Title: September Status Report
1Orleans Parish School Board Accounting, Human
Resource and Financial Management Plan and
Implementation Status Report 5
September Status Report Submitted October 4, 2005
2Table of Contents
- Section Page
- Executive Summary 2
- Working Group Updates
- Financial Management Accounting 4
- Human Resources Payroll 7
- Procurement Inventory Management 14
- Information Technology 16
- Facilities Maintenance 19
3Executive Summary
- Prior to the devastating impact of Hurricane
Katrina, Alvarez Marsals (AMs) role as
interim crisis managers turning around the
troubled New Orleans Public School System
(NOPS) had three distinct phases - Stabilize the Crisis this encompassed the
numerous controls we were implementing to control
the overspending outside the classroom and lack
of effective support being provided to the
classroom by the organization (ie. controlling
the checkbook, reviewing every purchase
requisition, reducing the number of Oracle
Superusers to 1, payroll benefits audit,
issuing a 50M RAN financing, etc.) - Develop a Restructuring Plan this encompassed
developing revised general fund and special
revenue budgets where NOPS anticipated revenues
would exceed its anticipated expenditures. - Execute building internal capacity within the
organization to ultimately replace AM interim
managers with permanent replacements. - Post Katrina, our role as interim crisis
managers has not changed. As well, our three
phased strategy is also the same, however, with
different tactics being implemented to achieve
the same goal delivering a world class system
through which public education is delivered to
the children of New Orleans. This three phased
restructuring approach can be summarized as
follows - Stabilize the Crisis The primary stakeholders
of NOPS, our students and employees, were
displaced around the country after New Orleans
was flooded. We set up a crisis call center
staffed with up to 20 operators as well as a
crisis web site to communicate to and with our
stakeholders. We secured critical backup tapes
for Oracle, operating systems and student
information from the Data Center in New Orleans 2
days after Katrina hit. We were able to
establish an operational NOPS Oracle environment
in a disaster recovery site in New York. We
performed site inspections with the aid of
donated professionals from other public school
districts and the Council of Great City Schools
and identified 16 schools in Algiers/WestBank and
Uptown that suffered minimal damage from the
floods and issued emergency work orders to patch
roofs and windows prior to Hurricane Ritas
arrival.
4Executive Summary (cont.)
- Develop a Restructuring Plan We have developed
a plan to potentially open up to 8 schools in
Algiers/West Bank in November. This plan is
contingent upon at least three critical
approvals i) student demand and teacher
availability ii) EPA, City and other
regulatory signoffs iii) state and federal
funding. We have begun accepting expressions of
interest to gauge demand levels by our students
and employees to return to NOPS by November 2005.
Expression of interest forms are capturing
information from this population through our
crisis call center, website, and eventually some
local businesses in Algiers. Project worksheets
are being developed under the guidance of FEMA,
and bids are being developed and eventually
competitively sourced to perform the repair and
restoration work. Similarly, bids are being
prepared for the delivery of key support systems
including food, transportation, security
monitoring, etc. The costs of the rehiring plan,
payroll benefits, overhead, support
infrastructure, etc are all being integrated into
a comprehensive financial plan to be presented to
the Board, State and Federal officials. - Execute - We have submitted to the State a
revised scope to include three additional
responsibilities that were not part of our
original contract scope - Real Estate key interim leadership is being
provided over the repair work of the 8 schools
and longer term over the physical reconstruction
of the entire school district. AM is providing
the construction project management and
development expertise to oversee this aspect of
the rebuilding effort. - Insurance Claims Recovery Management - key
interim leadership is being provided over the
creation, filing, submission and negotiation, and
eventual receipt of insurance proceeds from both
insurance carriers and FEMA that is necessary in
order to fund the continued rebuilding effort
described above. - Facilities - key interim leadership is being
provided in the ongoing day-to-day cleaning and
maintenance related issues in getting the schools
operational. - The additions to our original scope will not
result in an increasing in the contracts price.
We have accelerated the time frame in building
internal capacity within NOPS to eventually make
redundant the services and expertise being
provided by AM on an interim basis due to our
learning curve over the past few months and no
longer having the need to fix broken pre-existing
systems, but rather build new systems from
scratch. - Finally, the longer term rebuild and renovation
of the majority of NOPS schools that were
damaged more heavily will be the subject of
future status reports and planned in accordance
with the Citys phased re-opening and
repopulating process.
