GLAST Proposal Review - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

GLAST Proposal Review

Description:

GLAST LAT Project DOE/NASA Delta Baseline/Preliminary Design Review, July 30, 2002 ... Carbon-fiber sidewalls conduct heat to the base and stiffen the module. ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 25
Provided by: peterfmi
Category:

less

Transcript and Presenter's Notes

Title: GLAST Proposal Review


1
GLAST Large Area Telescope Tracker
Subsystem WBS 4.1.4 Highlights in Progress Since
the January Review Robert Johnson Santa Cruz
Institute for Particle Physics University of
California at Santa Cruz Tracker Subsystem
Manager johnson_at_scipp.ucsc.edu
2
Outline
  • Overview
  • Results from January Review
  • Action Item Status
  • Changes Since January Review
  • Hardware update since January
  • Schedule and Cost
  • Summary

3
Tracker Overview
  • 16 layers of tungsten converter foils.
  • 12 layers of 3 X0 converters
  • Followed by four 18 layers
  • x-y Si-strip detector pair closely following each
    converter foil.
  • Two additional pairs at the bottom are needed for
    triggering.
  • 19 stiff composite tray panels support SSDs on
    both faces with electronics on two sides.
  • Converters are on the bottom face, just above the
    SSD plane
  • 2-mm gap between trays
  • Carbon-fiber sidewalls conduct heat to the base
    and stiffen the module.
  • Electronics are based on 2 ASICs, PC boards, and
    custom flex cables.
  • 31.6 kg mass per module.
  • 10.5 W of power per module.

Multi-Chip Electronics Module (MCM)
19 Carbon-Fiber Tray Panels
Carbon-Fiber Wall
2 mm gap
Readout Cable
4
Tracker Production Overview
Module Structure (walls, flexures,
thermal-gasket, fasteners) Engineering SLAC,
Hytec Procurement SLAC
SSD Procurement, Testing Japan, Italy, SLAC
SSD Ladder Assembly Italy
10,368
Tracker Module Assembly and Test Italy
2592
18
Tray Assembly and Test Italy
342
342
Electronics Design, Fabrication Test UCSC, SLAC
Composite Panel Converters Engineering SLAC,
Hytec, and Italy Procurement Italy
648
Cable Plant UCSC
5
Results from January PDR/Baseline Review
  • The Tracker has an Experienced Project Team .
  • The concept of the Tracker is well matched to the
    science goals and utilizes mature technology.
  • The design is well thought out and can be
    implemented within the available time.
  • A strong consortium of groups in Italy has taken
    the responsibility for assembling and testing all
    the ladders, trays, and towers. This is a crucial
    contribution to the Tracker which is being
    executed in a very effective and competent
    manner.
  • Baseline the Tracker with Increased Contingency

6
Action Item Status
Action Item Response
1 Baseline the Tracker with Increased Contingency The current basis for estimating Project contingency needed uses 25 of the Tracker cost to go VS 18 in January
2 Thoroughly evaluate pre-production ICs Agreed Plan in place
3 Refine Assembly and Test Procedures Agreed In process
7
Changes Since January 02 Review
  • The schedule has been revised to accommodate the
    overall LAT schedule extension.
  • Added time for additional ASIC submissions.
  • Incorporated a more conservative schedule for
    Tracker module production with the Italian
    groups.
  • Critical Deliveries
  • Modules 3, 4 available March 29, 2004, with 11
    weeks of float.
  • Modules 15, 16 available August 4, 2004, with 7
    weeks of float.
  • Budget
  • Estimated cost at completion increased 180K
  • MOA with Italy
  • INFN ready to sign and has been providing the
    requested funding and covering for the delay in
    ASI approval.
  • ASI has not yet signed but has recently begun
    funding Tracker work with approval of 800k for
    FY2002.

