uiry/sp205-10.htm3 - In his oral evidence Dr Gibbons, when asked about
viability at handover, said - "From what we know now, it clearly was not."
- I am bound to conclude that
- 1. The Brief was not up to date, and did not
reflect the changes made since November 1998. - 2. The Brief did not anticipate the requirements
of the Parliament with the inevitable result that
adherence to it would have produced an unsuitable
building. - 3. The budgeted construction cost of 62 million
was flawed in that - a. there was inadequate accounting for risk, and
the stated budget bore no relationship to a cost
planb. there had been a failure to fully
appreciate the complexity of the design andc.
account had not been taken of considerations of
blast and security. - In short, the Project was not in a viable and
healthy condition when it was handed over to the
SPCB on 1 June 1999.
42The Scottish Parliament
- http//www.scottish.parliament.uk/vli/holyrood/inq
uiry/sp205-14.htm12 - Impact on Overall Cost and Programme
- 13.77 There is no doubt that by having to focus
on specific recurring themes in relation to
Queensberry House, the HPG and the Project Team
found it difficult to make progress and that
these issues were discussed at the highest level
by the First Minister and Presiding Officer to
try and find a resolution. Crucially, however, it
is to be noted this did not cause any delay to
the overall programme, as Queensberry House was
never on the critical path. At the same time the
costs of Queensberry House have been
significantly greater than anticipated at the
outset.
43The Scottish Parliament
- http//www.scottish.parliament.uk/business/committ
ees/audit/reports-04/grice-auditrep.htm - Adequacy of Cost Plan
- AGSs comments in paragraphs 4.3 4.7 of the
report reflect a misunderstanding of the purpose
of the Cost Plan at Stage D. Such a plan is
needed to translate the Stage D design into
individual works packages and to estimate the
value of the works under each package. This
provides a basis for project management and the
consultants to compare the values of tenders
based on the Stage D design. The adequacy of the
Cost Plan for this purpose is reflected in the
fact that, on average and after allowing for
inflation, tenders on which contracts were based
were within 5 of the Cost Plan Estimate. In view
of the uncertainties identified in Exhibit 9,
this could be regarded as a reasonably
satisfactory result.
44The Scottish Parliament
- Really use this web site
- http//www.audit-scotland.gov.uk/publications/pdf
/2004/04pf07ag.pdf
45The Scottish Parliament
46The Scottish Parliament
47The Scottish Parliament
48The Scottish Parliament
- http//www.scottish.parliament.uk/business/commit
tees/historic/finance/or-02/fi02-2502.htm - Alasdair Morgan I find it difficult to
understand why the target date has not only
slipped three to four months since last you gave
evidence on 8 October, but has become less
certain rather than more certain. - Sarah Davidson The current target date of best
completion at the end of August, which means that
everything will have happened to the best
possible outcome, has the same status as the
previous date of the end of April. - Alasdair Morgan Do you have a worst possible
outcome date? - Sarah Davidson No.
- Alasdair Morgan What kind of Gantt chart is
used? Some kind of worst-case scenario must have
been considered. - Robert Brown The object of the exercise is to
finish the thing as quickly as possiblethat is
clearly what we are after and the progress group
is keeping on top of the contractors to try to
ensure that that happens. However, as we have
already explained, the business of the glazing
and blast proofing could have had a dramatic
effect on the progress of the contract. Had last
Friday's blast test failed, we would be coming to
the committee today to report a serious
situation there are no two ways about that.
Happily, the blast test was passed. Although we
have to take account of the fact that the test
had to happen in the first place, that is part of
the risk review that is taking place at the
moment. The major concerns that we would have had
if the blast test had failed have not
materialised. We are therefore able to come to
the committee with good news on that particular
point because passing the test removes what was
probably the single biggest risk that remained on
the contract.