Culvert Design - PowerPoint PPT Presentation

About This Presentation
Title:

Culvert Design

Description:

Culvert Design Material Selection Central Office Hydraulics Steps for Material Selection Field Review Culvert Hydraulics Structural Strength Service Life Material ... – PowerPoint PPT presentation

Number of Views:352
Avg rating:3.0/5.0
Slides: 34
Provided by: jsy1
Category:

less

Transcript and Presenter's Notes

Title: Culvert Design


1
Culvert Design
  • Material Selection
  • Central Office Hydraulics

2
Steps for Material Selection
  • Field Review
  • Culvert Hydraulics
  • Structural Strength
  • Service Life
  • Material Analysis
  • Plan Alternates

3
Field Review
  • Determine pH of the water
  • Use an instrument that is capable of accuracy of
    0.1
  • Use Figures 1002-2 through 1002-3 only if no flow
    is present when performing the field check

4
Do not use unless there is no flow when
performing the site visit.
5
Field Review
  • Determine if there is a presence of abrasive
    material.
  • Abrasive Material Presence of gravel, stones,
    or a course sand in the barrel of an existing
    conduit (or in the existing stream bed) that has
    a stream gradient or flow sufficient to cause
    movement of the abrasive material.
  • Assume abrasive conditions if there is any
    question about the bed material.

6
Abrasive Condition
7
Non-Abrasive Condition
8
Field Review
  • Investigate the condition of existing structures.
  • If a replacement structure, look at the existing
    structure.
  • If a new structure look at any adjacent existing
    structures.

9
Culvert Hydraulics
  • Use approved methods outlined in the Location and
    Design, Volume 2 Manual

10
Structural Strength
  • Structural strength for Metal Conduits (steel and
    aluminum)
  • Select the gauge thickness and corrugation
    profile that is adequate (based upon fill
    height).
  • Figures 1008-1 through 1008-9 (steel)
  • Figures 1008-15 through 1008-21 (aluminum) (NOT
    Aluminized)

11
(No Transcript)
12
Structural Strength
  • Structural Strength for Concrete Conduits
  • Select the D-load that is adequate for structural
    strength (based upon fill height).
  • Figures 1008-10 through 1008-14

13
(No Transcript)
14
Service Life
  • Service life is either 50 or 75 years
  • Use 50 years as a minimum .
  • Use 75 years for high fills (gt16), under
    freeways, or where future costs may be high to
    replace the structure.

15
Service Life
  • Durability for Metal Conduits
  • Use the obtained pH and abrasiveness observation
    to determine the gauge thickness.
  • Use figures 1002-5(50) through 1002-6(75) the
    general notes for the figures.

16
(No Transcript)
17
Service Life
  • Durability for Concrete Conduits
  • Check for adequate service life based upon the
    pH, pipe slope, and pipe rise.
  • Use figure 1002-4.

18
(No Transcript)
19
Material Analysis
  • For metal conduit, choose the higher gauge
    thickness from the structural design, or the
    durability analysis.
  • When durability thickness is higher than
    structural thickness, provide the 1-inch
    corrugation profile for pipe diameters over 48
    inches.

20
Plan Alternates
  • Place all available material options in the plan
    (all metal alternatives and concrete).
  • In some cases, only one material may be specified
    in the plan
  • If the outlet velocity in a concrete pipe
    requires a ring chamber and the velocity of the
    metal alternative is below 20fps, then metal may
    be used exclusively.
  • When encountering excessive cover for a concrete
    pipe.

21
Plan Alternates
  • Where a larger corrugated metal pipe would
    require a higher pavement grade to satisfy
    minimum cover requirements, concrete may be used
    exclusively.
  • Where a metal pipe arch is required hydraulically
    and a round concrete pipe would work, concrete
    may be used exclusively.
  • Do not need to specify minimum D-loads or minimum
    gauge thicknesses in the item call-out.

22
Plan Alternates
  • Show the following in the plan
  • D-load or gauge thickness if it is above the
    minimum shown in the specifications.
  • The conduit shown in the plans should be the
    longest length pipe (the smallest diameter).
  • Hydraulic Design Information
  • Other information (see LD, Vol. 3, Section
    1312.2)

23
Example Problem
  • Given
  • Hydraulic design requires 96 inch corrugated or
    90 inch smooth lined
  • Outlet velocities
  • Corrugated V17.0 fps Smooth lined V21.0 fps
  • Height of cover 18 feet
  • Under a new alignment (minor state route)
  • pH was measured and found to be 7.5

24
Design Example
Photo from creek Is this Abrasive?
25
Example Problem
  • Select the appropriate design alternatives.
  • As per LD, we will exclude concrete conduit in
    the design due to the velocity of 21 fps.
  • Durability Design
  • Site was determined to be abrasive in nature
  • A design service life of 75 years will be used
    due to the high fill height.
  • Use Figure 1002-6(75) for the durability design

26
(No Transcript)
27
Example Problem
  • Options from figure notes are
  • 10 gauge 707.02 Aluminum Coated
  • 12 gauge 707.07 Aluminized Asphalt Coated
    Paved
  • 14 gauge 707.04 Polymer Coated with 1
    corrugations
  • 16 gauge 707.04 Polymer Coated Asphalt Coated
    Paved
  • 16 gauge 707.02 with Concrete Field Paving
  • 1 gauge 707.03
  • 12 gauge 707.03 with Concrete Field Paving
  • 707.22 (aluminum pipe) with Concrete Field Paving

28
Example Problem
  • Structural Design of Metal Conduit
  • Use Figure 1008-1 1008-3 to check for maximum
    height of cover

29
(No Transcript)
30
(No Transcript)
31
Example Problem
  • A gauge thickness of 0.064 (16 gauge) will be
    satisfactory up to a fill height of 31 feet for
    all steel options except for 707.03 (structural
    plate).
  • A gauge thickness of 0.109 (12 gauge) will be
    satisfactory up to a fill height of 29 feet for
    steel structural plate.
  • A thickness of 0.105 (the minimum for this size)
    will be satisfactory up to a fill height of 20
    feet for aluminum pipe.
  • A thickness of 0.100 (the minimum for this size)
    will be satisfactory up to a fill height of 20
    feet for aluminum structural plate.

32
Example Problem
  • Specifying in the Plan
  • Specify the alternative as per LD, Volume 3,
    Section 1312.3.
  • For this example it would be as follows
  • 603 180 L.F. 96 Conduit, Type A 707.02 (0.138)
    Aluminized, 707.02 with CFP, 707.03 (0.280),
    707.03 with CFP, 707.04 (1) (0.079) Polymer
    Coated, 707.04 (1) Polymer Coated Asphalt Coated
    and Paved, 707.07 (0.109) Aluminized Asphalt
    Coated and Paved, 707.22 with CFP, 707.23 with
    CFP

33
Questions ?
Write a Comment
User Comments (0)
About PowerShow.com