Title: Design of Open Channels and Culverts
1Design of Open Channels and Culverts
2Transverse Slopes
- Removes water from pavement surfaces in shortest
amount of time possible
3Longitudinal Slopes
- Gradient longitudinal direction of highway to
facilitate movement of water along roadway
4Drains
- Along ROW
- Collect surface water
A typical intercepting drain placed in the
impervious zone http//www.big-o.com/constr/hel-
cor.htm
5Drainage Channels (Ditches)
- Design
- Adequate capacity
- Minimum hazard to traffic
- Hydraulic efficiency
- Ease of maintenance
- Desirable design (for safety) flat slopes,
broad bottom, and liberal rounding
6Ditch Shape
- Trapezoidal generally preferred considering
hydraulics, maintenance, and safety - V-shaped less desirable from safety point of
view and maintenance
7(No Transcript)
8Flow Velocity
- Depends on lining type
- Typically 1 to 5 slopes used
- Should be high enough to prevent deposit of
transported material (sedimentation) - For most linings, problem if S lt 1
- Should be low enough to prevent erosion (scour)
- For most types of linings, problem if S gt 5
9Use spillway or chute if ?elev is large
10Rip Rap for drainage over high slope
11Side Ditch/Open Channel Design-Basics
- Find expected Q at point of interest (see
previous lecture) - Select a cross section for the slope, and any
erosion control needed - Mannings formula used for design
- Assume steady flow in a uniform channel
12Mannings Formula
-
- V R2/3S1/2 (metric) V 1.486
R2/3S1/2 - n n
- where
- V mean velocity (m/sec or ft/sec)
- R hydraulic radius (m, ft) area of the cross
section of flow (m2, ft2) divided by wetted
perimeter (m,f) - S slope of channel
- n Mannings roughness coefficient
13Side Ditch/Open Channel Design-Basics
- Q VA
- Q discharge (ft3/sec, m3/sec)
- A area of flow cross section (ft2, m2)
- FHWA Hydraulic Design Charts
- FHWA has developed charts to solve Mannings
equation for different cross sections
14(No Transcript)
15Open Channel Example
- Runoff 340 ft3/sec (Q)
- Slope 1
- Mannings 0.015
- Determine necessary cross-section to handle
estimated runoff - Use rectangular channel 6-feet wide
16Open Channel Example
- Q 1.486 R2/3S1/2
- n
- Hydraulic radius, R a/P
- a area, P wetted perimeter
P
17Open Channel Example
- Flow depth d
- Area 6 feet x d
- Wetted perimeter 6 2d
Flow depth (d)
6 feet
18Example (continued)
- Q 1.486 a R2/3S1/2
- n
- 340 ft3/sec 1.486 (6d) (6d)2/3 (0.01)1/2
- (6 2d)
- 0.015
- d ? 4 feet
- Channel area needs to be at least 4 x 6
19Example (continued)
- Find flow velocities.
- V 1.486 R2/3S1/2
- n
- with R a/P 6 ft x 4 ft 1.714
- 2(4ft) 6ft
- so, V 1.486(1.714)2/3 (0.01)1/2 14.2 ft/sec
- 0.015
- If you already know Q, simpler just to do
- VQ/A 340/24 14.2)
20(No Transcript)
21Example (continued)
- Find critical velocities.
- From chart along critical curve, vc ? 13 ft/sec
- Critical slope 0.007
- Find critical depth yc (q2/g)1/3
- g 32.2 ft/sec2
- q flow per foot of width
- 340 ft3/sec /6 feet 56.67ft2/sec
- yc (56.672/32.2)1/3 4.64 feet gt depth of 4
22Check lining for max depth of flow
23(No Transcript)
24Rounded
25A cut slope with ditch
26A fill slope
27Inlet or drain marker
28Ditch treatment near a bridge US 30 should pier
be protected?
29A fill slope
30(No Transcript)
31(No Transcript)
32Median drain
33Culvert Design - Basics
- Top of culvert not used as pavement surface
(unlike bridge), usually less than 20 foot span - gt 20 feet use a bridge
- Three locations
- Bottom of Depression (no watercourse)
- Natural stream intersection with roadway
(Majority) - Locations where side ditch surface drainage must
cross roadway
34Hydrologic and Economic Considerations
- Alignment and grade of culvert (with respect to
roadway) are important - Similar to open channel
- Design flow rate based on storm with acceptable
return period (frequency)
35Culvert Design Steps
- Obtain site data and roadway cross section at
culvert crossing location (with approximation of
stream elevation) best is natural stream
location, alignment, and slope (may be expensive
though) - Establish inlet/outlet elevations, length, and
slope of culvert
36Culvert Design Steps
- Determine allowable headwater depth (and probable
tailwater depth) during design flood control on
design size f(topography and nearby land use) - Select type and size of culvert
- Examine need for energy dissipaters
37Headwater Depth
- Constriction due to culvert creates increase in
depth of water just upstream - Allowable level of headwater upstream usually
controls culvert size and inlet geometry - Allowable headwater depth depends on topography
and land use in immediate vicinity
38Types of culvert flow
- Type of flow depends on total energy available
between inlet and outlet - Inlet control
- Flow is controlled by headwater depth and inlet
geometry - Usually occurs when slope of culvert is steep and
outlet is not submerged - Supercritical, high v, low d
- Most typical
- Following methods ignore velocity head
39(No Transcript)
40Ans.
Example Design ElevHW 230.5 Stream bed at
inlet 224.0 Drop 6.5 Flow 250cfs 5x5
box HW/D 1.41 HW 1.41x5 7.1 Need 7.1,
have 6.5 Drop box 0.6 below stream - OK
41Types of culvert flow
- Outlet control
- When flow is governed by combination of headwater
depth, entrance geometry, tailwater elevation,
and slope, roughness, and length of culvert - Subcritical flow
- Frequently occur on flat slopes
- Concept is to find the required HW depth to
sustain Q flow - Tail water depth often not known (need a model),
so may not be able to estimate for outlet control
conditions
42(No Transcript)
43Example Design ElevHW 230.5 Flow 250cfs 5x5
box Stream elev at inlet 240 200
culvert Outlet invert 240-0.02x200
220.0 Given tail water depth 6.5 Check
critical depth 4.3 from fig. 17.23 (next
page) Depth to hydraulic grade line (dcD)/2
4.7 lt 6.5, use 6.5 Head drop 3.3 (from
chart) 220.06.53.3 229.8lt230.5 OK
44(No Transcript)