MEG Overview - PowerPoint PPT Presentation

About This Presentation
Title:

MEG Overview

Description:

cooling using cold gas from the LN2 tank. ... Can be used also for initial setup. K. Bi. Tl. F. Li(p, 0) at 17.6 MeV. Li(p, 1) at 14.6 MeV ... – PowerPoint PPT presentation

Number of Views:25
Avg rating:3.0/5.0
Slides: 35
Provided by: satoshi3
Category:
Tags: meg | overview | setup | simic

less

Transcript and Presenter's Notes

Title: MEG Overview


1
MEG Overview
  • Cobra (W. Ootani)
  • LXe calorimeter (S. Mihara)
  • Calibrations (G. Signorelli)
  • Drift Chambers (J. Egger)
  • Timing counter (F. Gatti)
  • Electronics and DAQ (M. Grassi)
  • Software (R. Sawada)
  • Schedule

2
Quench Problem Status (W. Ootani)
  • The shielding and grounding scheme was improved
    after the December run.
  • There hasnt been no unexpected shutdown since
    then.
  • No shutdown for 10 days with SCNCBypass during
    shutdown period.
  • No shutdown for 10 days with SC (BTS) after
    accelerator started to run.
  • The problem by the external noise seems fixed.

A new problem happened during CW accelerator
testing. COBRA was unexpectedly shutdown after
40 hrs operation. Still under investigation, but
it seems there was a problem with NC power supply
according to the measured waveform.
3
Xenon detector (S. Mihara)Honeycomb panel test
completed
  • 3rd panel delivered to Pisa at 1630 on 20/Feb
  • Mounted on the text box and tested on 22, 23/Feb
  • 3 bar
  • Inspection by a Plyform expert
  • 4 bar x4 times
  • Hold for 3 minutes at 4 bar in the last test
  • Panel deformation (max)
  • 0.3 mm at 1 bar
  • 3.4 mm at 4 bar

Holes for evacuation
4
Cryogenic Test at SIMIC
  • -18/May
  • All nuts on the covers of the cold vessel were
    fastened tightly and the warm vessel was
    evacuated whole weekend.
  • 21/May
  • He leak test. 1.8Bar He was filled and found that
    the leak rate was larger than 10-4 mbarl/sec.
    Keep evacuation during the night.
  • 22/May
  • cooling using cold gas from the LN2 tank. Cold
    gas in the cold vessel Most parts were cooled
    down to -5-10 degree C.
  • 23/May
  • liquid N2 through the cooling pipe. All parts
    cooled below -110 degreeC around 1200.
  • Then N2 gas at 1.0Bar and He gas filled step by
    step with measuring leak rate.
  • N2 1.0 bar He 0.2 bar ? 5x10-7 mbarl/sec
  • N2 1.0 bar He 0.4 bar ? 1.6x10-6mbarl/sec
  • N2 1.0 bar He 0.6 bar ? 7.8x10-6mbarl/sec
  • N2 1.0 bar He 0.8 bar ? 2.2x10-5mbarl/sec
  • The leak was not fixed at SIMIC by any means.
  • We decided to bring the cryostat to PSI and
    perform a leak test

5
Cryostat arrived at PSI
  • Delivery at 700 am on 5/June
  • Works to be done
  • Cleaning
  • Leak/pressure test
  • Alignment
  • PMT installation

6
CW received on middle of may(G. Signorelli)
7
(No Transcript)
8
m radiative decay
LED
Laser
Lower beam intensity lt 107 Is necessary to reduce
pile-ups Better st, makes it possible to take
data with higher beam intensity A few days 1
week to get enough statistics
g
e
m
(rough) relative timing calib. lt 23 nsec
n
n
PMT Gain Higher V with light att. Can be repeated
frequently
p0? gg
p- p ? p0 n p0 ? gg (55MeV, 83MeV) p- p ?
g n (129MeV) 10 days to scan all volume
precisely (faster scan possible with less
points) LH2 target
alpha
Xenon Calibration
PMT QE Att. L Cold GXe LXe
e
g
e-
Nickel g Generator
Proton Acc
Li(p,?)Be LiF target at COBRA center 17.6MeV
g daily calib. Can be used also for initial
setup
9 MeV Nickel ?-line
on
off
quelle
K
NaI
Bi
Illuminate Xe from the back Source (Cf)
transferred by comp air ? on/off
Tl
Li(p, ?1) at 14.6 MeV
F
Polyethylene
0.25 cm Nickel plate
Li(p, ?0) at 17.6 MeV
9
DC (J. Egger)
10
  • 4 Levels of test
  • Pretest HV Air tightness
  • Aquarium functionality tightness
  • Cosmics Lab other preamps correct signal
    assignment inside COBRA up to panel
  • Cosmics pE5, with and without COBRA

