AGS RSVP Weekly Meeting - PowerPoint PPT Presentation

About This Presentation
Title:

AGS RSVP Weekly Meeting

Description:

Perform a detailed survey of cable trays and cables, etc. to assess conditions ... Tom Kirk is responsible for the review and will be conducted a committee ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 16
Provided by: cad53
Learn more at: https://www.c-ad.bnl.gov
Category:
Tags: ags | rsvp | cable | meeting | tom | weekly

less

Transcript and Presenter's Notes

Title: AGS RSVP Weekly Meeting


1
AGS RSVP Weekly Meeting16 Dec 2004
  • Agenda
  • Review updates (pile)
  • Status of cost scrubbing and resource loaded
    schedules (must be complete by 15 Jan, in time
    for the 18-20 LOG review), in addition to what
    has been done, SHOW ROAD MAP TO COMPLETION! -
    (Brown,Pendzick,Phillips and Pearson)
  • Beam development plan, Case 1 and 2 update
    (Ahrens)
  • Useful Links
  • RSVP Project http//rsvp.bnl.gov
  • C-AD AGS Project Office http//server.c-ad.bnl.
    gov/esfd/RSVP/RSVP_AGS_WBS.htm

2
4-5 Nov 04 AGS Review - Update
  • Committee Report is on the web at
  • http//server.c-ad.bnl.gov/esfd/RSVP/RSVP_AGS_WBS.
    htm
  • I havent received guidance from the RSVP Project
    Office concerning this documentread it and stay
    tuned

3
4-5 Nov 04 AGS Review - Update
  • Some Comments from the report Executive Summary
  • The Committee concluded that the proposed scope
    of new work accounting for the increased budget
    requests was reasonable and clearly desirable.
  • Only in the area of Beam Development was the
    Committee able to suggest a significant potential
    cost saving, namely reducing the planned time of
    this activity from five to two years, which the
    Upgrade team agreed was worth examining.
  • The Committee further recommends that all
    elements of the plan be subjected to future
    reviews to scrub technical content, costs and
    schedules.
  • Since overall project cost remains a major issue
    and threat to the project, the AGS Upgrade and
    Experimental Project Teams are challenged to
    collaborate on finding imaginative solutions to
    cost reduction.

4
4-5 Nov 04 AGS Review
  • Recommendations Booster/AGS Technical Issues
  • Perform a detailed survey of cable trays and
    cables, etc. to assess conditions that must be
    repaired for safety reasons. Refine cost
    estimates accordingly.
  • Assess risks of repair activities causing safety
    problems with at risk but still serviceable
    cables. Design plan to minimize costs of repairs
    while maintaining safety.
  • Consider the impact of limiting upgrades of those
    items specifically designed to make RSVP more
    convenient to operate, as opposed to unable to
    operate. Assess cost benefits in areas of
    controls, improvement of PFN kickers etc.
  • Assess impact on RHIC if magnet/ coil replacement
    plan is limited in scope. Compare with present
    status of backup and likely downtime if a magnet
    fails during present operation. Many magnets do
    not have backups. Work out ALARA repair scenarios
    for present vs. more highly activated conditions.
  • For the RF and Feedback systems, refine the
    conceptual designs with appropriate experienced
    RF engineering, generate resource-loaded
    schedules and revise cost estimates.
  • Develop a contingency plan if the present plan
    fails to produce the required extinction
    performance.

5
4-5 Nov 04 AGS Review
  • Recommendations Switchyard and Experiment Beams
    Technical Issues
  • Freeze production angle, beam aspect ratio as
    soon as possible so detailed design can begin.
  • Continue design of Beam Development plan to
    optimize (minimize) cost impact.
  • Continue developing requirements for experiment
    interfaces so detailed conceptual design and
    resource-loaded schedules can proceed.

