Title: Prsentation PowerPoint
1Regional PPP Workshop Riga, March 6-8 2007 The
French PPP Experience in the Rail Sector
Thomas VIEILLESCAZES Director France Southern
Europe DIF (Dutch Infrastructure Fund) www.dif.eu
2- Introduction
- Objectives of the PPP in the Rail Sector
- The Perpignan-Figueras Project
- Future Developments
3- Introduction
- Objectives of the PPP in the Rail Sector
- The Perpignan-Figueras Project
- Future Developments
4Introduction
- French rail sector a fully public-administered
sector so far progressively opening (1st
private freight train operated on june 2005) - A sector that heavily relies on public financing,
heavily indebted - Few participation of the private sector
- Laws regulation provide for monopoly of State
public companies for project undertaking and
infrastructure operation maintenance
Project financing
Allocation of Risks
- Infrastructure manager (RFF) pays the NPV of the
free cash flows - Railway undertaking (SNCF) pays for rolling stock
- State regional public authorities pay for the
rest (70 of investment)
- All risks (construction, traffic, maintenance)
borne by public sector - Use of subsidies (during construction period) for
Public part of financing - Important assymetry of information, few direct
control on execution from administration
French Public Sector Organization Is Likely to
Evolve Allocation of Risk Clearly Not Optimal for
Public Sector
5Introduction
An amibitious High Speed line 8yrs, 15 BN
investment program
with ever-shrinking budgetary capabilities
- 2004 setting up of a government agency for
transport infrastructure financing, to use money
from the road (dividends initially) to finance
rail - Use PPP as alternative means of financing
projects transfer project ownership to private
companies to seek for efficiency More for
less! - Mediocre project profitability a major drawback
(good projects done already!)
6- Introduction
- Objectives of the PPP in the Rail Sector
- The Perpignan-Figueras Project
- Future Developments
7Objectives for PPPs in the Rail Sector
- Leverage new ressources for the rail sector with
the usage of private funds - Optimize global investment costs, construction
and allocation of risks on rail infrastructure
projects with a better integration of
construction, operation and maintenance tasks - Lower the cost for the National community and
lower the impact of the debt of RFF - Accelerate the development of the National rail
network by constructing more projects in lesser
time enforce the decision taken by the
Government on dec. 18th 2003 - Improve competitiveness of rail mode
8Three Schemes to be Contemplated
Classical scheme (HSL East, Rhin-Rhône ) RFF
is project undertaker, subsidies to be put in
place ab initio Infrastructure PPP RFF is
contracting authority, public availability
payments occur during the life of the contract,
demand-traffic risk generally borne by Public
sector Concession Gov't or RFF as contracting
authority, Public subsidies ab initio, Project
undertaking, financing and operation at the own
risks of the concessionaire
9Risk Sharing Matrix
10Changes with the law 2006-10 of Jan. 5 2006 on
the Security and Development of Transports
- The State and RFF are allowed to use the PPP
contract (contrat de partenariat) or the
Concession for the provision of National rail
infrastructure - The contract can contemplate the construction,
maintenance and operation of part or all
infrastruction, with the exception of trafic
asignment procedures and operation and
maintenance of safety installations, which
continue to be undertaken by SNCF. - Creation of the Rail Safety Agency, independent
from RFF and SNCF, in charge of all (PPP and non
PPP) projects, in charge of authorizations
regarding safety, interoperability (safety
certificates, safey agreements, etc.)
11- Introduction
- Objectives of the PPP in the Rail Sector
- The Perpignan-Figueras Project
- Future Developments
12Perpignan-Figueras Project
13Project Rationale
- France Spain have different rail gauges
(1.435m -UIC gauge- in France Europe, 1.676m in
Spain) - Since 1988, Spain has progressively developed a
UIC gauge network - The Perpignan-Figueras project will directly link
the spanish rail network to the rest of Europe
(European TEN-T top priority project) - Relieving this bottleneck will have major impact
on both freight passenger transport - 10 hours for freight (4.2 MM added tons p.a.)