5 Financial Management Accounting
- Key Accomplishments
- Cash
- Modified weekly cash flow forecast for material
changes caused by the post-hurricane environment,
including projections of the following - Remaining payroll amounts owed to the
Districts pre-hurricane employees - Crisis management call center for displaced
employees - Ongoing benefits costs for recalled employees
and furloughed employees - Protection and recovery of critical fixed
assets including data and systems recovery - Loss and/or substantial reduction of cash
receipts from the City and State - Critical administrative payroll and critical
vendors post-hurricane and - One-time and recurring costs to stand up
schools. - Deferred September 1, 2005, bond obligations and
contacted all bond trustees and bond insurers to
provide them with financial and operational
updates. - Communicated financial and operational updates to
other key external constituencies related to the
finances of the District, including bankers and
bond counsel. - Indefinitely postponed 50 million RAN financing
that had been scheduled to close on August 31,
the week of Hurricane Katrina. - Began identifying school-based bank accounts
(student activity fund accounts) listed under
the school boards tax identification number, and
froze all transactions in identified accounts to
ensure security of these funds during immediate
post-disaster timeframe. Continued to work with
Liberty Bank and Whitney Bank on our outstanding
requests to provide the District with remaining
student activity bank account information for
those accounts yet to be identified and frozen. - Monitored daily cash receipt and disbursement
transactions in each of the Districts bank
accounts. Where visibility was not available
during the weeks following the hurricane,
contacted local banks to determine status. - Obtained Federal Reserve safe-keeping receipts
for local banks holding material funds of the
District to ensure security of the Districts
funds during the crisis. - Began consolidating and closing unnecessary
and/or dormant bank accounts, reducing the number
of financial institutions with whom the District
banks in order to streamline management of and
place better controls in the treasury function. - Obtained bond counsel opinion supporting the use
of existing capital project funds (over 15
million) to fund liquidity needs for the school
building repair efforts.
6 Financial Management Accounting (cont.)
- Accounts Payable
- Processed critical payments to vendors necessary
to resume essential activities, including travel
reimbursement requests made by board members. - Segregated pre-Katrina payables from post-Katrina
liabilities for go-forward accounting purposes. - Planning for proof of claim process to manage
pre-Katrina liabilities to vendors. - General Fund Budget
- Developed draft preliminary projection of school
and other operating expenses based on revised
school year and new enrollment assumptions for
submission to the US Department of Education - Began development of revised operating budget for
FY 2005-6. - General Accounting
- Supported payroll team in processing pre-Katrina
payroll in an off-line system as a result of the
damage to the District information systems. - Began recording accounting activity in an
off-line system until the Districts information
systems are fully operational. - Began analyzing and revising chart of accounts,
including disabling of inactive values, to
improve the accuracy and usefulness of accounting
data in the go-forward systems environment. - Began analyzing cross validation business rules
in the oracle system to improve the accuracy and
usefulness of accounting data in the go-forward
systems environment. - Met with Postlewaite Netterville, the
Districts external auditors, to discuss options
and strategies to ensure accuracy and usefulness
of accounting data in the go-forward systems
environment, including the potential creation of
a new oracle instance. - Develop short-term plan to process July and
August transactions against the revised chart of
accounts to identify exceptions/errors. - Special Revenue Accounting Claims
- Visited the Algiers central administration
building to begin documentation recovery efforts
for special revenue claims.
7 Financial Management Accounting (cont.)
- Organizational / Administrative / Project
Management / Crisis Management - Worked with the Interim Superintendent to
identify employees necessary for continued
operations and organized temporary offices at the
Louisiana Department of Education. - Met extensively with FEMA representatives to
determine the procedures, timing, and scope for
federal claims related to hurricane damage. - Coordinated with insurance carriers to collect
claims for hurricane damages. - Work Planned For Upcoming Weeks
- Meet with federal, state and local officials to
articulate anticipated funding requirements of
the District in FY 2005-6. - Assess anticipated revenue streams from the
federal, state and local governments in order to
determine the Districts ability to pay its
obligations on a go-forward basis. - Seek board resolution to approve usage of capital
project funds for Katrina-related school building
repairs. - Finish identifying and freezing all student
activity bank accounts. - Finish closing dormant bank accounts and
consolidate operating and payroll accounts with
two financial institutions. - Complete revisions and clean-up to the chart of
accounts and cross validation accounting rules in
oracle system. - Define requirements for implementation of a new
instance of Oracle for accounting data transfer
interim post-hurricane accounting data into
Oracle. - Assist HR and Payroll in defining requirements
for new HR data warehousing environment. - Propose to the Board the new operating budget for
FY 2005-6. - Implement new operating budget after Board
approval. - Identify additional finance department personnel
needs and recruit temporary and permanent
employees as appropriate. - Process the Success for All (SFA) documentation
for payment and claims reimbursement. - If applicable, begin revising special revenue
budgets based upon anticipated student
enrollment. Build special revenue budget
scenarios for various student enrollment levels,
where applicable.
