Title: AGS RSVP Weekly Meeting
1AGS RSVP Weekly Meeting16 Dec 2004
- Agenda
- Review updates (pile)
- Status of cost scrubbing and resource loaded
schedules (must be complete by 15 Jan, in time
for the 18-20 LOG review), in addition to what
has been done, SHOW ROAD MAP TO COMPLETION! -
(Brown,Pendzick,Phillips and Pearson) - Beam development plan, Case 1 and 2 update
(Ahrens)
- Useful Links
- RSVP Project http//rsvp.bnl.gov
- C-AD AGS Project Office http//server.c-ad.bnl.
gov/esfd/RSVP/RSVP_AGS_WBS.htm
24-5 Nov 04 AGS Review - Update
- Committee Report is on the web at
- http//server.c-ad.bnl.gov/esfd/RSVP/RSVP_AGS_WBS.
htm - I havent received guidance from the RSVP Project
Office concerning this documentread it and stay
tuned
34-5 Nov 04 AGS Review - Update
- Some Comments from the report Executive Summary
- The Committee concluded that the proposed scope
of new work accounting for the increased budget
requests was reasonable and clearly desirable. - Only in the area of Beam Development was the
Committee able to suggest a significant potential
cost saving, namely reducing the planned time of
this activity from five to two years, which the
Upgrade team agreed was worth examining. - The Committee further recommends that all
elements of the plan be subjected to future
reviews to scrub technical content, costs and
schedules. - Since overall project cost remains a major issue
and threat to the project, the AGS Upgrade and
Experimental Project Teams are challenged to
collaborate on finding imaginative solutions to
cost reduction.
44-5 Nov 04 AGS Review
- Recommendations Booster/AGS Technical Issues
- Perform a detailed survey of cable trays and
cables, etc. to assess conditions that must be
repaired for safety reasons. Refine cost
estimates accordingly. - Assess risks of repair activities causing safety
problems with at risk but still serviceable
cables. Design plan to minimize costs of repairs
while maintaining safety. - Consider the impact of limiting upgrades of those
items specifically designed to make RSVP more
convenient to operate, as opposed to unable to
operate. Assess cost benefits in areas of
controls, improvement of PFN kickers etc. - Assess impact on RHIC if magnet/ coil replacement
plan is limited in scope. Compare with present
status of backup and likely downtime if a magnet
fails during present operation. Many magnets do
not have backups. Work out ALARA repair scenarios
for present vs. more highly activated conditions. - For the RF and Feedback systems, refine the
conceptual designs with appropriate experienced
RF engineering, generate resource-loaded
schedules and revise cost estimates. - Develop a contingency plan if the present plan
fails to produce the required extinction
performance.
54-5 Nov 04 AGS Review
- Recommendations Switchyard and Experiment Beams
Technical Issues - Freeze production angle, beam aspect ratio as
soon as possible so detailed design can begin. - Continue design of Beam Development plan to
optimize (minimize) cost impact. - Continue developing requirements for experiment
interfaces so detailed conceptual design and
resource-loaded schedules can proceed.
64-5 Nov 04 AGS Review
- Recommendations Costs
- Organize detailed Cost scrubbing reviews of all
Booster, AGS and Switchyard major components as
soon as feasible. - Consider Table 2.2-1 to suggest possible
deferment or later staging of portions of
proposed upgrade plan with possible later
addition as needed during operations. - Freeze detector locations, parameters,
collimating devices as soon as possible to
minimize engineering costs. - Consider cost models constraining RSVP to (i)
only RHIC operation (ii) inside or outside RHIC
operation to finish total experimental schedule
as rapidly as possible. - Consider if KOPIO can be designed to use some or
all of existing nearby pit. - Explore if BNL laboratory funds may legitimately
be used to offset some of the AGS/ Booster
reliability improvements. - Consider shortening the beamline commissioning
(Beam Development) program if necessary at cost
of lower quality beams during initial 1-2 years.
74-5 Nov 04 AGS Review
- Recommendations Schedule
- Investigate ways to achieve an accelerated,
significantly shorter commissioning and
experimental operating schedule. Consider both
Life-Cycle and Opportunity Costs. - Investigate reducing the execution time of the
AGS Upgrade by - an accelerated development program, and
- reducing scope wherever possible to minimize time
to completion of installation and commissioning.
Consider supporting planned incremental upgrades
on an as-needed basis during future operational
downtimes to reduce costs.
84-5 Nov 04 AGS Review
- Recommendations Management
- Complete drafts of the Project Execution and
Project Management Plans including an accurate
assessment of the key technical risks, realistic
analyses of cost risks through detailed
bottom-up modeling, realistic personnel planning
across the board aided by resource-loaded
schedules, and a critical evaluation of
availability of personnel to match the needed
ramp-up. - b. Once the draft plans and supporting work are
complete, the RSVP project managers should
organize reviews to strongly focus on technical
justification, cost and schedule scrubbing of
overall system scope and key subsystem
components, particularly those requiring RD. - c. RSVP management needs to challenge the entire
RSVP Team to explore together imaginative ways
to eliminate, reduce or defer construction costs.
