Title: GLAST Proposal Review
1GLAST Large Area Telescope Performance Safety
Assurance Joseph Cullinan SLAC Perform
ance Safety Assurance Manager cullinan_at_slac.sta
nford.edu (650) 926-5034
24.1.A PSA Status August 2005
- DAQ/Electronics
- TEM/TPS
- Have now completed handoff of 14 TEM/TPS
assemblies to IT - MRB held to review replacement of TPS units
currently installed in Bays 0 and 4. - TPS units in the first two TEM/TPS assemblies
installed in the Grid did not have CCA rework
performed to eliminate voltage oscillation
problem (NCR 397). - MRB concluded to remove TPS units only from Bays
0 and 4. Plan is to keep existing TEMs in Bays 0
and 4. Pros and cons of five different options
hardware removal (including use-as-is) were
considered - This option will allow for subsequent removal of
TEM or TEM/CAL if replacement TPS fails to meet
electrical or mechanical fit requirements - Replacement TPS units with HV calibration
constants similar to those of the TPS units to be
removed have been selected from fully tested
TEM/TPS assemblies - TPS removal and replacement procedure being
finalized and documented by IT - Recalibration of new TEM/TPS telemetry and TKR
and CAL detectors will be required following TPS
replacement - PDU
- T/V test started on 1st box, 2nd box delivered to
SLAC for initial testing - GASU
- GASU Power Supply boards and CCAs for 1st GASU
completed rework at SLAC following initial
testing - Updating drawings and BOM to reflect changes
- Boards and CCAs for 2nd GASU still in assembly at
Aeroflex
34.1.A PSA Status August 2005
- DAQ/Electronics
- LCB/SIB/CPS boards
- Last month LAT QA observed workmanship issues
with first SIB, LCB and CPS boards delivered and
reviewed these issues with Aeroflex and SLAC
source inspector - Discrepancies were result of carelessness rather
than unclear drawings or lack of technical
expertise at Aeroflex - Corrective action Aeroflex project management
reviewed procedures with technicians to increase
awareness of drawing requirements, hardware
handling and workmanship requirements - SLAC source inspector now documents all
in-process and final inspections and forwards
reports to LAT QA and DAQ for review. - Discrepancies now are more clearly documented for
evaluation. Any discrepancies that require
rework is more quickly addressed by LAT/GSFC QA
and DAQ, and if necessary additional corrective
action can be implemented - Cables
- Performing final inspection of remaining flight
cables (including spares) at vendor facility
(Cicon) this week.
44.1.A PSA Status August 2005
- Integration and Test
- Supported completion of 6-tower and 8-tower
testing - Supported receipt and acceptance of ACD
- ACD final acceptance data package forthcoming
- Elevated 4 open ACD nonconformances to LAT level
NCRs -
54.1.A PSA Status August 2005
- TKR
-
- Supported MRB presented by INFN on Tower 8 tray
anomaly observed during T/V testing (INFN NCR
551) - Ladders in Tray M007 began to show excessive
noise or dead channels when temperatures rose
above 25 deg. C - Similar failure was observed on Tray M010 on
Tower 7. This tray was eventually removed and
replaced, and Tower 7 retested - Both trays were fabricated for Tower 0 and
subsequently requalified and placed into Towers 7
and 8 - MRB concurred to remove and replace tray M007
from Tower 8, and followed by repeat of
environmental testing - Cause is unknown after considerable electrical
testing on tray M010 - Testing on tray M010 to troubleshoot this problem
appears to be exhausted currently INFN does not
have additional testing planned for tray M007 - INFNs analysis indicates failure is typical of
missing bias on Si detector and not wire bond
intermittent failure - Additional Tower 0 requalified trays L023 and
B002 are installed in flight Towers 4 and 5 no
anomalies have been observed with these trays - INFN reported that insignificant performance
degradation would result in Towers 4 and 5
ifthese trays began to show similar problems with
ladders - Last flight tray (L015) from Tower 0 is now on
hold at INFN -
64.1.A PSA Status August 2005
- TKR
- Pioneer Flex Cables
