Title: W.Ootani
1COBRA Magnet Status
- W.Ootani
- ICEPP, University of Tokyo
- MEG experiment review meeting
- Feb.11 2004, PSI
2First Excitation Test in June03
- Summary
- First excitation test was done in Japan last
June. - The test was not completed because of some
problems. - Some of the quench protection heaters were
burned. - Cold spots on the cryostat inner wall.
- Superconducting magnet was tested up to 83
excitation. - Compensation coils were successfully tested up to
110 excitation. - Field measurement device was tested.
- Field profile in the bore and fringing field
around photon detector region were roughly
measured.
3First Excitation Test in June03
Graded field profile measured at 200A
Design field
Measured field
4Problems in First Test
- Protection heaters were burned.
- All heaters were replaced with larger heaters and
back-up heaters were added. - Cold spots on the cryostat wall
- Too thick super Insulation layers in narrow gap
of the cryostat. - Radiation shield cylinder was slightly displaced.
The problems were quickly fixed and the second
excitation test was carried out last August.
5Second Excitation Test
- The second test was done in Japan last August.
- The magnet was successfully tested up to 380A
- (5.6 higher than the operating current, 360A)
- No cold spot
- No protection heater was broken.
6Quench Tests
- Quench propagation observed by voltage taps,
temperature sensors and superconducting quench
detectors (SQDs). - Severest test heater quench test at central coil
at 360A. - Quench induced by firing a heater in the central
coil, which is the farthest coil from the
refrigerator. - DC OFF and quench protection heater ON after the
quench is detected.
Quench was propagated in the magnet fast enough
to keep ?T and ?V below the acceptable level.
7SQD Reaction in Quench Test
8Voltage Change in Quench Test
- Maximum voltage across the central coil of 1200V
was observed 500msec after the quench in the
central coil.
9Temperature Rise in Quench Test
- Temperature was peaked at 110K in the central
coil 16sec after the quench occurred.
10Mechanical Strength
- Strains in the central coil and support cylinder
measured up to coil current of 380A. - Fairly linear relation between strain and I2
Sufficient mechanical strength
11COBRA arrived at PSI
- COBRA arrived at PSI Nov.1213, 2003.
- Placed in SLS hall for the initial test before
the installation in pE5, which is planned this
April. - System check after the transportation was carried
out last December and no serious problem was
found.
Power supply, compressor, mapping machine, etc
Main body
12Excitation Test at PSI
- COBRA is placed at Axis34-36 in SLS.
- Excitation test was done between Jan.17-27,2004.
- Full excitation for SC and 8 excitation for NC
because of limited utility at SLS.
COBRA in SLS hall
MEG magnet team
13Excitation Test at PSI
5.6 over excitation was successfully done.
COBRA seems to survive long journey from Japan.
14Excitation Test at PSI
Good performance was confirmed in quench test up
to 360A.
Mechanical strength
Voltage
Temperature
15Summary
- The second excitation test of the COBRA magnet
was successfully performed last August in Japan
after fixing the problems in the first test. - The magnet was tested up to 380A(5.6 higher than
normal operating current). - Good quench propagation and mechanical
performance were observed. - The magnet was transported to the PSI and placed
in SLS hall to be tested. - The excitation test was carried out in SLS hall
between Jan.17 and 27 and the magnet was
successfully tested up to 380A. - Field mapping study is starting at SLS hall and
COBRA is planned to move to pE5 this April.