6
4-5 Nov 04 AGS Review
  • Recommendations Costs
  • Organize detailed Cost scrubbing reviews of all
    Booster, AGS and Switchyard major components as
    soon as feasible.
  • Consider Table 2.2-1 to suggest possible
    deferment or later staging of portions of
    proposed upgrade plan with possible later
    addition as needed during operations.
  • Freeze detector locations, parameters,
    collimating devices as soon as possible to
    minimize engineering costs.
  • Consider cost models constraining RSVP to (i)
    only RHIC operation (ii) inside or outside RHIC
    operation to finish total experimental schedule
    as rapidly as possible.
  • Consider if KOPIO can be designed to use some or
    all of existing nearby pit.
  • Explore if BNL laboratory funds may legitimately
    be used to offset some of the AGS/ Booster
    reliability improvements.
  • Consider shortening the beamline commissioning
    (Beam Development) program if necessary at cost
    of lower quality beams during initial 1-2 years.

7
4-5 Nov 04 AGS Review
  • Recommendations Schedule
  • Investigate ways to achieve an accelerated,
    significantly shorter commissioning and
    experimental operating schedule. Consider both
    Life-Cycle and Opportunity Costs.
  • Investigate reducing the execution time of the
    AGS Upgrade by
  • an accelerated development program, and
  • reducing scope wherever possible to minimize time
    to completion of installation and commissioning.
    Consider supporting planned incremental upgrades
    on an as-needed basis during future operational
    downtimes to reduce costs.

8
4-5 Nov 04 AGS Review
  • Recommendations Management
  • Complete drafts of the Project Execution and
    Project Management Plans including an accurate
    assessment of the key technical risks, realistic
    analyses of cost risks through detailed
    bottom-up modeling, realistic personnel planning
    across the board aided by resource-loaded
    schedules, and a critical evaluation of
    availability of personnel to match the needed
    ramp-up.
  • b. Once the draft plans and supporting work are
    complete, the RSVP project managers should
    organize reviews to strongly focus on technical
    justification, cost and schedule scrubbing of
    overall system scope and key subsystem
    components, particularly those requiring RD.
  • c. RSVP management needs to challenge the entire
    RSVP Team to explore together imaginative ways
    to eliminate, reduce or defer construction costs.
    Some possibilities are
  • Constrain proposed upgrades to items vital to
    meeting the RSVP minimum beam requirements and
    non-interference with RHIC.
  • Explore deferment of changes that are designed
    mainly to minimize MTTR for RHIC, such as
    stocking of magnet spares, replacement of
    controls systems, redesign of kicker magnet
    drivers, etc. to later as needed repairs or
    upgrades.
  • Explore a future operating fund set-aside for
    repairs on an as-needed basis.
  • Significantly reduce or eliminate Beam
    Development proposal designed to prepare beams
    for maximum levels on Day One of experimental
    engineering and data runs.
  • Explore global changes to plan to reduce
    life-cycle costs such as more rapid completion of
    MECO while initially delaying KOPIO buying more
    running hours earlier to accelerate completion of
    MECO without beam sharing with KOPIO buying more
    running hours later to accelerate KOPIO
    completion.
  • Consider capital costs, operating costs,
    Life-Cycle costs and (lost) Opportunity costs in
    all scenarios.

9
RSVP Cost and Schedule Review, 9 Dec 2004
  • Guidance, agenda and presentations can be found
    at http//rsvp.bnl.gov/Project_Office/Reviews/RSV
    PCSDec2004.htm
  • Attendees Goldberg (NSF), Firestone, Willis,
    Kotcher, Kirk,
  • Hebert, Marx, Pile, Littenberg, Bryman, Zeller,
    Molzon (telephone)
  • An outcome of the meeting
  • Cost Roll-up of RSVP
  • WBS 1.1 RSVP Project Office 20.5M
  • WBS 1.2 K0PI0 106.9M
  • WBS 1.3 MECO 94.6M plus (several omissions
    not added in)
  • WBS 1.4 AGS 69.2M (with 3 years beam
    development)
  • TOTAL 292.1M plus
  • i.e. Costs are now an openly recognized problem
    for the NSF..

