Title: Attitude Control System
1Section 19 Attitude Control System
. . . Paul Sanneman EO-1 ACS Lead Systems
Engineer, Swales Aerospace, Inc.
2Contents
- Attitude Control Subsystem Block Diagram
- Changes since March 2000 Red Team Review
- Thermal/Vacuum II Evaluation
- Open Problem Reports
- Special Topics
- IRU Removal and Reinstallation
- On-orbit Testing of Safe Hold Mode
- Autonomous Star Tracker Issues (including IMAGE
AST issue)
3ACS Architecture Block Diagram
4As Run Verification Matrix
5Projected Power On Time
6Changes Since Red Team Review
- ACS Components
- AST ACDS DC/DC Converter lid stiffeners (see
Special Topic) - Removed IRU to prevent helium exposure (see
Special Topic) - ACE Software
- ACE RSN S/W update to Version 3.11 on 8-JUN-00
- PTR0927 Generic Code modified to have IRAM2
checksum protection on had been missed since ACE
is the only RSN with the extended RAM capability - PTR0939 Prevent ACE 25 Hz Event Messages and use
telemetry error counters instead - Code changes tested on 8-JUN-00 416 failure
free hours - M5 ACS Software
- Minor parameter changes via M5 Table loads to RAM
- Related to improving operation issues - no S/C
safety issues
7Summary of Open Items fromMarch Red Team Review
(1 of 2)
- Verification Matrix, no update necessary (page
18-14) - Updated operating hours included on Slide 7-5
(page 18-15) - PR 674-20-41 AST number of stars issue (page
18-19) - Confirmed this is a star field simulator issue
(see Slide 19-9) - GPS tensor warm start ground procedures (page
18-20) - Fully tested and available in MOC ASIST
- No updates to SHM from final CPT (page 18-34)
- Updates to remaining work
- AST/IRU alignmentdetailed in Slide 19-10
- Conclusion of AST DC/DC Converter concern (18-40)
- See Special Topic on AST DC/DC Converter
8Summary of Open Items fromMarch Red Team Review
(2 of 2)
- Updated summary of IRU PDV history (page 18-49)
- Details in Special Topic. No outstanding
performance issues. - SIRU return to spacecraft (page 18-57)
- Details in Special Topic. Reintegration
successful. Degradation reversed. - Open actions from ACS Phasing Review (page 18-63)
- CPT phasing tests following final MV S/W load
-completed - CSS phasing following final solar array
attachment -completed - Final magnetic phasing completed on 28-JUL-00 -
no issues
9Thermal Vacuum II Test Results
- Attitude Control Subsystem performance validated
as part of CPT segments and via other special
tests - All CPT associated tests run at hot and cold
plateaus - RWA Overspeed protection verified at hot and cold
plateaus - AST Thermal Electric Cooler operation modes
verified - AST TEC default state and Effective Focal Length
changed/restored during T/V II as demonstration
of planned on-orbit maintenance procedures - IRU internal heater control of gyro platform
validated
10Reaction Wheel Assemblies
- RWA performance has been verified in both air and
vacuum - Control torques issued by override and
closed-loop software - Overall run-up and coast down trends have been
verified with vendor and are summarized on next
page - T/V II testing of overspeed protection provided
below with wheel speeds in RPM
11RWA Run-up / Coast Down Trend Table
Trending data is consistent over time. Estimated
drag torque very consistent and near 50 of spec
level
12Critical PR Status
- PR-468-20-4 IRU Parametric Drive Voltage
- See Special Topic
- PR-674-20-41 AST Number of Stars 18
- Issue and problem report have been closed
- Similar operation noted on the MAP ASTs during
Thermal/Vac testing at the component level - Investigation of MAP occurrence with AST-GSE
confirmed this is a Star Field Stimulator GSE
issue - Contamination on lens of GSE can cause double
reflection that causes a match with a very dim
star in the AST internal star catalog
13ACS Flight Readiness
- ACS components and hardware are ready
- ACS and ACE software are ready
- ACE Safehold Mode is ready
- Ops preparations/training are ready
- Remaining Work
- No outstanding problems or issues
- AST/IRU alignment measurements at launch site
- Red Book Item IRU sensitivity to helium exposure
- Under control via upgraded purge system on S/C
and at launch site
Attitude Control Subsystem is READY
14Special Topic Star Tracker Issues
. . . Wayne Roher Litton Advanced Systems
15AST Interpoint DC/DC Converters Failure Mode
- MAP experienced failure with 15V DC/DC
converter - MAP2 - Open failure during ATP at ambient after
Thermal/Vacuum - DPA indicate inadequate stress relief on internal
bond wire, insufficient solder, and solid
adhesive attachment to lid caused bond wire to
pull away from pad in vacuum. - EO-1 AST X-ray investigation
- The two DC/DC converters on the EO-1 AST were
X-rayed and found to have met the criteria
determined by Code 562 as having sufficient
relief distance from the transformer. - Code 562 speculated that an additional failure
mode exists - Oil canning of converter package could cause
adhesive on bottom of transformer to release.
