Talvivaara Projekti Oy - PowerPoint PPT Presentation

1 / 11
About This Presentation
Title:

Talvivaara Projekti Oy

Description:

Successful nickel and zinc sulphide production campaigns in Jan-Feb and Apr-May ... Nickel 12-14 tonnes/day. Zinc 29-30 tonnes/day ... – PowerPoint PPT presentation

Number of Views:35
Avg rating:3.0/5.0
Slides: 12
Provided by: talvi
Category:

less

Transcript and Presenter's Notes

Title: Talvivaara Projekti Oy


1
August 2009
2
  • DISCLAIMER
  • The following information contains, or may be
    deemed to contain, forward-looking statements
    (as defined in the U.S. Private Securities
    Litigation Reform Act of 1995). These statements
    relate to future events that involve known and
    unknown risks and other uncertainties. By their
    nature, forward-looking statements involve risks
    and uncertainties because they relate to events
    and depend on circumstances that may or may not
    occur in the future. All forward-looking
    statements made in this presentation based on
    information presently available and Talvivaara
    Mining Company Plc. assumes no obligation to
    update any forward-looking statements.
  • Nothing in this presentation constitutes
    investment advice and this presentation shall not
    constitute an offer to sell or the solicitation
    of an offer to buy any securities or otherwise to
    engage in any investment activity.

1
3
Highlights
  • Successful EUR 82.7 million / GBP 71.3 million
    placing completed in July putting Talvivaara in
    strong financial position
  • Decision to expand production capacity by almost
    50 to up to 50,000 tonnes nickel per annum from
    2012
  • Good progress with upgrade of crushing circuit to
    eliminate earlier design problems and to expand
    capacity to approx. 22 million tonnes of ore per
    annum
  • As anticipated, crushing capacity with old
    circuit remained below budgeted levels due to
    significant downtime
  • Successful nickel and zinc sulphide production
    campaigns in Jan-Feb and Apr-May with subsequent
    product deliveries to Norilsk Nickel and zinc
    customers
  • Secondary listing of shares on Helsinki Stock
    Exchange on 11 May 2009 resulting in significant
    expansion of shareholder base
  • Continued good safety record with 3 LTIs to
    Talvivaara personnel in Jan 2009 and none since
    the launch of the Work Group Safety Challenge in
    Feb 2009

Kuusilampi open pit at Talvivaara June 2009
2
4
Key figures
1 Prior to receiving the proceeds of the EUR 82.7
million equity placing
3
5
Financial review
  • First income from deliveries to customers
  • Sales EUR 1.8m
  • Other operating income EUR 25.6 mostly from
    realised and unrealised gains on nickel, zinc and
    USD forwards
  • Operating loss EUR 7.9m
  • Strong cash position
  • Drawdown of EUR 45m Finnvera facility
  • EUR 82.7m equity placing of 22,280,000 shares at
    EUR 3.70/ GBP 3.20 each proceeds were received
    in July
  • Capital expenditure
  • H1 2009 capital expenditure EUR 57.7m on
    completion of mine construction and railway
  • H2 2009 new commitments towards expansion capex
    being made (hydrogen plant, mobile equipment)

4
6
Production summary
  • Materials handling bottleneck being resolved
    alongside expansion

5
7
Production update mining and materials handling
  • Mining
  • Processes performing well
  • Full capacity not tested due to bottleneck in
    crushing
  • Materials handling
  • Ongoing problems in fine crushing throughout H1
    2009 despite temporary improvements in capacity
    as a result of amendments to existing circuit
  • Total capacity achieved H1 2009 was 4.0 mt or ore
    (53 of budgeted amount)
  • Primary crusher also experienced technical
    problems
  • Modifications being made
  • Capacity secured by contractors for the time
    being
  • Crushing circuit being upgraded
  • Capacity to increase to 22 million tonnes per
    annum
  • Installation of redesigned circuit progressing on
    schedule for start-up in the beginning of
    September

6
8
Installation of upgraded crushing circuit
progressing as planned
New secondary crushing equipment installed, 24
Aug 2009
7
9
Production update - bioheapleaching and metals
recovery
  • Bioheapleaching
  • Bioheapleaching proceeding as planned
  • Control of heat generation through aeration and
    irrigation critical to prevent re-precipitation
    metals in the heap
  • 6.5 million tonnes of ore under leaching at the
    end of H1 2009
  • Plans to stack the heap in two layers being
    reconsidered likely return to original plan of
    a single layer primary heap
  • Metals recovery
  • Successful nickel and zinc production campaigns
    in January-February and April- May
  • Production levels during May campaign
  • Nickel 12-14 tonnes/day
  • Zinc 29-30 tonnes/day
  • Leached amounts corresponded to the size and age
    of the heap at the time
  • Quality of metal products good and improving
    throughout campaigns

8
10
Environment, health and safety
  • Environment
  • Ongoing environmental management and monitoring
    programmeaccording requirements set out in the
    Environmental Permit
  • Talvivaara is preparing its environmental
    processes for ISO 14001 certification
  • Health and safety
  • Good health and safety record
  • Three minor lost time injuries (LTIs) among
    Talvivaara employees during H1, none since the
    launch ofWork Group Satey Challenge in Feb 2009
  • Good safety rating
  • Talvivaara 12 LTIs/ million man hours
  • Finnish mining industry 40 LTIs/ million man
    hours
  • Construction industry 80 LTIs/ million man hours

Talvivaara personnel 2003-2010e
Aug 2009
9
11
Market outlook
  • Short term outlook still uncertain
  • Underlying demand yet to grow
  • Temporary fall in commodity prices still
    possible
  • Positive long term outlook
  • Promising recent development in developing
    economies
  • Signs of restocking and increasing industrial
    demand also on OECD markets

10
Write a Comment
User Comments (0)
About PowerShow.com