Detours – Selection and Design - PowerPoint PPT Presentation

1 / 87
About This Presentation
Title:

Detours – Selection and Design

Description:

Detours Selection and Design Highways & Engineering Conference March 2, 2006 Presenters: Paul Ferry, Highways Engineer Lesly Tribelhorn, Highways Design Engineer ... – PowerPoint PPT presentation

Number of Views:28
Avg rating:3.0/5.0
Slides: 88
Provided by: mdtMtGov
Learn more at: http://www.mdt.mt.gov
Category:

less

Transcript and Presenter's Notes

Title: Detours – Selection and Design


1
Detours Selection and Design
  • Highways Engineering Conference
  • March 2, 2006

2
(No Transcript)
3
(No Transcript)
4
Presenters
  • Paul Ferry, Highways Engineer
  • Lesly Tribelhorn, Highways Design Engineer

5
Objectives
  • Know which types of detours are appropriate
  • Apply proper design criteria
  • Consider safety and costs
  • Think about environmental, other site constraints
  • Know where to look for information

6
Types of Detours
7
Types of Detours
  • Detour traffic onto an existing route
  • Temporary detour
  • Median crossovers (divided highways)
  • Lane closures
  • Part-width construction

8
Interstate/Freeway
9
Interstate/Freeway
  • Median crossovers design considerations
  • Guardrail
  • Bridge widths
  • Interchange proximity and access
  • Review distance between crossovers
  • Location (topography, geometrics, distance
    between)
  • Drainage
  • Future projects

10
Interstate/Freeway
  • Median crossovers safety
  • Ingress/egress controlled
  • Interstate standards met
  • Two-way traffic
  • Cross over of traffic
  • No passing

11
Interstate/Freeway
  • Median crossovers cost considerations
  • Construct remove crossover
  • Traffic control (length, maintenance)
  • Guardrail revisions
  • Median crossovers site constraints
  • Topography considerations for crossover location
  • No environmental
  • No R/W

12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
(No Transcript)
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
(No Transcript)
38
(No Transcript)
39
(No Transcript)
40
Interstate/Freeway
  • Lane closure design considerations
  • Bridge widths
  • Temporary barrier rail
  • Length of area to be protected
  • Barrier deflection
  • Taper rates
  • End treatment

41
Interstate/Freeway
  • Lane closure safety
  • Directional traffic separated
  • Interstate standards met
  • Access controlled
  • Excavation located next to travel lane
  • Bridge work extended duration
  • No passing

42
Interstate/Freeway
  • Lane closure cost considerations
  • Traffic control
  • Lane closure site constraints
  • Interchange locations

43
Interstate/Freeway
  • Temporary detours design considerations
  • Usually for culvert replacement in high fill
  • May need temporary widening, barrier rail
  • Jack and bore instead (48 diameter)?
  • Need temporary access control fence?
  • Proximity of interchanges

44
Interstate/Freeway
  • Temporary detours safety
  • Short length
  • Driver expectations violated
  • Temporary detours cost considerations
  • Construction removal of detour
  • Traffic control minimized

45
Interstate/Freeway
  • Temporary detours site constraints
  • Environmental involvement possible
  • R/W, access fence possible

46
Interstate/Freeway
  • Detour traffic onto an existing route
  • Bridge widths, structural capacity, clearance
  • Road surfacing and structure
  • Roadway width
  • Safety issues (mixing traffic, accesses,
    standards)
  • Clear zone
  • Length and duration of detour
  • Costs - traffic control and surfacing improvement

47
Interstate/Freeway
48
Two-lane rural routes
49
Two-lane rural routes
  • Detour onto an existing route - design
  • Cost of temporary detour excessive?
  • Bridge widths and capacity
  • Adequate clearance
  • Roadway widths and structural capacity
  • Clear zone
  • Work with construction and maintenance

50
Two-lane rural routes
  • Detour onto an existing route
  • Safety depends on route selected
  • Costs minimal traffic control, route
    maintenance
  • Site constraints should be minimal

51
Two-lane rural routes
  • Temporary detours

52
(No Transcript)
53
Two-lane rural routes
  • Temporary detours
  • Replacement of drainage structures
  • Excavation leaves insufficient room for traffic

54
(No Transcript)
55
Design Criteria temporary detours
56
Alignment
  • Design speed
  • Route design speed 10 mph
  • Location
  • Duration
  • Sight distance