Transformer would move upward with package lid,
causing transformer bond wire to pull away even
if adequate stress relief existed for normal
operation in a vacuum.
16AST Interpoint DC/DC ConvertersRework
- Lockheed Martin Palo Alto and Lockheed Martin
Mission Success agreed that this failure mode
potential justified corrective action. - Stiffening the lid to prevent oil canning was
determined to be the best solution to address all
concerns of stress, unattached adhesives, and
vibration. - Lid stiffener of 20 mil Kovar and minimum 5 mil
bond line of epoxy was added to both D/CDC
converters. (See Converter Lid Stiffening
Special Topic) - Both converters tested to deflect less that 1 mil
in vacuum
17AST Interpoint DC/DC ConverterRework Conclusion
- Retest
- AST workmanship vibration
- AST Functional on Spacecraft
- AST CPT on Spacecraft
- Spacecraft level T/V
- 272 hours on time since lid stiffener was added
- Conclusion
- EO-1 AST has successfully completed all testing
post lid stiffening - EO-1 AST is ready for flight
18Other Subsystem DC/DC Converter Rework and
Re-Qualification
- All MTRxxD type Interpoint DC/DC Converters were
considered as potentially defective due to the
failure mode detected on the MAP AST2 - Two other Subsystems contained Converters that
required rework - GPS PCU (1)
- ACDS box (2) CDH LVPC and ACE I/O cards
19GPS PCU DC/DC Converter
- Rework and Re -Qualification process of GPS PCU
- Removed from Spacecraft
- Added stiffener lids, 40 mil Kovar, 10 mil
minimum bond line - Vacuum test, deflection less than I mil
- One Axis workmanship vibration
- Functional on Spacecraft
- CPT on Spacecraft
- Spacecraft level Thermal Vacuum
- Conclusion
- No anomalies recorded
- GPS PCU is ready for flight
20ACDS DC/DC Converters
- Rework and Re -Qualification process of ACDS
- Box removed from Spacecraft, CDH LVPC and ACE
I/O boards removed - Added stiffener lids, 40 mil Kovar, 10 mil
minimum bond line - Vacuum test, deflection less than I mil
- Board level functional tests
- Boards reassembled in ACDS chassis
- Pre-vibe box level Functional Test run
- One Axis workmanship vibration
- Post-vibe box level Functional Test run
- Spacecraft Integration tests
- CPT on Spacecraft
- Spacecraft level Thermal Vacuum
- Conclusion
- No unexplained anomalies recorded
- ACDS is ready for flight
21Image AST Anomaly
- The IMAGE AST was unable to acquire between June
9 and August August 3 - The AST remained in standby mode during this
time power was not recycled - On August 3, the AST re-acquired
- 1.4 degree angle further from the sun than on
June 9 - Dropped out twice during that day, quickly
recovered - Has not dropped out since.
22Image AST Anomaly Investigation
- A Failure Review Board (FRB) was held to
determine potential causes of the AST acquisition
failure. - Stray Light is the most probable root cause
- Housekeeping nominal (voltages, temperatures)
- Increased elevated background and reduction in
guide star identification were observed during
and leading up to the failure to acquire after a
loss of track. - Periodic trending occurred nearest the sun loss
of track and re-acquisition. Symptoms got worse
as sun angle decreased. - Symptoms improved and re-acquisition was attained
during eclipse portion of the the orbit. - No increase in brightness or position error was
found. - All observation are symptomatic of stray light
effects.
23Image AST Anomaly Investigation
- Straylight analysis indicates the AST should have
been able operate under the current mission
attitude. - The IMAGE AST uses a lightshade (or baffle)
designed to keep the sun or Earth out of the
boresight (within 12.5 degrees) with no
redirected light within 15.1 degrees of the
boresight. - Image minimum bore sight axis to the sun in July
at loss of track was 22 -42 degrees (AST is 10
degrees off spin axis) - Most likely sources of Stray light are
- Contamination
- Glint from 10 Meter Boom
- Contributions from CCD Mask
24Differences Between Image EO-1
- Sun Angle
- Image AST approaches within 4 degrees of the Sun
- Lost track at 22-42 degrees
- EO-1 AST approaches within 70 degrees of the Sun
for nominal nadir pointing operations - Baffle differences
- Image
- 16 inches
- 12.5 degrees of protection from sun
- EO-1
- 12 inches
- 30 degrees of protection from sun
25Results of Image AST Anomaly and Investigation
- Lockheed believes the anomaly occurred due to
unknown form of contamination - Evidence indicates the AST did not experience a
functional failure of the electronics - Data indicates the AST is functioning nominally
and the data is good - Lockheeds preliminary conclusion of the anomaly
event and investigation analysis is that this
event is not a systemic failure of the ASTs and
does not impact the expected reliability of the
ASTs built for other missions. - Formal conclusion of the FRB is expected late
August - Lockheed believes EO-1s AST is ready for flight.