8 Human Resources and Payroll
- Summary of Activities
- Human Resources
- Established a call center within 24 hours
post-Katrina to locate New Orleans Public School
employees, disseminate information and respond to
questions. To date, we have located almost 7,000
employees through this call center. We have
averaged 2,000 calls a week. Maintained a record
of the calls and responses. As an example, one
day last week included - 594 - Employees called regarding check that has
now been picked-up. - 375 - Employees were paid and initial call to
provide MTCN needs to be made (or notification of
supplemental check w/o MTCN). - 287 - Employees were NOT paid but has called
looking for payment data. - 289 - Employees have specific questions and need
to be contacted (i.e.-questions on amount of
payment, deductions, benefits, etc). - 56 - Employees that we have called and left
messages for. They will call back if they have
further questions/issues. - 220 Incomplete tickets Contact phone
number/email address for the employee not
provided in ticket details. - 12 Specific questions that do not deal with
payroll issues. - Established a NOPS website to increase
communication to parents, students and employees
of NOPS (i.e., Frequently Asked Questions,
current press releases and important information
for NOPS parents and employees). - Updated the call center and website Frequently
Asked Questions daily based on anticipated and
repeat employee questions. - Conducted internal and external meetings with key
stakeholders, including UTNO, PANOPSI, and NOPS
staff, to develop effective recruiting, staffing
and retaining strategy for up to 16 schools so
that we can potentially have those schools up and
running during November, 2005. - Drafted HR related internal and external
communications including press releases, website
communications, FAQs, and call center scripts. - Developed a process for Student and Employee
Indication of Interest. - Collected and communicated with 40 organizations
and individuals who have offered assistance and
donations for New Orleans Public Schools so that
we can be prepared to accept their donations of
books, desks, or funds (e.g., 10 laptops from
Rollins College).
9 Human Resources and Payroll (cont.)
- Summary of Activities (Cont.)
- Developed Student and Employee Indication of
Interest forms (web-based hard copy) to garner
an understanding of those NOPS Parents and
Employees who would like to return to the
district, given the opportunity. - Developed Employee Verification form for those
NOPS employees who will be brought back to ensure
clarity and agreement on salary, benefits,
position, title, location, deductions, etc. - Built agreements with external stakeholders to
post job opportunities outside of the Parish in
an effort to support NOPS employees in generating
an income while they are on Disaster Leave. - Drafted a motion to put before the board to
declare NOPS employees on Disaster Leave so that
they could be eligible for and begin receiving
unemployment. - Began verifying NOPS employees employment so
that they can secure alternate job opportunities
and housing. - Conducted a best practice study on staffing in
large, urban, inner city schools including cities
like Boston, Cleveland, Indianapolis and
Jefferson County. - Calculated estimated vacation and sick leave
liabilities. - Began process to determine ongoing HR data
management/system requirements. - Began processing of terminations, employment
verification requests, mortgage requests, etc. - Helped draft the Disaster Leave Motion that was
approved by the BOD - Scheduled and attended a meeting with the
Louisiana Department of Labor Unemployment
Insurance Division to confirm NOPS employees
eligibility for Unemployment instead of Disaster
Unemployment Assistance. Currently working with
the agency to provide and receive the necessary
information required for eligibility and
reporting purposes. - Met with NOPS third party unemployment
administrator, Temple Resource Management, to
determine the appropriate level of assistance
they can provide as a result of the Disaster
Leave determination for NOPS employees.
Reviewing and revising TRMs proposed contract,
which may be able to reduce the amount of our
state reimbursement. - Scheduled and attended meetings with the Teachers
Retirement System of Louisiana, Louisiana State
Employees Retirement System, and Louisiana School
Employees Retirement System to discuss procedures
for assisting NOPS employees who are interested
in retiring or had questions about DROP. - Responded to questions from the agencies
regarding employee status and developed scripts
for the various retirement agencies to response
to questions from NOPS employees.
