Attitude Control System - PowerPoint PPT Presentation

1 / 37
About This Presentation
Title:

Attitude Control System

Description:

NMP EO-1 DELTA PRE-SHIP REVIEW. Summary of Open Items from. March Red Team Review (1 of 2) ... NMP EO-1 DELTA PRE-SHIP REVIEW. Thermal Vacuum II Test Results ... – PowerPoint PPT presentation

Number of Views:422
Avg rating:4.0/5.0
Slides: 38
Provided by: paulsanne
Category:

less

Transcript and Presenter's Notes

Title: Attitude Control System


1
Section 19 Attitude Control System
. . . Paul Sanneman EO-1 ACS Lead Systems
Engineer, Swales Aerospace, Inc.
2
Contents
  • Attitude Control Subsystem Block Diagram
  • Changes since March 2000 Red Team Review
  • Thermal/Vacuum II Evaluation
  • Open Problem Reports
  • Special Topics
  • IRU Removal and Reinstallation
  • On-orbit Testing of Safe Hold Mode
  • Autonomous Star Tracker Issues (including IMAGE
    AST issue)

3
ACS Architecture Block Diagram
4
As Run Verification Matrix
5
Projected Power On Time
6
Changes Since Red Team Review
  • ACS Components
  • AST ACDS DC/DC Converter lid stiffeners (see
    Special Topic)
  • Removed IRU to prevent helium exposure (see
    Special Topic)
  • ACE Software
  • ACE RSN S/W update to Version 3.11 on 8-JUN-00
  • PTR0927 Generic Code modified to have IRAM2
    checksum protection on had been missed since ACE
    is the only RSN with the extended RAM capability
  • PTR0939 Prevent ACE 25 Hz Event Messages and use
    telemetry error counters instead
  • Code changes tested on 8-JUN-00 416 failure
    free hours
  • M5 ACS Software
  • Minor parameter changes via M5 Table loads to RAM
  • Related to improving operation issues - no S/C
    safety issues

7
Summary of Open Items fromMarch Red Team Review
(1 of 2)
  • Verification Matrix, no update necessary (page
    18-14)
  • Updated operating hours included on Slide 7-5
    (page 18-15)
  • PR 674-20-41 AST number of stars issue (page
    18-19)
  • Confirmed this is a star field simulator issue
    (see Slide 19-9)
  • GPS tensor warm start ground procedures (page
    18-20)
  • Fully tested and available in MOC ASIST
  • No updates to SHM from final CPT (page 18-34)
  • Updates to remaining work
  • AST/IRU alignmentdetailed in Slide 19-10
  • Conclusion of AST DC/DC Converter concern (18-40)
  • See Special Topic on AST DC/DC Converter

8
Summary of Open Items fromMarch Red Team Review
(2 of 2)
  • Updated summary of IRU PDV history (page 18-49)
  • Details in Special Topic. No outstanding
    performance issues.
  • SIRU return to spacecraft (page 18-57)
  • Details in Special Topic. Reintegration
    successful. Degradation reversed.
  • Open actions from ACS Phasing Review (page 18-63)
  • CPT phasing tests following final MV S/W load
    -completed
  • CSS phasing following final solar array
    attachment -completed
  • Final magnetic phasing completed on 28-JUL-00 -
    no issues

9
Thermal Vacuum II Test Results
  • Attitude Control Subsystem performance validated
    as part of CPT segments and via other special
    tests
  • All CPT associated tests run at hot and cold
    plateaus
  • RWA Overspeed protection verified at hot and cold
    plateaus
  • AST Thermal Electric Cooler operation modes
    verified
  • AST TEC default state and Effective Focal Length
    changed/restored during T/V II as demonstration
    of planned on-orbit maintenance procedures
  • IRU internal heater control of gyro platform
    validated

10
Reaction Wheel Assemblies
  • RWA performance has been verified in both air and
    vacuum
  • Control torques issued by override and
    closed-loop software
  • Overall run-up and coast down trends have been
    verified with vendor and are summarized on next
    page
  • T/V II testing of overspeed protection provided
    below with wheel speeds in RPM