11
DC test with Cosmic ray (in Lab.)
12
cosmic ray counter for DC wire alignment
  • 10 counters (10 plastic scintillators 20 PMTs)
    are prepared
  • DC wire alignment will be performed w/o COBRA
    field

13
TC F. Gatti
14
TC MC vs data E loss in bars

15
6 years of operation !!
16
(No Transcript)
17
(No Transcript)
18
Positron efficiency
Confirmed by a 3 calculation including PR,
tracking and fitting from DC to TC
19
missing hits
missing hits
Positrons from off-centre m-decays and hitting
DCH outer frame
20
Where do they come from?
  • Front view (x-y) of
  • m-decay vertices on
  • the target
  • all events
  • c2gt50 N1lt5
  • Source of inefficiency
  • for the TC

21
Way(s) out?
  • Reduction of beam spot size on the target?
  • (sx,y ? 1.1 cm ? 0.5 cm)
  • is it achievable by shrinking the target (not
    this year)
  • Background ? Investigate...
  • Increase of the magnetic field?
  • shrinking of the bending radius by ? 1 cm needed
  • increase of B by ? 7 (B0 1.26 T ? 1.35 T)
  • distortion of hit pattern on TC?
  • might it affect COBRA behaviour?
  • ...

22
Multi-threading model
Electronics and DAQ M. Grassi
Calibration Thread
Zero-copy ring buffers
VME
Round-Robin distribution
Calibration Thread
VME Transfer Thread
Collector Thread
Calibration Thread
Network
Calibration Thread
23
DRS Readout rate
  • Optimal readout rate of DRS full waveforms with 4
    calibration threads 30 events/s
  • During Dec 06 run max readout at 7 events/s
  • Double event readout
  • Code optimization
  • Single calibration thread

24
DAQ rate vs. amount of data
  • DAQ speed is not a limiting factor
  • The total data size needs solution
  • 30 Hz is maximal VME speed for full waveforms ?
    gt270 MB/sec
  • Data transmission limit is 20 MB/sec
    (250TB/year)? need online reduction 10x (M.
    Grassis and R. Sawadas talk)
  • Storage limit is 30 TB/year? need offline
    reduction 8x (R. Sawadas talk)

25
Conclusions
  • Splitters installed, operational, expected
    performances, test in Dec 06
  • Fiber preamp problem with an IC fixed, test
    passed, mounted on the TC detector, installation
    in Aug 07
  • Hit registers mezzanine boards produced, FPGA
    firmware ready (PSI GPVME board), installation in
    Aug 07
  • Trigger installed, operational, built-in
    debugging and control tool, need tuning after
    detector turn on, test in Dec 06
  • DRS2 installed, operational, good for timing,
    temperature dependence, usable with DC
  • DRS3 prototype test phase, final solution, not
    available in 2007
  • Aux digitizer production problem solved,
    prototype test completed successfully, ready for
    2007 run
  • DAQ installed, operational, good performances,
    test in Dec 06 run
  • The electronics and the DAQ systems are expected
    to be ready for the 2007 run

26
Software (R. Sawada)
27
(No Transcript)
28
Pdfs 1)
g
e
Signal
Signal
RD
Accidental
FWHM 0.8
RD
FWHM 5
Accidental
All pdfs normalized to 1 and summed by relative
weights of different types of events. Positron
FWHM improved from 1.0 ? 0.8 photon FWHM
improved from 6.5 ? 5 .
29
Pdfs - 2)
Signal
Dq
Dt
Signal RD
RD
FWHM ? 1o
FWHM 180 ps
Accidental (assumed flat in cos q)
Accidental (assumed flat)
Dt assumed flat for accidental and gaussian for
signal/RD (MC results predict gaussian shape,
but with worse resolution) Dq taken from MC
(results close to the proposal FWHM).
30
Sensitivity result
  • Three different sets of windows results do not
    depend on the cuts.
  • The sensitivity limit is
  • 2.15 x 10-13
  • equivalent to the sensitivity that one
    obtains with a box
  • analysis assuming ? 0 bck.
  • (not surprising).
  • Important point the spill-in
  • of bck events within the signal region is
    automatically
  • taken into account by the
  • knowledge of the bck pdf.

2.15 x 10-13
N.B. Empty circles crosses shifted by 0.05 on
B.R. axis for clarity.
of null experiment
31
Advantage boundary effect
0 events in box analysis
Box analysis window
Likelihood analysis window
1 event in box analysis
Box analysis window
Likelihood analysis window
Box analysis quote a worse upper limit, with a
sudden jump. Likelihood analysis treated as
a bck fluctuation, likelihood value only
slightly changed ? upper limit increases by a
small amount and continuously.
32
Conclusions
First result very good agreement of rates
predicted by MC ? no significant unwanted
backgrounds !!
33
Schedule
34
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com