Some possibilities are - Constrain proposed upgrades to items vital to
meeting the RSVP minimum beam requirements and
non-interference with RHIC. - Explore deferment of changes that are designed
mainly to minimize MTTR for RHIC, such as
stocking of magnet spares, replacement of
controls systems, redesign of kicker magnet
drivers, etc. to later as needed repairs or
upgrades. - Explore a future operating fund set-aside for
repairs on an as-needed basis. - Significantly reduce or eliminate Beam
Development proposal designed to prepare beams
for maximum levels on Day One of experimental
engineering and data runs. - Explore global changes to plan to reduce
life-cycle costs such as more rapid completion of
MECO while initially delaying KOPIO buying more
running hours earlier to accelerate completion of
MECO without beam sharing with KOPIO buying more
running hours later to accelerate KOPIO
completion. - Consider capital costs, operating costs,
Life-Cycle costs and (lost) Opportunity costs in
all scenarios.
9RSVP Cost and Schedule Review, 9 Dec 2004
- Guidance, agenda and presentations can be found
at http//rsvp.bnl.gov/Project_Office/Reviews/RSV
PCSDec2004.htm - Attendees Goldberg (NSF), Firestone, Willis,
Kotcher, Kirk, - Hebert, Marx, Pile, Littenberg, Bryman, Zeller,
Molzon (telephone) - An outcome of the meeting
- Cost Roll-up of RSVP
- WBS 1.1 RSVP Project Office 20.5M
- WBS 1.2 K0PI0 106.9M
- WBS 1.3 MECO 94.6M plus (several omissions
not added in) - WBS 1.4 AGS 69.2M (with 3 years beam
development) - TOTAL 292.1M plus
- i.e. Costs are now an openly recognized problem
for the NSF..
10RSVP Detector Capabilities, Simulations and
Backgrounds Review (11-13 Jan 2005 at NYU)
We are not directly involved (Don, Wuzheng,
Kevin, Kin (1 day) and I will attend as observers)
- RSVP Simulation and Background Review Committee
- Ed Blucher, University of Chicago
- Martin Cooper, Los Alamos
- Cy Hoffman, Los Alamos
- Patty McBride, Fermilab
- Jack Ritchie (Chair), University of Texas, Austin
- Mike Shupe, University of Arizona
- Bob Tschirhart, Fermilab
- Koji Yoshimura, Osaka University
- Charge and Agenda
- http//server.c-ad.bnl.gov/esfd/RSVP/simulations_c
harge_agenda.pdf - Detailed agenda is in preparation
11Resource Loaded Schedule Review(18-20 Jan 2005)
- Tom Kirk is responsible for the review and
will be conducted a committee appointed by Tom,
the Laboratory Oversight Group (LOG) - Guidance from RSVP Project Office
- It will be a cost and schedule review, delving
as deeply as possible into the justifications for
each, documentation, etc..charge and agenda
should be out this weeka close look at the cost
and schedule, their basis, and the backup
documentation -- both in place, and in planning. - Subsystem Managers will be directly involved in
this review!
12Guidance our plan(subject to change we have
not yet received guidance from Willis/Kotcher as
result of the 10-12 Oct MECO Magnet, 4-5 Nov AGS,
and 9 Dec Cost and Schedule Reviews changes
since 18 Nov meeting is red)
- Continue cost scrubbing and schedule development
- Highest priority to AGS/BOOSTER WBS 1.4.1
- Cost scrubbing, what can we postpone until
operations phase? etc - Schedule in particular a plan to get the
AGS/BOOSTER in shape for high intensity beam
development --- by beginning of 3rd year of
construction? - Beam development plan that fits within constant
effort RHIC budget scenario with 2 beams i.e.
figure on 80 hrs/week and 15 weeks/year - Case 1 Beam development during entire 5 year
construction period (looking less and less
likely) - Case 2 Beam development beginning 3rd year of
construction - The construction plan should be developed
consistent with no beam development in first two
years of the project (Case 2 above) unless short
run(s) outside RHIC operations is (are)
critically needed - D-line decommissioned
- C-Line available beginning of 3rd year for tests
- theres a risk (small) that we may have to revert
back to the original plan (Case 1). - All costs scrubbed and resource loaded schedules
available for review for all major projects with
DRAFT first pass at full integration into a
master schedule deadline, 15 Jan 05, needed for
Kirks 18-20 Jan LOG Review.. All experiment/AGS
interface issues are not expected to be resolved
by this date - Use AGS Project Office account number for this
work!
13next significant events
14Message from Steve Kane (today) We have
implemented web-based reporting to provide status
tracking and simplify input. The new Reporting
Center also provides an archive for the monthly
reports. You can get to the reporting center via
the RSVP Project Office web page,
http//rsvp.bnl.gov/Project_Office/RSVPProjectOffi
ce.htm, or you can go directly to the RSVP
Reporting Center at http//www.c-ad.bnl.gov/rsvp/r
svp_index.pl. The RSVP Reporting Center should be
used for the December RSVP Monthly Report. The
pages are intended to be self-explanatory, but
please e-mail if you have questions or
problems. So Al, Kevin, Dave and Charlie
enter your monthly reports directly into the
system by the end of each month (Im out of the
loop! except for editorial changes and Project
Office input)
15Next Meeting
- 30 Dec 2004
- Agenda
- Status of cost scrubbing and resource loaded
schedules (must be complete by 15 Jan, in time
for the 18-20 LOG review), in addition to what
has been done, SHOW ROAD MAP TO COMPLETION! -
(Brown,Pendzick,Phillips and Pearson) - Beam development plan, Case 1 and 2 update
(Ahrens)