57
Alignment
  • Location
  • Topography which side most economical
  • Utility impacts
  • R/W issues
  • Environmental impacts
  • Impacts to adjacent developments
  • Accesses

58
Alignment
  • Request adequate survey for proper design
  • Offset and detour length
  • Normal crown horizontal curves
  • Adequate cover over culverts
  • Bridge freeboard
  • Downstream location preferred

59
Surfacing
  • Traffic loading
  • Detour duration

60
(No Transcript)
61
Roadway Width
  • 24 adequate for most
  • ADT lt 400, consider narrower lanes
  • 10 11
  • Two-way, one lane

62
Grading/side slopes
  • Typically 31
  • Traffic volumes
  • Detour duration
  • Temporary barrier
  • Geotech involvement!
  • Detour embankment part of roadway?

63
Drainage
  • Size provided by Hydraulics
  • Address sequencing for flowing streams

64
Safety and costs
  • Safety level varies
  • Design
  • Traffic
  • Driver expectations
  • Costs can be significant
  • Construction and removal
  • R/W, utility moves
  • Traffic control and maintenance

65
Environmental considerations
66
(No Transcript)
67
Environmental considerations
  • Coordinate with district biologist
  • Special construction methods for streams
  • Wetland, historic, archaeological site avoidance

68
Part-width construction
  • Design considerations
  • Low speed environment?
  • Wide enough for oversize loads?
  • Bridges impacted?
  • Practical locations available for temp. detour?
  • Can temporary barrier rail reduce widening?

69
Part-width construction
  • Safety can be compromised
  • Driver expectation sudden speed reduction?
  • Design may be necessary
  • Offset by short construction time
  • Cost savings can be significant
  • Evaluate environmental, R/W involvement

70
(No Transcript)
71
Lane closures
  • Special case for two-lane highway
  • Costs or construction issues for other detour
    types
  • Safety compromised - very short duration only
  • 24-hour flaggers for safety
  • Short length preferred (sight distance, safety)
  • Costs low traffic control only
  • Environmental, other impacts minimal

72
Two-lane rural routes
73
Other options?
74
Other options?
  • Offset alignment and use PTW
  • Detours for drainage installation not needed
  • More efficient construction operation
  • Enhanced safety
  • Jack and bore
  • Road closures

75
Urban construction
76
Urban construction
  • Pedestrian/ADA access
  • Utility considerations
  • Emergency vehicle access
  • Impacts to businesses
  • Public relations
  • Worker safety

77
Urban construction
  • Costs and safety comparisons
  • Depend on work, location
  • Specific to project

78
Urban construction
  • Detour traffic onto an existing route
  • Close one block at a time
  • Sequencing and coordination

79
Urban construction
  • Existing route detour considerations
  • Additional traffic loads on adjacent streets
  • Surfacing improvements necessary?
  • Pedestrian/ADA accommodation
  • Business access signing critical
  • Hospital, residences, school access

80
Urban construction
  • Lane closures
  • Room to accommodate traffic and construction work
  • Need positive separation for utility work in
    trenches?
  • Access to businesses - may need detour
  • Pedestrian/ADA access on both sides of street

81
Urban construction
  • Temporary detour median crossovers
  • Usually impractical
  • Costs
  • Adequate room

82
Safety features compromise
  • Detour traffic onto an existing route
  • Temporary detour
  • Median crossovers (divided highways)
  • Lane closures
  • Part-width construction

83
General questions to address
84
General questions to address
  • ADT and truck traffic emergency vehicle use
  • Site considerations
  • Can the road be closed to through traffic?
  • Are there adjacent projects?
  • Are there other projects that may be affected?
  • Detour onto another construction project
  • Wide loads

85
Summary
  • Types of detours
  • Types of highway
  • Considerations
  • Design issues
  • Cost comparisons
  • Safety compromises
  • Environmental impacts other site constraints

86
Resources
  • MDT Road Design Manual 2006
  • Chapter 15
  • AASHTO A Policy on Geometric Design of Highways
    and Streets (Green Book) 2004
  • AASHTO Guidelines for Geometric Design of Very
    Low-Volume Local Roads (ADT lt 400) 2001

87
Resources
  • Paul Ferry
  • (406) 444-6244
  • pferry_at_mt.gov
  • Lesly Tribelhorn
  • (406) 444-6242
  • ltribelhorn_at_mt.gov
Write a Comment
User Comments (0)
About PowerShow.com