- Supported in-process and final source inspection
of cable assemblies at Pioneer - Pioneer has delivered qty 29 finished cable
assemblies qty 22 have been hand carried to
INFN - Minor workmanship issues have been observed
during source inspections - Omnetics connectors with damaged and bent pins
from handling and worn test connector savers were
removed and replaced without problems - Missing conformal coating observed on some
resistors - On-site inspection and Pioneers responsiveness
has allowed quick resolution of these workmanship
issues. Causes were identified and corrective
actions were put in place - GSFC has not rejected any Pioneer test coupons to
date - Parlex Flex Cables Qualification Test Plan
- Reviewed relevant documentation on Qual plan with
GSFC and TKR - Will use flight and non-flight cables and coupons
to complete qual testing - Non-flight cables will be hand selected to ensure
qual testing will not be impacted by
nonconforming condition of cable. Non-flight
cables with slight annular ring failures would be
best candidates. - Minor changes to the Parlex qualification test
plan would include using cables instead of
coupons for some tests. -
74.1.A PSA Status August 2005
- Mechanical Systems
- X-LAT Plate
- Delivered to SLAC in July still awaiting
acceptance data package from Lockheed Martin. - Lifting sling returned to LM for scheduled rework
- Radiators
- T/V testing initiated
8LAT NCR Metrics 8/26/05
94.1.A PSA Status August 2005
- Software QA
- Supporting reviews of FSW test procedures
- Supported the IT release of LATTE R4.10.0
including VV and documention review for LAT
Docs. - Met with GSFC Software QA (Randy Worden) to
discuss LAT QA processes for FSW oversight - QA requirements for FSW were reviewed
- Randy provided recommendations for the LAT QA
process overseeing FSW documentation and approval - SLAC reviewing these recommendations for
implementation
10Issues and Concerns
- Pioneer Flex Cables
- Must ensure that coupon testing at GSFC keeps up
with cable production and delivery to INFN, so we
dont end up waiting for a test report before a
cable can be installed on a tower. - GSFC has provided exceptional support in
prioritizing coupon testing in response to a
highly accelerated delivery schedule for Pioneer
cables, so the process is working so far. - Tower testing
- TKR, INFN and LAT QA need to closely follow the
process for removing non-flight cables used to
support tower environmental testing, and the
subsequent replacement of flight cables - Towers 7, 8 tray anomalies observed in T/V
- Cause is still unknown, and currently there are
no known additional tests or analyses on removed
trays to determine cause -
-
-
114.1.A PSA Planned Accomplishments September
2005
- Support PDU, GASU testing
- Support electronics assembly at Aeroflex
- Support flex cable production at Pioneer
- Support flex cable qual testing at Parlex
-
-
12Cost Report
13Cost Variance Explanation
- Why overrun/underrun?
- Did not reduce headcount to follow planned FTE
dropoff due to extended production runs through
end of July at Teledyne and General Technology
with full time source quality engineers. Also
required same headcount as last month to support
subsystem production and testing. - What will be done to correct?
- Source quality engineers at Teledyne and General
Technology have rolled off as of end of July (2
FTE) - Look to consolidate QA headcount at SLAC in
September as subsystem production (cables, flex
cables, incoming inspection) ramps down
14FTE Report (DOE/NASA-funded only)
15FTE Variance Explanation
- Why overrun/underrun?
- Source QA support was needed longer than expected
at Teledyne and General Technology to support
production. Also needed to continue current
level of QE support at SLAC - What is the impact?
- 2 FTE required to support extended production
cycles at these two vendors - What will be done to correct?
- Roll off of 2 source QEs at end of July is
reduction of 2 FTE for August. Will also see
additional reduction of approximately 1 FTE in
August due to vacations. Also look to consolidate
FTE at SLAC in September as vendor production
runs near completion.