8
Prototype Tower Module
  • Mechanical prototype loaded with dummy SSDs.
  • Includes flexure interface to the Grid.
  • Used to test and evaluate assembly methods.
  • Assembly worked well, but tray tolerances were
    not quite to specification. Tray assembly
    tooling has since been revised and specifications
    met.
  • Vibration and Thermal testing
  • Single panel LAT-TD-759. ?
  • Grid-to-tower interface thermal cycle report in
    progress. ?
  • Random vibration of the full module LAT-TD-788.
    Problems (see following)

Composite trays and mass models of the prototype
tower, before mounting of the sidewalls.
9
Vibration Test Problem 1
  • Some screws attaching the sidewalls to the bottom
    tray backed out during transverse-axis
    qualification-level random vibration. This
    problem was solved (as verified in a retest)
  • Replace hex heads by Torx-Plus to enable
    tightening to the full specification without
    stripping the heads.
  • Double the number of screws in the non-MCM sides
    of the bottom tray.
  • Add aluminum washer-inserts to the sidewalls for
    these fasteners.
  • We also plan to use a secondary locking mechanism
    for the screws in the final assembly, as extra
    insurance.

Full module instrumented for thrust-axis vibration
10
Vibration Test Problem 2
  • In the first test, a hairline crack formed in the
    bottom-tray closeout between the edge and a
    corner-flexure fastener.
  • In the second test suite at transverse-axis
    qualification levels the cracking increased and
    the problem propagated to all 4 corners, breaking
    loose the corner-flexure mount inserts. (The
    mid-span flexures all held fast.)
  • Remediation in process
  • Analysis to make sure we understand the failure
    and the cure.
  • Remove light-weighting cutouts in the bottom tray
    and increase its height by 5 mm.
  • Reinforce each corner with a bonded metal
    bracket.
  • Remediation Plan presented to Project ART.

Cracking as seen after the second test suite.
11
Tracker ASICs
  • The second run of the GTRC and GTFE ASICs needed
    to be resubmitted
  • GTRC V2
  • Missing rule in the Tanner DRC led to a short in
    the memory.
  • Although complete chip was simulated with
    Synopsys Timemill, clock skew margins were not
    sufficient for the IC to function at nominal
    supply voltage (Tanner does not extract the clock
    network as a distributed RC network).
  • GTFE Vf a minor modification was not verified by
    simulation due to misunderstanding, missing an
    error that removed the baseline restoration.
  • GTFE Ve the same missing DRC rule led to a
    nonfunctional analog chain.
  • Remediation
  • Careful crosscheck of the DRC rule-set against
    the Agilent vendor rules and use of the MOSIS DRC
    checking service.
  • Improved pre-submission procedural control.
  • Controlled row-wise clock routing in the GTRC
    core.
  • Submission of a back-up GTRC version without RAM.

12
Tracker ASICs
  • The digital section does function in the GTFE Ve
    Vf chips, allowing substantial testing to
    proceed
  • Probe-card testing of the GTFE using the full set
    of test vectors developed according to
    LAT-TD-247.
  • Testing on the mini-MCM using GTRC V1 chips.
  • Several problems were addressed in the versions
    in production
  • Proper response in the GTFE to undefined
    op-codes.
  • Logic errors in GTFE register loading.
  • Protection resistors in the I/O pads led to
    unreliable operation at the full 20 MHz.
  • Clock skew issues in the GTRC.
  • DRC errors and the GTFE Vf comparator bug.
  • Chips presently in fabrication (Due August 22)
  • GTRC with custom RAM and GTRC with Flip-Flop RAM
    (both usable for flight).
  • AC and DC coupled GTFE versions.

13
Electronics Testing
  • Several mini-MCMs are under test at UCSC and
    SLAC, using the V1 GTRC and Vf GTFE chips.
  • Using COM card, interface board, and Python
    script at UCSC, to develop the test station for
    MCM production.
  • Using 2 COM cards, TEM, and SCL script at SLAC to
    debug the ultimate readout scheme.
  • Mini-MCM has been interfaced with flight like
    Tower Electronics Module(TEM) to verify
    functionality and interfaces. Continued use for
    hardware and flight software development.
  • Parts qualification is in progress for
    poly-switches and HV caps.
  • Planning is in progress for radiation testing
    (total dose and FEE) after the new chips arrive.

