Title: Early Environmental Coordination for Design Projects
1Early Environmental Coordination for Design
Projects
2Yearly Advertising Program
- 400 million FY 1991
- 470 million FY 2004
- 600 million (projected) FY 2005
- 500 600 million out years
3Statewide Transportation Improvement Program
(STIP)
- Fiscally Constrained Need to advertise
everything that is in the STIP - FY 2003 Only Advertised 30
- FY 2004 Only Advertised 56
- FY 2005 Targeted Goal 100
4Transportation Need versusAvailable Funding
- Increase advertising
- Improve meeting STIP Targets (Planning)
- Improve accountability in Federal Programming
(Funding) - Increased credibility of yearly advertising
program
5Elements for Advertising
- Plans, Specifications and Estimates (PS E)
- All necessary permits obtained
- Rights of Way acquisition (ROW)
6Project Development Process
- Design Schedule within control of consultant
- Design Review Schedule within control of
MassHighway
7Environmental Approvals
- Applications set schedule
- Agency review varies
- Many approval processes are sequential
8What We Can Control
- Understanding of permit application requirements
- Understanding of approval process and schedules
- Limit number of surprises
9Coordination During Project Development
- Environmental Approvals
- Context Sensitive Design
- Communities First
- Smart Growth
10Early Environmental Coordination
- Goal
- Receipt of all permits coincides with 100-percent
design submittal
11Schedule (24-month timeline)
NOTICE TOPROCEED
100 DesignPSE
25 Design
96 weeks
40 weeks
104 weeks
75 Design
Notice of Intent(30-60 days) MEPA (45
days) ACOE Section 404(60 days) Section
4(f)(120-180 days) Water QualityCertification(
120-150 days)
12Early Coordination for Design Projects
- Community issues
- Environmental issues
- Design parameters
- Permit identification
- Context-sensitive solutions
- 25 design plans
13Plan Ahead for Permit Process
- Permit section of contract is starting point
- Field work can reveal unexpected conditions
- Advanced design can identify further unexpected
impacts
14(No Transcript)
15Plan Ahead for Permit Process
- Permit section of contract is starting point
- Field work can reveal unexpected conditions
- Advanced design can identify unexpected impacts
16Existing Conditions
- Office research
- Field work
- Document results in Early Environmental
Coordination 25 Design Submittal
17Early EnvironmentalChecklist
18Existing Conditions
- Office research
- Field work
- Document results in Early Environmental
Coordination 25 Design Submittal
19Coordination/Office Research
- Send Letter to Local Historic Commission
- Send Letters to other Local Boards, Commissions,
and interested parties - Review known hazardous material releases with
local Fire Department - Send letter to Massachusetts Natural Heritage
Program - Send letter to Federal Resource Agencies
20On-Line Information
- MassHighway Environmental Section
www.mass.gov/mhd/environ - Department of Environmental Protection
www.mass.gov/dep - Army Corps of Engineerswww.nae.usece.mil/
- MassGISwww.mass.gov/mgis/
21MassHighway Environmental
22Sample Letters
23Sample Forms
24MassGIS
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30Existing Conditions
- Office research
- Field work
- Document results in Early Environmental
Coordination 25 Design Submittal
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35(No Transcript)
36(No Transcript)
37(No Transcript)
38(No Transcript)
39(No Transcript)
40(No Transcript)
41(No Transcript)
42(No Transcript)
43(No Transcript)
44(No Transcript)
45(No Transcript)
46(No Transcript)
47(No Transcript)
48Existing Conditions
- Office research
- Field work
- Document results in Early Environmental
Coordination 25 Design Submittal
49Early EnvironmentalChecklist
50Put Field Data on Plans
- Existing and proposed drainage structures
- Bridges, culverts within/adjacent to project
limits - Include all MassHighway structure numbers
- Label all historical/locally significant
monuments and markers - Publicly-owned parks
- Label tops and bottom of slopes with
takings/easements
51Sample Plan
52Proposed Alignment
53Proposed Toe of Slope
54Wetland and Water Resources
- Wetland Resources within 100 feet of project
limits - Show location of wetland replacement and
compensatory flood storage - Bridge rehabilitation/replacement photos of four
quadrants
55(No Transcript)
56Wetland Delineation
57Trees with Diameter 14 inches
58Cultural Resources
- Show all bridges and culverts with MassHighway
numbers - Illustrate historic buildings/structures/district
boundaries - Provide photos
- Label street address
- Label significant monuments/markers
- Detail of typical street light
59(No Transcript)
60Historic Stone Wall
61Culverts or Bridges(with MHD )
62Property Lines and Building Footprints
63Include Office Research
- Letters and correspondence from local Boards
- Letters from State/Federal Agencies
- Photos of historic structures
- Photos of river banks where work will occur
64Schedule (24-month timeline)
NOTICE TOPROCEED
100 DesignPSE
25 Design
96 weeks
40 weeks
104 weeks
75 Design
Notice of Intent(30-60 days) MEPA (45
days) ACOE Section 404(60 days) Section
4(f)(120-180 days) Water QualityCertification(
120-150 days)
65(No Transcript)
66Questions