10 Human Resources and Payroll (cont.)
- Summary of Activities (cont.)
- Working with Coventry to develop a plan to
provide continuing healthcare coverage to
impacted employees. Coordinated September
premium payments and participant eligibility for
September October. Working to try to resolve
participant discrepancies related to the
non-completion of the open enrollment process. - Continued reviewing the red-lined version of
Coventry contact. Received 4th Amendment to
previous contact in lieu of new contract. - Worked with third benefits party administrator,
Fringe Benefit Management Company, to assist with
the continuation of non-Coventry benefits.
Coordinating the distribution of COBRA notices
and the collection/remittance of COBRA premiums
for eligible individuals. - Worked with UTNO regarding the provision of
benefits to members through the Health Welfare
Fund, including Coventry and FBMC/FARA benefits. - Coordinated Workers Compensation payments with
our third party administrator, Hammerman
Gainer. Working to create a process for meeting
our statutory obligations and manage cash flow. - Assisted AFT and LFT as they were trying to
locate their members/our employees. Tried to
utilize their website for job opportunity
postings. Arranged to have job postings put on
LDE website. - Payroll
- Located payroll employees and updated contact
information. - Worked with IT, Finance, and HRIT resources to
develop an Excel-based estimated payroll which
was disbursed via Western Union on 9/13/2005. - Using an existing list of current employees and
salaries, performed analyses and used filters to
identify the employee population and salaries
eligible for estimated payroll payments - Screened the employee population for retirement
plan participation and assigned relevant
employees to the assumed relevant retirement
plan - Analyzed recent Coventry file and matched against
estimated payroll file matched appropriate
Coventry plan level for all paid employees - Analyzed file received from State of Louisiana to
determine certification status of all personnel
and arranged PEP payment for appropriate
certificated personnel - Calculated federal, state, Coventry,
retirement/social security, and Medicare
withholdings for paid employees
11 Human Resources and Payroll (cont.)
- Communicated with Western Union to determine the
content and format of payroll data to be
transmitted - Sent all estimated payroll files to Western Union
and performed reconciliations against
returned/processed Western Union files - Compared estimated payroll against actual payroll
calculations and calculated difference, if any,
owed to each employee. - Worked with HRIT and IT resources to bring up an
operating Oracle instance and production
environment. - Processed the actual payroll by 9/14.
- Summary of Activities
- Began reconciliation process between Estimated
payroll and Actual payroll. Expected completion
by 10/7/2005. - Worked with Coventry benefits provider and HR
staff to develop move ahead plans for the month
of September concerning employee benefits. - Continuing to work with Western Union on payroll
funds disbursement. - Beginning the process of developing plans and
procedures for perfecting FEMA related claims as
they pertain to payroll costs. - Developed plans and procedures for the filing of
payroll tax returns subsequent to the last Oracle
based payroll. - Developed RFP for Outsourced Payroll/HR vendors.
- Beginning to develop plans and processes for the
go-forward payroll system and department. - Worked with ADP to develop a short term, interim,
payroll processing and disbursing solution. - Implemented the ADP PC/PW payroll system.
- Began the process of reconciling and closing the
Oracle Payroll System and working with ADP to
print 2005 W2s. - Began the process of collecting and storing
necessary Oracle system payroll data. - Began developing plans and processes to
facilitate the opening of schools and additions
of returning personnel to payroll system by
11/01/2005.
12 Human Resources and Payroll (cont.)
- Summary of Activities (cont.)
- Performing general payroll clean-up activities.
- Developed new payroll calendar for remainder of
2005. - Converted payroll data to ADP payroll format.
- Worked with finance and accounting to develop new
accounting string structure for go-forward
payroll system. - Assisted HRIT and budget personnel in activities
involving Position Control development. - Analyzed earnings and deduction element.
- Work Planned For Upcoming Weeks
- Human Resources
- Continue to maintain and monitor call center to
locate New Orleans Public School employees,
disseminate information and respond to questions.