A mini-MCM loaded with 2 prototype front-end
chips and 1 controller chip.
14
Electronics Test Systems
  • GTFE wafer probing
  • Operational on a manual probe station (undiced
    wafers will be available end of August).
  • Thorough set of test vectors for complete
    functional testing (see LAT-TD-247).
  • All of the test vectors have been exercised
    through the simulation and actual chips (which
    uncovered the bugs fixed in the present
    submission).
  • GTRC wafer probing
  • Complete hardware and software for manual
    testing.
  • Thorough set of test vectors (see LAT-TD-248).
  • No bare die yet to test it on (probes dont fit
    V1).
  • Test vectors are presently being exercised
    through the simulation and on the mini-MCM (with
    some restrictions, such as not being able on the
    mini-MCM to cycle through the address space).

15
Electronics Test Systems
  • MCM testing during production at Teledyne
  • Second-version interface board is in hand with
    enclosure plus a better monitoring interface for
    power supplies and LVDS bias levels.
  • Test plan documented in LAT-TD-153 and
    LAT-TD-249.
  • Test vectors are under development for functional
    testing, based on extending the GTRC set.
  • VME ADC modules were obtained, and software is in
    progress to test the power supply voltages and
    the LVDS driver bias levels.
  • Some software has been developed for threshold
    scanning (analog performance tests) and tested on
    the d-version chip.
  • Basic system, to be operated by its developers,
    will be ready for testing the engineering-model
    MCMs in September.
  • MCM burn-in station layout of special cables is
    in progress.

16
Electronics Production
  • Teledyne has successfully developed and tested
    the tooling for bonding the pitch adapter flex
    circuit onto the MCM PWB.
  • All parts and materials are present at Teledyne
    to begin assembly of the dummy MCMs for the
    mechanical/thermal engineering model tracker
    module. These modules will have all parts, but
    with dummy or bad (GTFE Ve) ICs and with some
    capacitors replaced with resistors to mimic the
    IC heat load.
  • All of the molded plastic MCM carrying cases are
    in hand (in fact, in sufficient numbers for the
    flight build). These are used for MCM testing
    and burn-in following assembly, as well as for
    storage and transport.
  • Assembly of the dummy MCMs is beginning at
    Teledyne.
  • Pisa is testing the MCM-tray interface,
    especially with thermal cycling.

17
Engineering Model Tooling Production
  • Experience with the prototype Tracker module led
    to many detailed changes in the assembly tooling
    designs for trays.
  • Plyform (Italy) is now assembling EM composite
    panels with the new tooling, and work is
    beginning to add the converters and bias
    circuits.
  • GA Engineering (Italy) has assembled all of the
    dummy SSD ladders and is now working on the live
    ones, expected completion July 30, 2002. The
    electronics test system for the ladders is
    operational.
  • Tools for mounting the ladders and for assembly
    of the top/bottom trays are in progress.

18
Procurement of Long-Lead Items
  • Silicon procurement and deliveries on schedule.
  • 2314 HPK SSDs have been received and tested in
    Italy.
  • Production of flight SSD ladders will begin as
    early as August 5, 2002 pending ladder assembly
    procedure review and release.
  • The carbon-carbon closeout material is on order
    from Alcomp (US).
  • In purchasing some items for the EM sufficient
    quantities for the flight build were ordered to
    reduce costs
  • The molded MCM carrying cases.
  • All of the screws for sidewall attachment.

19
Summary Schedule
20
Key Milestones
21
Cost Commitments
22
Cost Profile
23
Workforce Plan
24
Summary
  • The flexure-mount redesign effort is on schedule
    and should not delay the Engineering Model
    schedule or the CDR.
  • All other aspects of the Tracker design are
    complete. All lowest-level drawings are in place
    as drafts, with 22 released. Good progress on
    assembly and tooling drawings. See the drawing
    tree on the Tracker web page.
  • Some details of the production fixtures and
    processes are still being tweaked and tested as
    the Engineering-Model build progresses.
  • Work is accelerating on documentation of test
    plans and processes and production processes, in
    preparation for CDR.
  • Overall, the Tracker development is progressing
    on schedule for the subsystem CDR in January 2003
    and the LAT CDR in April 2003.
Write a Comment
User Comments (0)
About PowerShow.com