Title: FEMA Map Amendments and Revisions


1
FEMAMap Amendmentsand Revisions
2
MAP REVISIONS
  • Changes in physical condition of floodplain
  • Increased or decreased flood heights (BFE)
  • Availability of new and improved technical data

3
PROPOSED CHANGES
  • Because of the legal significance of NFIP maps,
    information supporting revisions must be
    scientifically and technically accurate

4
MAP REVISION CATEGORIES
  • Appeals
  • Map revisions
  • Map amendments

5
LOMA LOMR-F
  • Topography is wrong or
  • has changed because of fill

6
LOMR
  • New technical data, such as
  • Channel modification
  • Bridge
  • Culvert
  • Levee (floodwall)

7
LOMC-LOMA-LOMR
  • Letter of Map Change, or
  • Letter of Map Amendment
  • Letter of Map Revision-Based on Fill
  • Letter of Map Revision
  • Map Accuracy

8
LOMA-LOMR
  • MT-1 Forms
  • MT-2 Forms
  • MT-EZ (Single Lot or Structure)

9
LOMC-LOMA-LOMR
  • Provides an administrative procedure where by
    FEMA will review information submitted by an
    owner of property who believes that his or her
    property has been inadvertently included in a
    designated special flood hazard area

10
LOMA Letter of Map Amendment
  • A letter from FEMA stating that an existing
    structure or parcel of land that has not been
    elevated by fill would not be inundated by the
  • 100-year flood

11
LOMR-FLetter of Map Revision (Based on Fill)
  • A letter from FEMA stating that an existing
    structure or parcel of land that has been
    elevated by fill would not be inundated by the
    100-year flood

12
CLOMAConditional Letter of Map Amendment
  • A letter from FEMA stating that a proposed
    structure that is not to be elevated by fill
    would not be inundated by the 100-year flood if
    built as proposed

13
CLOMR-FConditional Letter of Map Revision (Based
on Fill)
  • A letter from FEMA stating that a parcel of land
    or proposed structure that is to be elevated fill
    would not be inundated by the 100-year flood if
    fill is placed on the parcel as proposed or the
    structure is built as proposed

14
LOMA LOMR-F MT-1 Forms
  • 1. Property Information Form
  • 2. Elevation Information Form
  • 3. Community Acknowledgment and
    Certification,Reasonably Safe From Flooding



15
LOMRLetter of Map Revision
  • A letter from FEMA officially revising the
    current National Flood Insurance Program map to
    show changes to floodplains, floodways, or flood
    elevations

16
CLOMRConditional Letter of Map Revision
  • A letter from FEMA commenting on whether a
    proposed project, if built as proposed, would
    justify a map revision (LOMR or PMR), or proposed
    hydrology changes

17
PMRPhysical Map Revision
  • A reprinted National Flood Insurance Program map
    incorporating changes to floodplains, floodways,
    or flood elevations

18
LOMR MT-2 Forms
  • 1. Revision Requestor and Community Official
    Form
  • 2. Certification by Registered Professional
    Engineer
  • 3. Hydrologic Analysis Form
  • 4. Riverine Hydraulic Analysis Form
  • 5. Riverine/Coastal Mapping Form

19
LOMR MT-2 Forms
  • 6. Channelization Form
  • 7. Bridge/Culvert Form
  • 8. Levee Floodwall System Analyses
  • 9. Coastal Analysis Form
  • 10. Coastal Structures Form
  • 11. Dam Form
  • 12. Alluvial Fan Flooding Form

20
LOMA LOMRFrequently Asked Questions
  • Fee Charged?
  • Internet
  • www.fema.gov/MIT/feesch.htm

21
LOMA LOMRFrequently Asked Questions
  • What is the allowable increase in the base flood
    elevation (BFE)?
  • Without Floodway - allowable increase is 1.0 foot
    (if allowed by local ordinance)
  • With Floodway - allowable increase is 0.00 foot

22
LOMA LOMR-F
  • topography is wrong or has changed because of
    fill

23
LOMR
  • new technical data
  • channel modification, bridge or culvert, levee
    or floodwall

24
LOMA-LOMR
  • LOMA LOMR-F MT-1
  • LOMR MT-2

25
References
  • NFIP Regulations 44 CFR 65, 67, 70
  • FIA-12, A Guide for Community Officials, Appeals,
    Revisions, and Amendments to NFIP Maps
  • MT-1, MT-2, and MT-EZ Forms www.fema.gov
  • FEMA website www.fema.gov