11
RWA Run-up / Coast Down Trend Table
Trending data is consistent over time. Estimated
drag torque very consistent and near 50 of spec
level
12
Critical PR Status
  • PR-468-20-4 IRU Parametric Drive Voltage
  • See Special Topic
  • PR-674-20-41 AST Number of Stars 18
  • Issue and problem report have been closed
  • Similar operation noted on the MAP ASTs during
    Thermal/Vac testing at the component level
  • Investigation of MAP occurrence with AST-GSE
    confirmed this is a Star Field Stimulator GSE
    issue
  • Contamination on lens of GSE can cause double
    reflection that causes a match with a very dim
    star in the AST internal star catalog

13
ACS Flight Readiness
  • ACS components and hardware are ready
  • ACS and ACE software are ready
  • ACE Safehold Mode is ready
  • Ops preparations/training are ready
  • Remaining Work
  • No outstanding problems or issues
  • AST/IRU alignment measurements at launch site
  • Red Book Item IRU sensitivity to helium exposure
  • Under control via upgraded purge system on S/C
    and at launch site

Attitude Control Subsystem is READY
14
Special Topic Star Tracker Issues
. . . Wayne Roher Litton Advanced Systems
15
AST Interpoint DC/DC Converters Failure Mode
  • MAP experienced failure with 15V DC/DC
    converter
  • MAP2 - Open failure during ATP at ambient after
    Thermal/Vacuum
  • DPA indicate inadequate stress relief on internal
    bond wire, insufficient solder, and solid
    adhesive attachment to lid caused bond wire to
    pull away from pad in vacuum.
  • EO-1 AST X-ray investigation
  • The two DC/DC converters on the EO-1 AST were
    X-rayed and found to have met the criteria
    determined by Code 562 as having sufficient
    relief distance from the transformer.
  • Code 562 speculated that an additional failure
    mode exists
  • Oil canning of converter package could cause
    adhesive on bottom of transformer to release.
    Transformer would move upward with package lid,
    causing transformer bond wire to pull away even
    if adequate stress relief existed for normal
    operation in a vacuum.

16
AST Interpoint DC/DC ConvertersRework
  • Lockheed Martin Palo Alto and Lockheed Martin
    Mission Success agreed that this failure mode
    potential justified corrective action.
  • Stiffening the lid to prevent oil canning was
    determined to be the best solution to address all
    concerns of stress, unattached adhesives, and
    vibration.
  • Lid stiffener of 20 mil Kovar and minimum 5 mil
    bond line of epoxy was added to both D/CDC
    converters. (See Converter Lid Stiffening
    Special Topic)
  • Both converters tested to deflect less that 1 mil
    in vacuum

17
AST Interpoint DC/DC ConverterRework Conclusion
  • Retest
  • AST workmanship vibration
  • AST Functional on Spacecraft
  • AST CPT on Spacecraft
  • Spacecraft level T/V
  • 272 hours on time since lid stiffener was added
  • Conclusion
  • EO-1 AST has successfully completed all testing
    post lid stiffening
  • EO-1 AST is ready for flight

18
Other Subsystem DC/DC Converter Rework and
Re-Qualification
  • All MTRxxD type Interpoint DC/DC Converters were
    considered as potentially defective due to the
    failure mode detected on the MAP AST2
  • Two other Subsystems contained Converters that
    required rework
  • GPS PCU (1)
  • ACDS box (2) CDH LVPC and ACE I/O cards

19
GPS PCU DC/DC Converter
  • Rework and Re -Qualification process of GPS PCU
  • Removed from Spacecraft
  • Added stiffener lids, 40 mil Kovar, 10 mil
    minimum bond line
  • Vacuum test, deflection less than I mil
  • One Axis workmanship vibration
  • Functional on Spacecraft
  • CPT on Spacecraft
  • Spacecraft level Thermal Vacuum
  • Conclusion
  • No anomalies recorded
  • GPS PCU is ready for flight

20
ACDS DC/DC Converters
  • Rework and Re -Qualification process of ACDS
  • Box removed from Spacecraft, CDH LVPC and ACE
    I/O boards removed
  • Added stiffener lids, 40 mil Kovar, 10 mil
    minimum bond line
  • Vacuum test, deflection less than I mil
  • Board level functional tests
  • Boards reassembled in ACDS chassis
  • Pre-vibe box level Functional Test run
  • One Axis workmanship vibration
  • Post-vibe box level Functional Test run
  • Spacecraft Integration tests
  • CPT on Spacecraft
  • Spacecraft level Thermal Vacuum
  • Conclusion
  • No unexplained anomalies recorded
  • ACDS is ready for flight

