Title: COOP END OF TERM PRESENTATION
1CO-OP END OF TERM PRESENTATION
BY CAMERON MOSER
2OVERVIEW
- PRIMARY ENGINEERING DIMENSIONS
- STORMWATER PROJECT
- SLAG DEWATERING PROJECT
- MISCILLANEOUS ACHEIVEMENTS
- LESSONS LEARNED
- CONCLUSION
3Primary Engineering Dimensions
- Safety
- Project Management Practices
- Documentation
- Construction Support (QA)
- Application of Engineering Principles
- Professional Development
4Storm Water Project
1
2
4
5
7
8
9
11
12
10
13
5Storm Water Project
Process Diagram
WEST Coal Field
East Plant
Plant Area
6Storm Water Project
Process Diagram
- Provide Operations
- Overview of system flow during normal and
emergency conditions - Location of sumps pumps
- Location of pump breakers for maintenance
purposes
7Storm Water Project
Level Control Calibration
- Provide Construction Operations
- Specifications of sump
- Start/stop levels for multiple pumps
- Visual aid in calibrating level control
transmitter - Calibration chart with detailed levels and their
associated milliamp readings
8Storm Water Project
- Primary Engineering Dimensions
- Project Management
- Coordinated and led meetings
- Scheduled walk downs of sumps
- Document Control
- DWR
- Arranged PIDs, pump specs/manuals, and drawings
into turnover packages to be used by start-up. - As - Builts
- Construction Support (QA)
- Level Control and Calibration
- Performed walk downs of sumps
- Application of Engineering Principles
- Conducted flow tests on Sump-011 for orifice
sizing
9SLAG DEWATERING PROJECT
10Slag Dewatering Project
Process Diagram
- Provide Operations
- Overview of system flow during normal and
emergency conditions - Location of key equipment
11Slag Dewatering Project
Testing, Start - Up, Troubleshooting
- Provide Operations
- Checklist to monitor system operation
- Familiarization with buttons and readings
- Detailed, graphical description of step-by-step
process
12Slag Dewatering Project
Simulated Run
13Slag Dewatering Project
- Examples of problems found
- Lag pump failed to initiate after lead pump trip
- Valves failed to align during certain functions
- Misleading ,unclear, and incorrect labels on HMI
- Some HMI buttons were of little or no practical
use - No indication of power or communication failure
- Chatter or the rapid activation and
deactivation of pumps from interaction with each
other
14Slag Dewatering Project
Testing, Start - Up, Troubleshooting
- Solving Chatter
- Using trend function, amp readings were used for
analysis - Data shows spiking of amps upon activation or
deactivation of lag pump, resulting in chatter - Problem could be solved in PLC
15Slag Dewatering Project
Testing, Start - Up, Troubleshooting
- Solving Chatter
- Problem solved by adding delay timers before pump
activation / deactivation in PLC logic
16Slag Dewatering Project
Testing, Start - Up, Troubleshooting
Solving Chatter
BEFORE
AFTER
17Slag Dewatering Project
Minimum Flow Bypass Orifice Sizing Calculation
- Designed to meet minimum flow conditions
- Associated measures, constants, equations, and
frictional factors were used. Cameron Hydraulic
Data and Crane were consulted to determine these - Pump hydraulic curves were referenced to
determine head losses
18Slag Dewatering Project
Minimum Flow Bypass Orifice Sizing Calculation
- Simplified Using Excel
- Changing of different variables lead to redundant
calculations - Flow properties of different cases easily
explored using macros in excel - Regression with equation used to estimate values
and iterate
19Slag Dewatering Project
- Primary Engineering Dimensions
- Safety
- Submitted safety suggestion to install life
support atop the bins. - Project Management
- Devised test regimen for return water and
overflow pumps - Assisted Allan Sherman-Hoff representative in PLC
reconfiguration - Created and implemented log for use by operations
- Document Control
- Compiled and organized drawings for slag
dewatering system - Updated redundant line drawing using AutoCAD
- Construction Support (QA)
- Ordered and tracked shipments from vendors
- Administered tests on return water and overflow
pumps while recording necessary punch-list items - Reviewed and marked up drawings submitted for the
minimum flow bypass line - Application of Engineering Principles
- Calculated orifice size for minimum flow bypass
line
20Miscellaneous Achievements
- Primary Engineering Dimensions
- Safety
- Completed safety training course
- Provided safety tips at meetings
- Professional Development
- Scheduled to take Hudson Pump Centrifugal Pump
Seminar - Attended various Lunch and Learn meetings
- Construction Support (QA)
- Performed piping takeoffs for Recycle Pond
Project - Calculated fill volume for settling pond and
removed CCPs - Application of Engineering Principles
- Performed walk down inside UNIT-3 Boiler for
fault inspections
21Lessons Learned
- Safety First
- See the Big Picture
- Teamwork
- Have a Plan
- Define Expectations
- People must Buy in
- Take Initiative
22Special Thanks
- Jamie Arenas
- George Bolos
- Asa Cuellar
- Eid Dahdal
- Jerid Fortney
- Jessica Helkin
- Brit Johnston
- Sonny Miller
- Yogesh Patel
- Fred Wyly
- Troy Yambura
- Fellow CO-Ops - Allan Morales, Sabri Fattah,
Johel Comas, Tyson Dabney, Joseph Maydell
23Conclusion
- Questions/Comments after Allans Presentation