10
RSVP Detector Capabilities, Simulations and
Backgrounds Review (11-13 Jan 2005 at NYU)
We are not directly involved (Don, Wuzheng,
Kevin, Kin (1 day) and I will attend as observers)
  • RSVP Simulation and Background Review Committee
  • Ed Blucher, University of Chicago
  • Martin Cooper, Los Alamos
  • Cy Hoffman, Los Alamos
  • Patty McBride, Fermilab
  • Jack Ritchie (Chair), University of Texas, Austin
  • Mike Shupe, University of Arizona
  • Bob Tschirhart, Fermilab
  • Koji Yoshimura, Osaka University
  • Charge and Agenda
  • http//server.c-ad.bnl.gov/esfd/RSVP/simulations_c
    harge_agenda.pdf
  • Detailed agenda is in preparation

11
Resource Loaded Schedule Review(18-20 Jan 2005)
  • Tom Kirk is responsible for the review and
    will be conducted a committee appointed by Tom,
    the Laboratory Oversight Group (LOG)
  • Guidance from RSVP Project Office
  • It will be a cost and schedule review, delving
    as deeply as possible into the justifications for
    each, documentation, etc..charge and agenda
    should be out this weeka close look at the cost
    and schedule, their basis, and the backup
    documentation -- both in place, and in planning.
  • Subsystem Managers will be directly involved in
    this review!

12
Guidance our plan(subject to change we have
not yet received guidance from Willis/Kotcher as
result of the 10-12 Oct MECO Magnet, 4-5 Nov AGS,
and 9 Dec Cost and Schedule Reviews changes
since 18 Nov meeting is red)
  • Continue cost scrubbing and schedule development
  • Highest priority to AGS/BOOSTER WBS 1.4.1
  • Cost scrubbing, what can we postpone until
    operations phase? etc
  • Schedule in particular a plan to get the
    AGS/BOOSTER in shape for high intensity beam
    development --- by beginning of 3rd year of
    construction?
  • Beam development plan that fits within constant
    effort RHIC budget scenario with 2 beams i.e.
    figure on 80 hrs/week and 15 weeks/year
  • Case 1 Beam development during entire 5 year
    construction period (looking less and less
    likely)
  • Case 2 Beam development beginning 3rd year of
    construction
  • The construction plan should be developed
    consistent with no beam development in first two
    years of the project (Case 2 above) unless short
    run(s) outside RHIC operations is (are)
    critically needed
  • D-line decommissioned
  • C-Line available beginning of 3rd year for tests
  • theres a risk (small) that we may have to revert
    back to the original plan (Case 1).
  • All costs scrubbed and resource loaded schedules
    available for review for all major projects with
    DRAFT first pass at full integration into a
    master schedule deadline, 15 Jan 05, needed for
    Kirks 18-20 Jan LOG Review.. All experiment/AGS
    interface issues are not expected to be resolved
    by this date
  • Use AGS Project Office account number for this
    work!

13
next significant events
14
Message from Steve Kane (today) We have
implemented web-based reporting to provide status
tracking and simplify input. The new Reporting
Center also provides an archive for the monthly
reports. You can get to the reporting center via
the RSVP Project Office web page,
http//rsvp.bnl.gov/Project_Office/RSVPProjectOffi
ce.htm, or you can go directly to the RSVP
Reporting Center at http//www.c-ad.bnl.gov/rsvp/r
svp_index.pl. The RSVP Reporting Center should be
used for the December RSVP Monthly Report. The
pages are intended to be self-explanatory, but
please e-mail if you have questions or
problems. So Al, Kevin, Dave and Charlie
enter your monthly reports directly into the
system by the end of each month (Im out of the
loop! except for editorial changes and Project
Office input)
15
Next Meeting
  • 30 Dec 2004
  • Agenda
  • Status of cost scrubbing and resource loaded
    schedules (must be complete by 15 Jan, in time
    for the 18-20 LOG review), in addition to what
    has been done, SHOW ROAD MAP TO COMPLETION! -
    (Brown,Pendzick,Phillips and Pearson)
  • Beam development plan, Case 1 and 2 update
    (Ahrens)
Write a Comment
User Comments (0)
About PowerShow.com