- Continue to monitor and update NOPS website to
increase communication to parents, students and
employees of NOPS (i.e., Frequently Asked
Questions, current press releases and important
information for NOPS parents and employees). - Monitor and analyze Student and Employee
Indication of Interest via web-based hard copy
forms. - Begin to execute recruiting, staffing and
retaining strategy for up to 16 schools. - Develop, as required, HR related internal and
external communications including press releases,
website communications, FAQs, and call center
scripts. - Continue to collect and communicated with donor
organizations and individuals who have offered
assistance and donations for NOPS so that we can
be prepared to accept their donations of books,
desks, or funds. - Populate Employee Verification form for those
NOPS employees who are brought back to ensure
confirmation, clarity and agreement on salary,
benefits, position, title, location, deductions,
etc. - Continue to develop agreements with external
stakeholders to post job opportunities outside of
the Parish in an effort to support NOPS employees
in securing employment while they are on Disaster
Leave. - Continue to verifying and processing of NOPS
terminations, employment verification requests,
mortgage requests, etc.
13 Human Resources and Payroll (cont.)
- Work Planned For Upcoming Weeks (cont.)
- Continue process to determine ongoing HR data
management/system (position control) requirements
including strategic outsourcing opportunities. - Continue to work through Unemployment Insurance
to confirm NOPS employees eligibility for
Unemployment instead of Disaster Unemployment
Assistance. Work with the agency to provide and
receive the necessary information required for
eligibility and reporting purposes. - Revise TRMs (unemployment TPA) proposed
contract, to reduce the amount of our state
reimbursement. - Finalize procedures for assisting NOPS employees
who are interested in retiring or had questions
about DROP. - Continue to respond to questions from the
Retirement agencies regarding employee status and
develop scripts for the various retirement
agencies to respond to questions from NOPS
employees. - Work with Coventry to finalize a plan to provide
continuing healthcare coverage to impacted
employees. Coordinate September premium payments
and participant eligibility for September
October. Work to try to resolve participant
discrepancies related to the non-completion of
the open enrollment process. - Summary of Activities
- Finalize the red-lined version of Coventry
contact. - Work with third benefits party administrator,
Fringe Benefit Management Company, to assist with
the continuation of non-Coventry benefits.
Coordinate the distribution of COBRA notices and
the collection/remittance of COBRA premiums for
eligible individuals. - Determine which non-healthcare coverages (i.e.,
dental, vision, life, etc) to continue,
eliminate, or amend. - Work with UTNO regarding the provision of
benefits to members through the Health Welfare
Fund, including Coventry and FBMC/FARA benefits. - Continue to coordinate Workers Compensation
payments with our third party administrator,
Hammerman Gainer. Create a process for meeting
our statutory obligations and manage cash flow. - Finalize staffing, hiring and on-boarding process
for NOPS and non-NOPS employees. - Develop NOPS organization charts.
14 Human Resources and Payroll (cont.)
- Summary of Activities (cont.)
- Payroll
- Continue to located payroll employees, update
contact information and respond to payroll
questions. - Reconciliation process between Estimated payroll
and Actual payroll. Expected completion by
10/7/2005. - Continue to work with HRIT and IT resources to
bring up an operating Oracle instance and
production environment. - Process bi-weekly payroll for employees brought
back. - Finalize plans and procedures for perfecting FEMA
related claims as they pertain to payroll costs. - Finalize plans and procedures for the filing of
payroll tax returns subsequent to the last Oracle
based payroll. - Continue to develop plans and processes for the
go-forward payroll system and department to
include decision regarding earning and deduction
elements. - Refine the ADP PC/PW payroll system, interim,
payroll processing and disbursing solution. - Reconcile and close the Oracle Payroll System and
work with ADP to print 2005 W2s. - Collect and store necessary Oracle system payroll
data. - Continue to evaluate new risk environment and
developing revised payroll controls. - Continue to refine new payroll time entry
processes. - Continue to perform general payroll clean-up
activities. - Continue to work with finance and accounting to
develop new accounting string structure for
go-forward payroll system.
15 Procurement
- Summary of Activities
- Reviewed District Insurance Policies.
- Various conversations with Districts Risk
Manager concerning Insurance Policies. - Reviewed LA state emergency procedures/policies.