21
Image AST Anomaly
  • The IMAGE AST was unable to acquire between June
    9 and August August 3
  • The AST remained in standby mode during this
    time power was not recycled
  • On August 3, the AST re-acquired
  • 1.4 degree angle further from the sun than on
    June 9
  • Dropped out twice during that day, quickly
    recovered
  • Has not dropped out since.

22
Image AST Anomaly Investigation
  • A Failure Review Board (FRB) was held to
    determine potential causes of the AST acquisition
    failure.
  • Stray Light is the most probable root cause
  • Housekeeping nominal (voltages, temperatures)
  • Increased elevated background and reduction in
    guide star identification were observed during
    and leading up to the failure to acquire after a
    loss of track.
  • Periodic trending occurred nearest the sun loss
    of track and re-acquisition. Symptoms got worse
    as sun angle decreased.
  • Symptoms improved and re-acquisition was attained
    during eclipse portion of the the orbit.
  • No increase in brightness or position error was
    found.
  • All observation are symptomatic of stray light
    effects.

23
Image AST Anomaly Investigation
  • Straylight analysis indicates the AST should have
    been able operate under the current mission
    attitude.
  • The IMAGE AST uses a lightshade (or baffle)
    designed to keep the sun or Earth out of the
    boresight (within 12.5 degrees) with no
    redirected light within 15.1 degrees of the
    boresight.
  • Image minimum bore sight axis to the sun in July
    at loss of track was 22 -42 degrees (AST is 10
    degrees off spin axis)
  • Most likely sources of Stray light are
  • Contamination
  • Glint from 10 Meter Boom
  • Contributions from CCD Mask

24
Differences Between Image EO-1
  • Sun Angle
  • Image AST approaches within 4 degrees of the Sun
  • Lost track at 22-42 degrees
  • EO-1 AST approaches within 70 degrees of the Sun
    for nominal nadir pointing operations
  • Baffle differences
  • Image
  • 16 inches
  • 12.5 degrees of protection from sun
  • EO-1
  • 12 inches
  • 30 degrees of protection from sun

25
Results of Image AST Anomaly and Investigation
  • Lockheed believes the anomaly occurred due to
    unknown form of contamination
  • Evidence indicates the AST did not experience a
    functional failure of the electronics
  • Data indicates the AST is functioning nominally
    and the data is good
  • Lockheeds preliminary conclusion of the anomaly
    event and investigation analysis is that this
    event is not a systemic failure of the ASTs and
    does not impact the expected reliability of the
    ASTs built for other missions.
  • Formal conclusion of the FRB is expected late
    August
  • Lockheed believes EO-1s AST is ready for flight.

26
What Happens If the AST Fails?
  • AST has been extensively tested on S/C and
    performance has been nominal. All issues have
    been aggressively pursued.
  • Demonstrated reliability of product line is less
    than desirable.
  • Error prone manufacturing and test efforts
  • Similar AST on DSI failed 15 months into mission
  • Flight dynamics ground based attitude
    determination could achieve 1 to 5 degree
    pointing accuracy
  • Would allow Landsat 7 limited image comparison
    since we would be within its 15 degree swath
    width
  • Ground attitude estimate developed using TAM and
    gyro data
  • Current flight ACS S/W has capability to use
    daily uploaded attitude estimate, propagated
    using gyro data
  • Would require some ground software to prepare and
    uplink daily attitude data would be developed if
    AST fails. Sun sensor safehold used until
    software developed.

