Title: Overview of the experiment


1
Overview of the experiment
  • MEG is being built (Beam line, Magnet, LXe, DC,
    TC, Elect., Software)
  • Delays in some items O(months)
  • We keep the deadline of starting data taking
    when the beam will start on 2006

2
Collaboration construction responsibilities
unchanged
  • Spokespersons T.Mori, A.Baldini
  • Technical Coordinator S.Ritt
  • Detectors
  • Beam line PSI P.-R.Kettle
  • COBRA KEK/Tokyo W.Ootani
  • Drift Chamber PSI J.Egger
  • Timing Counter Genova/Pavia/Roma Cecchet/Gatti
  • Photon Detector Tokyo/Pisa/KEK S.Mihara
  • Trigger Pisa M.Grassi
  • DAQ/Elec. PSI S.Ritt
  • Offline C.Gatto/S.Yamada/F.Cei

UCI (W. Molzon)
3
Beam line BTS _at_ PSI
Dear colleagues! BTS progress report for
18.07.2005 morning - replace the Helium
transfer line 1100   - the Helium temperature
is achieved, coil is superconducting          
but Helium dewar is empty 1320   - receive full
Helium dewar 1530   - the BTS cryostat is full
1620   - ramp up current up to 30A, the field
in BTS is observed by           deflection of
steel screw, which hangs on wire at cryostat edge
...     - test and adjust quench protection
circuit 2000   - the current of 283 A is
reached The maximal current is limited by power
the supply maximal voltage and the power cable
resistance now. The BTS was tested up to 300 A at
Novosibirsk with another power supply. with
best regards,                     Dima
4
Beam line separator almost ready, experimental
area more and more crowded (platform, COBRA
barrack...)
5
COBRA mag. field measurements and comparison with
calculations going on
6
LXe calorimeter
  • Liquid phase purification successfully tested
  • PMT base modifications tested Ok
  • 110 PMTtested at Pisa (rate of about 3/day)
    starting at PSI
  • Delay in cryostat construction (3 months)
    bureaucracy steel property

With Filter, no noise observed, narrow pedestal
7
Drift chambers
  • Detailed measurements of geometry during
    construction procedure to get the final values
    and to check tools being established

Timing counter
  • APDs received OK
  • Mechanical drawing of the transverse part almost
    finished
  • Final desig of the TC electronics (long.
    tansverse) almost ready
  • He bag being studied

8
Calibrations
  • Proton accelerator int. on Li target (17.6 MeV
    ?) 50 financing from INFN 250 K how to get
    the rest ??
  • ??calibration new possibility (could be used to
    calibrate the DC system too)
  • alphas neutrons on Ni update

MEG TN027
9
Electronics
  • Trigger the test of the final boards wil be
    done in September, as foreseen in the schedule.
    On schedule
  • DRS temperature dependence to be kept under
    control. DRS3 available in 2006 will substitute
    DRS2

Software
  • MC status (BG simulation going on)
  • DATA storage and CPU estimates

10
  • No change in the expected sensitivity since last
    february
  • We consider LHC as our competitor
  • We will try to get significant results ASAP