Title: Overview of the experiment
1Overview of the experiment
- MEG is being built (Beam line, Magnet, LXe, DC,
TC, Elect., Software) - Delays in some items O(months)
- We keep the deadline of starting data taking
when the beam will start on 2006
2Collaboration construction responsibilities
unchanged
- Spokespersons T.Mori, A.Baldini
- Technical Coordinator S.Ritt
- Detectors
- Beam line PSI P.-R.Kettle
- COBRA KEK/Tokyo W.Ootani
- Drift Chamber PSI J.Egger
- Timing Counter Genova/Pavia/Roma Cecchet/Gatti
- Photon Detector Tokyo/Pisa/KEK S.Mihara
- Trigger Pisa M.Grassi
- DAQ/Elec. PSI S.Ritt
- Offline C.Gatto/S.Yamada/F.Cei
UCI (W. Molzon)
3Beam line BTS _at_ PSI
Dear colleagues! BTS progress report for
18.07.2005 morning - replace the Helium
transfer line 1100 - the Helium temperature
is achieved, coil is superconducting
but Helium dewar is empty 1320 - receive full
Helium dewar 1530 - the BTS cryostat is full
1620 - ramp up current up to 30A, the field
in BTS is observed by deflection of
steel screw, which hangs on wire at cryostat edge
... - test and adjust quench protection
circuit 2000 - the current of 283 A is
reached The maximal current is limited by power
the supply maximal voltage and the power cable
resistance now. The BTS was tested up to 300 A at
Novosibirsk with another power supply. with
best regards, Dima
4Beam line separator almost ready, experimental
area more and more crowded (platform, COBRA
barrack...)
5COBRA mag. field measurements and comparison with
calculations going on
6LXe calorimeter
- Liquid phase purification successfully tested
- PMT base modifications tested Ok
- 110 PMTtested at Pisa (rate of about 3/day)
starting at PSI - Delay in cryostat construction (3 months)
bureaucracy steel property
With Filter, no noise observed, narrow pedestal
7Drift chambers
- Detailed measurements of geometry during
construction procedure to get the final values
and to check tools being established
Timing counter
- APDs received OK
- Mechanical drawing of the transverse part almost
finished - Final desig of the TC electronics (long.
tansverse) almost ready - He bag being studied
8Calibrations
- Proton accelerator int. on Li target (17.6 MeV
?) 50 financing from INFN 250 K how to get
the rest ?? - ??calibration new possibility (could be used to
calibrate the DC system too) - alphas neutrons on Ni update
MEG TN027
9Electronics
- Trigger the test of the final boards wil be
done in September, as foreseen in the schedule.
On schedule - DRS temperature dependence to be kept under
control. DRS3 available in 2006 will substitute
DRS2
Software
- MC status (BG simulation going on)
- DATA storage and CPU estimates
10- No change in the expected sensitivity since last
february - We consider LHC as our competitor
- We will try to get significant results ASAP