- Attended various meetings with Department of
Education, FEMA, OEP. - Reviewed FEMA Public Assistance materials,
policies, and procedures. - Read and Reviewed 44 CFR Part 206 and Part 13 of
the Stafford Disaster Act. - Arranged for tours of the Council for the Great
City Schools at various school facility/properties
. - Coordinated with Security personnel in securing
open properties. - Worked with Facilities to properly procure
emergency contract repairs on 10 schools. - Reviewed Districts and States Emergency
Procurement Policies. - Developed interim, non-Oracle based Requisition
and Purchasing processes. - Began developing informal RFPs for Construction
services, Custodial services and Environmental
services. - Met with States Child Nutrition officials in
developing an interim Food Service Program. - Worked with Transportation department in
developing informal RFPs to provide interim
transportation services. - Worked with Security department in developing an
interim, near term Security plan. - Created timesheets for Security personnel in
order for them to track time for FEMA
reimbursement purposes. - Participated in various meetings and follow-up
discussions with FEMA, LDE, NOPS and AM
personnel. - Met with local Councilwoman of Algiers and
National Guard representative to seek help in
debris removal and other general clean-up
activities along with seeking temporary lodgings
for AM and NOPS personnel in Algiers.
16 Procurement (cont.)
- Work Planned For Upcoming Weeks
- Prepare and send informal RFPs for
- General Contracting Construction Services
- Environmental Consulting Services
- Janitorial and Custodial Services
- HVAC Repair and Contracting Services
- Transportation Services
- Food Services (procurement of food supplies only)
- Complete implementation of Emergency Procurement
processes/procedures. - Work with the IT department to map/upload manual
Emergency Procurement process/procedures with
Oracle. - Research and implement strategic sourcing
arrangements for - Office and school supplies
- Computers, printers and other related peripherals
- Copiers, fax machines and other related
peripherals - Work with the Security department to establish
appropriate manpower levels and procure supplies
necessary to re-establish security presence at
schools. - Work collaboratively with State Officials and the
Child Nutrition department to provide food
services for initial school openings.
17Information Technology
- Summary of Activities
- Secured a Post-Katrina Disaster Recovery site and
established an operational NOPS Oracle
environment - Secured backup tapes for Oracle, operating
systems and student information from Data Center
in New Orleans - Negotiated a processing contract with IBM to use
their disaster recovery data center in Tuxedo,
New York - Transported and delivered 170 backup tapes
- Restored operating systems and management systems
- Restored Oracle in Test and Production instances
- Established a VPN for access by NOPS and AM
users to Oracle applications - Located and secured key NOPS IT leadership and
personnel - Processed a Post-Katrina Payroll
- Validated the data from the backup tapes as NOPS
Oracle payroll and HR information - Located and secured key NOPS payroll personnel
for processing of payroll from the AM Houston
office accessing the Oracle applications located
at the IBM disaster recovery data center in New
York - Facilitated and supported the running of three
payroll cycles in a production instance to create
the payroll for the 3 payroll cycles disrupted by
Katrina in an organized and systematic process
with appropriate backups and security - Concurrent to the processing of the Oracle
payroll, facilitated and supported the
development of an payroll advance file for
employees distributed around the country so they
could be paid as soon as possible - Supported the development roll-out of a
pre-registration call center for parents of
students - Supported the development of the AM NOPS website
18Information Technology (cont.)
- Communicated with the state CIOs of New York,
Michigan and Utah and the independent school
districts in Dallas and Richardson, Texas, where
Oracle Public Sector is also implemented to
determine what assistance could be offered - Performed a high-level evaluation of other
financial software solutions for the short-term
bridge period and concluded that Oracle would
scale much better than the other software
solutions - Negotiated and established a short-term bridge
payroll solution with ADP to process payroll for
the next few months while a longer-term payroll
and possibly HR solution goes to RFP and is
selected - Negotiating with IBM, Oracle and Savvis for
outsourcing of the Oracle Financial applications
for a bridge solution while a longer-term hosting
solution goes to RFP and is selected - Assessed the NOPS IT infrastructure and
reestablished operations where appropriate - Performed a physical assessment of the data
center at 3510 General De Gaulle and determined
that the building was un-inhabitable and
unsuitable for housing NOPS data center assets - Assessing the IT assets at schools to insure that
as schools return to operations and that the
computers and network connectivity are working - Developed an interim plan for the non-Oracle
applications/systems to reside at a 3rd party
data center. Negotiations BellSouth, Cox
Communications or Network Technology Group were
completed. Cox Communications, our existing
network and telephone carrier, has offered their
New Orleans data center facilities free of charge
for as long as NOPS needs this transitional
support - Reestablishing the following key operations of
the systems - SASI The Student Information System
- Winsnap cafeteria systems
- Telephone and data networks
- Instructional Technology Distance Learning
- Help Desk and PC Support
- Email and website
- Terminated Verizon Blackberry users for
employees not on NOPS active payroll
19Information Technology (cont.)