26What Happens If the AST Fails?
- AST has been extensively tested on S/C and
performance has been nominal. All issues have
been aggressively pursued. - Demonstrated reliability of product line is less
than desirable. - Error prone manufacturing and test efforts
- Similar AST on DSI failed 15 months into mission
- Flight dynamics ground based attitude
determination could achieve 1 to 5 degree
pointing accuracy - Would allow Landsat 7 limited image comparison
since we would be within its 15 degree swath
width - Ground attitude estimate developed using TAM and
gyro data - Current flight ACS S/W has capability to use
daily uploaded attitude estimate, propagated
using gyro data - Would require some ground software to prepare and
uplink daily attitude data would be developed if
AST fails. Sun sensor safehold used until
software developed.
27Special Topic IRU Removal and Re-installation
. . . Paul Sanneman EO-1 ACS Lead Systems
Engineer, Swales Aerospace, Inc.
28SIRU Nitrogen Purge - Background
- Litton Guidance Control Space Inertial
Reference Unit - Utilizes three Hemispherical Resonator Gyros
(HRGs) - Quartz crystal hemisphere oscillated at specific
amplitude and frequency - Input angular rate measured by nodal displacement
on rim - Quartz crystal becomes permeated with Helium
- Increases gaseous damping, requires larger drive
voltage - Parametric Drive Voltage (defined as a
negative voltage) - Not an issue prior to arrival at GSFC Building 7
- Significant amounts of Helium released in
Building 7 by environmental chamber testing
processes
29Summary of PDV History
30Gyro A PDV Slope Estimate
31PDV Trends Since S/C Thermal/Vac
32SIRU Return To Spacecraft
- Re-integration performed 11-MAY-00
- Building 7 air sampling validated low helium
concentration - Building 7 air under constant He monitoring using
leak detector - Continue to have close coordination with Building
7 operations personnel to further minimize
exposure - Re-integration included new aluminum-wrapped
Teflon tube inside spacecraft and stainless steel
tube from S/C to tank - Gyro Parametric Drive Voltages indicate that both
the storage at Swales and the upgraded purge
system have reversed the degradation
33Outlook
- Mechanical and launch vehicle I/F engineers have
focused activity for IRU protection throughout
remaining S/C IT at GSFC, during transport and
launch site processing - The increased PDV is NOT a performance issue -
just needs to stay within (-5V) capability - About one volt of margin required for full 10
deg/sec rate capability - Desire PDV values of 3.5 V (_at_25C) at time of SC
mount on LV - PDV Voltages on 28-JULY-00 A-2.66, B-2.23, C
-2.50 _at_23C - Purge installation on Launch Vehicle (L/V) has
been improved to the extent allowable by the L/V
vendor/operator - Expect Parametric Drive Voltage to remain stable
or slight improvement through launch and will
slowly recover over the course of the mission -
residual risk has been minimized
34Special Topic On-Orbit Testing of Safe Hold Mode
. . . Paul Sanneman EO-1 ACS Lead Systems
Engineer, Swales Aerospace, Inc.
35RFA 33.33
- Reviewer Ann Merwarth
- Specific Request
- Hold a technical peer review with operations
experts from outside the project to identify the
pros and cons of conducting the safemode test on
orbit. Review the results with Center and Program
management and ensure that all parties "buy into"
the plan for this test. If the Project decides to
do this test, we recommend that it be delayed as
long as possible. - EO-1 Response Peer review held on 20 APR 2000
- Chaired by Eric Holmes, GSFC Code 571 GNC
Systems Engineering - Board members Alan Reth, Sam Placanica, Landis
Markley
36Summary of Peer Review
- Review Agenda
- Review Team Introductions and Purpose
- Safe Hold Mode Implementation
- Safe Hold Mode Reviews
- Safe Hold Mode Testing during S/C IT
- On-orbit SHM Test Plans for Two tests
- Benefit/Risk Summary for On-orbit SHM Test
- Review Conclusion
- The review panel unanimously agreed with the plan
to proceed with the planned on-orbit test of SHM
with the following actions to Swales Aerospace
37Peer Review Action Items
- Action 1 (by Sam Placanica)
- Verify that all instruments can survive dwelling
on the Sun for at least 10 minutes. - ACS, Thermal and Systems investigated and
determined that there is enough attitude
variation following SHM entry to prevent
instrument thermal issues - Action 2 (by Sam Placanica)
- The duration of the SHM shall be at least 1
complete orbit. - This is now included in the launch early orbit
mission plan. - Action 3 (by review panel)
- Augment test 1 as follows Have the solar array
outside of the 5 degree "indexed" tolerance at
the time SHM is initiated, so that SHM's indexing
function via ECU2 and Pot 2 are demonstrated. - STOL procedure ACS_SAD_10 developed and tested to
perform this function prior to commanded SHM
entry - Second SHM test removed from mission plan as
there was limited benefit and timing would be
obtrusive to instrument activation/checkout
All action items closed. RFA 33.33 closed.