27
Special Topic IRU Removal and Re-installation
. . . Paul Sanneman EO-1 ACS Lead Systems
Engineer, Swales Aerospace, Inc.
28
SIRU Nitrogen Purge - Background
  • Litton Guidance Control Space Inertial
    Reference Unit
  • Utilizes three Hemispherical Resonator Gyros
    (HRGs)
  • Quartz crystal hemisphere oscillated at specific
    amplitude and frequency
  • Input angular rate measured by nodal displacement
    on rim
  • Quartz crystal becomes permeated with Helium
  • Increases gaseous damping, requires larger drive
    voltage - Parametric Drive Voltage (defined as a
    negative voltage)
  • Not an issue prior to arrival at GSFC Building 7
  • Significant amounts of Helium released in
    Building 7 by environmental chamber testing
    processes

29
Summary of PDV History
30
Gyro A PDV Slope Estimate
31
PDV Trends Since S/C Thermal/Vac
32
SIRU Return To Spacecraft
  • Re-integration performed 11-MAY-00
  • Building 7 air sampling validated low helium
    concentration
  • Building 7 air under constant He monitoring using
    leak detector
  • Continue to have close coordination with Building
    7 operations personnel to further minimize
    exposure
  • Re-integration included new aluminum-wrapped
    Teflon tube inside spacecraft and stainless steel
    tube from S/C to tank
  • Gyro Parametric Drive Voltages indicate that both
    the storage at Swales and the upgraded purge
    system have reversed the degradation

33
Outlook
  • Mechanical and launch vehicle I/F engineers have
    focused activity for IRU protection throughout
    remaining S/C IT at GSFC, during transport and
    launch site processing
  • The increased PDV is NOT a performance issue -
    just needs to stay within (-5V) capability
  • About one volt of margin required for full 10
    deg/sec rate capability
  • Desire PDV values of 3.5 V (_at_25C) at time of SC
    mount on LV
  • PDV Voltages on 28-JULY-00 A-2.66, B-2.23, C
    -2.50 _at_23C
  • Purge installation on Launch Vehicle (L/V) has
    been improved to the extent allowable by the L/V
    vendor/operator
  • Expect Parametric Drive Voltage to remain stable
    or slight improvement through launch and will
    slowly recover over the course of the mission -
    residual risk has been minimized

34
Special Topic On-Orbit Testing of Safe Hold Mode
. . . Paul Sanneman EO-1 ACS Lead Systems
Engineer, Swales Aerospace, Inc.
35
RFA 33.33
  • Reviewer Ann Merwarth
  • Specific Request
  • Hold a technical peer review with operations
    experts from outside the project to identify the
    pros and cons of conducting the safemode test on
    orbit. Review the results with Center and Program
    management and ensure that all parties "buy into"
    the plan for this test. If the Project decides to
    do this test, we recommend that it be delayed as
    long as possible.
  • EO-1 Response Peer review held on 20 APR 2000
  • Chaired by Eric Holmes, GSFC Code 571 GNC
    Systems Engineering
  • Board members Alan Reth, Sam Placanica, Landis
    Markley

36
Summary of Peer Review
  • Review Agenda
  • Review Team Introductions and Purpose
  • Safe Hold Mode Implementation
  • Safe Hold Mode Reviews
  • Safe Hold Mode Testing during S/C IT
  • On-orbit SHM Test Plans for Two tests
  • Benefit/Risk Summary for On-orbit SHM Test
  • Review Conclusion
  • The review panel unanimously agreed with the plan
    to proceed with the planned on-orbit test of SHM
    with the following actions to Swales Aerospace

37
Peer Review Action Items
  • Action 1 (by Sam Placanica)
  • Verify that all instruments can survive dwelling
    on the Sun for at least 10 minutes.
  • ACS, Thermal and Systems investigated and
    determined that there is enough attitude
    variation following SHM entry to prevent
    instrument thermal issues
  • Action 2 (by Sam Placanica)
  • The duration of the SHM shall be at least 1
    complete orbit.
  • This is now included in the launch early orbit
    mission plan.
  • Action 3 (by review panel)
  • Augment test 1 as follows Have the solar array
    outside of the 5 degree "indexed" tolerance at
    the time SHM is initiated, so that SHM's indexing
    function via ECU2 and Pot 2 are demonstrated.
  • STOL procedure ACS_SAD_10 developed and tested to
    perform this function prior to commanded SHM
    entry
  • Second SHM test removed from mission plan as
    there was limited benefit and timing would be
    obtrusive to instrument activation/checkout

All action items closed. RFA 33.33 closed.
Write a Comment
User Comments (0)
About PowerShow.com