- Assisted and supported the definition of the new
HR, Payroll, Financials and Procurement - operating model and Oracle instance
- Working with the Finance Team and state auditors
to define regulatory reporting data
requirements - Working with Finance and HR/Payroll Teams to
design operating model requirements to align with
the rebuilding of the schools and the return of
students teachers - Working with Finance and HR/Payroll Teams to
design requirements to align with the rebuilding
of the schools and the return of students
teachers - Researching document management solutions for
FEMA documentation reporting - Supported communications
- Interacted with the media regarding the disaster
recovery experience - Facilitated the development of joint NOPS AM
work plan for Post-Katrina activities
20Facilities and Maintenance
- Executive Summary
- Over the last month, the Facilities Maintenance
team has focused on assessing the damage
inflicted on the Orleans Parish schools due to
Hurricane Katrina, identifying those schools that
are best suited to be re-opened and initiating a
plan to repair the damages. - In order to assess the damage to the schools, we
contacted the Council for Great City Schools for
assistance. This non-profit organization offered
six engineers/architects to work with the
AM/NOPS team to perform an initial assessment
and to provide their input on how best to address
the situation based on their prior experiences.
Over a two day time period, the team assessed 21
schools across the West Bank and Uptown District.
Excessive flooding was not the main issue at
these sites. Rather, most of these schools
exhibited damage due to high winds that resulted
in broken windows, damage to roofs, downed gutter
and water spouts, broken branches and general
debris. Additionally, the Hurricane provided
power outages, which subsequently resulted in the
rotting of perishable foods and various degrees
of mold and mildew. - After performing the assessment of the schools,
the Council for Great City Schools made a
recommendation that up to 16 of these schools
could be re-opened in a relatively short time
period. These schools included the following - West Bank Schools
- Behrman Walker Harte Karr
- Fischer Eisenhower Rosenwald Henderson
- Uptown District
- Audubon Banneker Arthur Ashe Lusher Extension
- Bauduit Allen McNair McDonough 7
- Lusher Extension, as well as Lusher, have been
identified as Charter schools by Tulane.
Therefore, we are responsible for making repairs
in order to allow them to open the schools on
January 1st, but we are not responsible for
staffing these facilities. - We subsequently met with Mayor Ray Nagin and
decided to develop a plan for opening those
schools on the West Bank only for November,
pending the demand level shown by interested
students. In the Mayors opinion, the Uptown
District still does not have drinkable water and
is resource-constrained regarding
hospital/medical facilities and sewage capacity.
The Mayor suggested we concentrate on the West
Bank Schools for November and allow some time to
lapse for Uptown and other areas, as the City
brings back essential services in those areas
more gradually than our November 2005 timeframe.
We concur with the Mayor as our primary concern
is the health and welfare of our students and
employees.
21Facilities and Maintenance (cont.)
- Executive Summary (cont.)
- The plan to repair the schools for a possible
November re-opening has followed a multi-step
process. First, the team quickly contacted
several vendors to make emergency repairs, e.g.
boarding up holes on the roof, boarding up broken
windows, etc., in order to limit any further
damage. Secondly, the team went back to the 16
priority schools to perform detailed assessments
where we quantified all repairs to be made.
Simultaneously, we met with FEMA representatives
several times to ensure that our documentation
and level of detail was meeting their
expectations. - The detailed assessments are in the process of
being consolidated. We will send them to FEMA,
who will subsequently create the Project
Worksheets and initiate the process for future
reimbursement. The detailed assessments are also
being delivered to various General Contractors as
part of an overall Request For Proposal (RFP) to
determine who will make the repairs to the
schools. In addition to identifying the General
Contractor, the team has begun working with the
Procurement team to develop Bid packages to
address various other needs, including custodial,
environmental, food services, transportation and
waste removal.
22Facilities and Maintenance (cont.)
