Landslide Risk Management - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Landslide Risk Management

Description:

You can add a subtitle here Land Risk Management Westlynn and Pemberton Heights Escarpments Land Risk Assessment Presentation to District Council – PowerPoint PPT presentation

Number of Views:1544
Avg rating:3.0/5.0
Slides: 20
Provided by: ScottBr3
Category:

less

Transcript and Presenter's Notes

Title: Landslide Risk Management


1
You can add a subtitle here
  • Landslide Risk Management
  • Westlynn and Pemberton Heights Escarpments
  • Landslide Risk Assessment
  • Presentation to District Council
  • December 3, 2008
  • Michael Porter, Sam Fougere
  • BGC Engineering Inc.

1 of 19
2
Outline Westlynn and Pemberton Heights
Escarpments
  • Landslide Risk Management Program
  • Preliminary Landslide Hazard Assessment (Nov 07)
  • Risk Scenarios, Recommendations
  • Landslide Risk Assessment (Nov 08)
  • Risk Estimation Individual and Societal Risk
  • Risk Evaluation
  • Remediation Options
  • Recommendations

2 of 19
3
Study Areas
Westlynn
Pemberton Heights
3 of 19
4
Landslide Risk Management Program
Nov 2007 Report
Nov 2008 Report
Nov 2008 Report
Nov 2008 Report
4 of 19
5
Preliminary Landslide Hazard Assessment
  • Completed in November, 2007
  • Four main landslide risk scenarios identified
  • - based on presence or absence of evidence of
    slope instability and the presence or absence of
    homes at the base of the escarpment
  • INCREASING RISK from A to
    D

RISK SCENARIO RESIDENTIAL DEVELOPMENT AT THE BASE OF THE SLOPE HISTORIC LANDSLIDE ACTIVITY OR POTENTIALLY HAZARDOUS CONDITION IDENTIFIED
A NO NO
B YES NO
C NO YES
D YES YES
5 of 19
6
Preliminary Landslide Hazard Assessment
  • Recommendations (Nov 07)
  • Scenario A no further work
  • Scenario B periodic geotech review
  • Scenario C remotely possible these sites may
    pose unacceptable individual or societal risk
  • Scenario D may pose unacceptable individual
    or societal risk but further investigation
    required to conclude this

6 of 19
7
Follow-up Risk Assessment - Site Selection
  • DNV retained BGC to conduct follow-up risk
    assessment for the Scenario D points of
    interest
  • Sites/properties investigated about 30 m either
    side of Scenario D points of interest
  • 11 Points of Interest 24 Properties

7 of 19
8
Landslide Risk Estimation
  • Risk PSLIDE x N (fatalities per year)
  • (Risk Hazard x Consequence)
  • Consequence expected number of fatalities
  • N PSH x PTS x V x E

Based on position of homes and runout behaviour
of previous slides on the Berkley Escarpment
based on consequences of previous slides at the
Berkley Escarpment
12 to 16 hrs per day
4 people per home
8 of 19
9
Landslide Runout
  • Consequence a function of the angle to the crest
    of the escarpment

9 of 19
10
Risk Evaluation
  • Interim landslide risk tolerance criteria for
    existing developments
  • Tolerable Risk 10-4 per year (110,000 chance)
  • ALARP principal demands lower risk, where
    practical
  • In early 2008, DNVs Natural Hazards Task Force
    recommended continued use of the interim criteria

10 of 19
11
Individual Risk Estimates
  • Risk faced by a single individual exposed to one
    or more landslide hazards
  • Interim Tolerance Criteria
  • Existing slopes 10-4 per year (110,000)
  • New development 10-5 per year (1100,000)

11 of 19
12
Individual Risk Estimates
  • Identified as shaded properties on the report
    maps
  • One Unacceptable Red Zone Property (gt10-4)
  • but drainage improvements implemented prior to
    completion of this study
  • 14 ALARP Yellow Zone Properties (10-4 10-5)
  • 12 properties at the base of the escarpment
  • 2 properties at the crest of the escarpment

12 of 19
13
Societal Risk Estimates
  • Risk imposed upon society by a single landslide
  • Interim Tolerance Criteria
  • F-N Curves

13 of 19
14
Societal Risk Estimates
  • No Unacceptable Zones Properties
  • 18 ALARP Zone
  • 6 Broadly Acceptable
  • Shown as Yellow or Blue stars on the report maps

14 of 19
15
Discussion
  • Landslide risk assessment addresses risk of loss
    of life from landslides triggered by heavy
    rainfall
  • Landslide risks in the vicinity of the Scenario
    D points of interest are currently tolerable
  • Risks are lower than found along the Berkley
    Escarpment (generally less fill less development
    at the base of the escarpments)
  • Keep risks under review and reduce further, if
    practical (ALARP)

15 of 19
16
Remedial Options
  • Drainage improvements, followed by fill removal,
    found to be most cost effective

16 of 19
17
Recommendations
  • Encourage homeowners along crest of escarpments
    to connect their downpipes to the storm drain
    system
  • Continue to provide educational material to the
    public about how to reduce landslide risk when
    living near steep slopes (pamphlet in circulation
    at present)
  • Prioritize Scenario C sites for follow-up risk
    assessment once results of other preliminary
    landslide studies are available

17 of 19
18
Five Landslide Preliminary Study Areas
  • Preliminary landslide study areas work in
    progress at
  • Capilano River East
  • Mosquito Creek
  • Mount Fromme East
  • Deep Cove
  • Riverside West
  • Reports due February 2009

18 of 19
19
  • Thank you
  • Report available at
  • www.dnv.org

19 of 19
Write a Comment
User Comments (0)
About PowerShow.com