- Key Accomplishments
- Developed plan for assessing damage to schools
with intent of determining when to re-open
schools. - Developed Facilities Maintenance Workplan to
help focus our efforts for the coming weeks. - Assembled team to assess schools most likely to
have received least damage. Team members
included 6 members from the Council for Greater
City Schools, UTNO representative, FEMA
representatives, Johnson Controls, NOPS and AM
resources. - Teams inspected 21 schools across the West Bank
and Uptown districts. - Outcome of the inspection was the determination
that the following 16 schools could be opened in
the November time period West Bank schools
(Behrman, Walker, Fischer, Eisenhower, Harte,
Karr, Rosenwald and Henderson) and Uptown schools
(Audobon, Banneker, Lusher Extension, Arthur
Ashe, Badouin, McD 7 , Allen, McNair). As a
note, Lusher Extension is now a Charter school
for Tulane and therefore needs to be repaired by
January 1st. - Facilities Maintenance workplan developed to
guide team towards a November 1st school opening. - Paul L. and Frank gained access to Almonaster
site on Tuesday, September 20th to obtain keys to
schools. Keys had rust removed and were cleaned
in order to utilize. - Following the prioritized school listing, Paul
and Frank accessed schools to ensure rooms were
open and to determine cases where rooms could not
be opened. - Contacted military group in West Bank to assist
in getting the 8 West Bank schools ready.
Military will mow lawns, weed and pick-up
garbage/debris. - Met with Johnson Controls on Tuesday, September
20th to discuss short term and long term needs
for the schools. - After gaining agreement on the 16 priority
schools to re-open, the Facilities Maintenance
team contacted the appropriate contractors to
perform emergency repairs, e.g. close holes in
the roof, board up broken windows, secure access
to facilities, etc. - Met with FEMA (Michael Jacques) on Thursday,
September 22nd to discuss project worksheet
development process. Due to limited FEMA
resource availability (re Hurricane Rita), Ron
Leone, Amy Carbonette and Marty McFarland
inspected schools, developed detailed assessments
and then reviewed with Michael Jacques on Monday,
September 26th to get his feedback on the
content. - Amy, Ron and Marty performed detailed assessments
of the 16 priority schools between Monday,
September 26th Wednesday, September 28th - Met with Procurement to develop General
Contractor bid.
23Facilities and Maintenance (cont.)
- Key Accomplishments (cont.)
- Met with an Environmental Group (EEG) on
Wednesday, September 28th to begin process of
collecting key criteria to be included in the RFP
package. - Met with Custodial Services Group (AME) on
Wednesday, September 28th to begin process of
collecting key criteria to be included in the RFP
package. - Coordinated access to schools with Risk
Management (Greg Risher) in order to allow for
Insurance Adjuster reviews. - Coordinated access to schools with IT team to
allow for them to perform detailed assessments. - Paul and Frank determined the number of external
access points to the schools in order to plan for
implementing a standard locking system. - Met with Johnson Controls on Friday, September
30th to discuss HVAC issues per the 16 priority
sites and performing an operational assessment to
ensure were ready for school re-opening. - Performed a detailed assessment of the West Bank
Transportation Depot to provide feedback to
potential transportation companies, as well as to
include repair needs in the General Contractor
RFP. - Work Planned for Upcoming Weeks
- Complete and distribute RFP packages to support
the need for the General Contractor,
Environmental group, Custodial Services, Waste
Removal, HVAC and Transportation. - Confirm plan for implementing a standard locking
system across the schools. - Develop and confirm a plan as to how we can best
track the progress of the various providers who
will soon begin work on the 16 priority schools. - Conduct QA calls and site visits with the
various bidders. - Work with the Procurement to ensure we are
following the correct process, i.e.
documentation, approvals, etc. - Gather bids and select service providers.
- Perform detailed assessment of fire alarm and
intercom systems to determine needs.
24Facilities and Maintenance (cont.)
- Issues, Comments and Other
- The priority issue for the team is the
uncertainty as to the magnitude of the
environmental issues. We have met with an
environmental firm to understand the key
activities to be performed in order to certify
that schools are ready to be re-opened and will
use this input as the basis for the RFP.
Additionally, we will offer the opportunity for
bidders to tour the facilities to better gauge
the scope of work. These activities should
provide further clarity, but at the moment, the
scope, effort and costs of the environmental
issue are not obvious. - Limited FEMA resource availability requires the
Facilities Maintenance team to create the
detailed contents, which will eventually be
included in the project worksheets to be
developed by FEMA Project Officers. - The team needs to relocate to New Orleans to more
effectively oversee the work on the schools. - Need to expedite the RFP process to confirm the
necessary providers, including the General
Contractor, HVAC, Environmental Group, Custodial
Services, Waste Removal, Food Services and
Transportation. - Due to resource and financial constraints, the
team has not begun the assessment of the
remaining 95 schools and district facilities.
Emergency repairs have not been initiated.