- 2 hours for passengers (2.6 to 3.5 MM added
passengers p.a.) - Project under discussion/study on a
Franco-Spanish basis since 1992
0.5 MM inhab.
0.2 MM inhab.
2 MM inhab.
1995 Madrid Treaty Perpignan-Figueras will be
constructed as a Concession (Treaty Also Sets Up
Concession Framework)
14Project description
A 50 km-long freight High-Speed link, the first
of its kind in Europe
- Freight trains 100-120 km/h
- High-Speed trains 300-350 km/h
- 5 bridges
- Links to French UIC network at Perpignan
- Links to Spanish new UIC line (under
construction) Figueras-Barcelona - a 8 km-long tunnel
- dual-tube with safety galleries
- A 1 Bn investment
15The Concession
- The concession has been granted through a
bi-national tender process (EEC Directive
93/37) - under the aegis of the French Spanish States
- The Concessionaire will Build Operate the rail
link (as an Infrastructure Manager), then
Transfer it back to the States - Design of the Project was undertaken by States
(subcontracted to a JV formed by the 2 public
railways companies no infra managers) - Concessionaire will build finance the project
at its own risk - Concessionaire will receive a subsidy for the
construction of the project - Concesionaire will operate and manage the
infrastructure (maintenance, availability,
performance, security, ) at its own risk - Concessionaire will levy tolls on Train Operating
Companies (SNCF, RENFE, others) operating
freight, passenger high speed trains tolling
scheme will be specified in the Concession
contract - At the expiry of the Concession period, project
will be transferred to the States in the exact
shape it was at the opening of the line
16Tender Organization
France
Spain
Inter-Government Commission
Selection Commitee
- Representatives of 2 administrations
- In charge of 1995 Treaty implementation
- Assists the 2 Govts during tender preparation
process
- Evaluates selects candidates bids
- Experts from 2 countries
Negociation Commitee
- Negociates the contract
- Experts from 2 countries
Technical group
Legal group
Economics Finance group
Construction Exploitation
Contract issues
Tarification Financing
Technical support
Legal counsel
Financial advisor
Tendering and Contract Negotiation Were
Undertaken Directly Jointly By The Two
Administrations
17The Tender Process
- Tender preparation was launched in May 2000
(Santander Franco-Spanish summit - Technical preparation
- Legal framework preparation of the Consultation
Rules/ terms of reference/ draft of the
Concession contract - July 2001 Tender published at the OJEC
- Oct. 1st, 2001 6 candidates
- Nov. 2001 all candidates are permitted to submit
bids - April 2002 6 bids received
- July 2002 EUROFERRO (Bouygues- Dragados)
selected as preferred bidder - Sept. 2002 negotiations start with EUROFERRO,
6 bidders, mostly major civil works constructors
in Spain France (Bouygues-Dragados,
Eiffage-ACS, SPIE-FCC, Acciona-Sacyr,
Vinci-Ferrovial) and the incumbent infrastructure
managers (RFF-GIF)
18The Tender Process (Contd)
April 16th 2003 negociation with
Bouygues-Dragados interrupted May 8th 2003 new
tender published in OJEC
- A Tender as closed as possible
- Benefit from Tender 1 experience
- Major innovation candidates are invited to bid
on an non-negociable draft contract (except a few
clauses), based on Tender 1 contract as finally
negociated - No technical options allowed to ease comparison
- Objective reach a conclusion as fast as
possible - But doubts about number of candidacies and level
of subsidies demanded - July 2003 4 candidacies
- RFF-GIF, ACS-Dragados-Eiffage (ACS bought
Dragados during Tender 1), Bouygues-FCC,
Ferrovial-Vinci - All candidacies accepted, bids received October 7
2003 - November 13 TP Ferro (ACS-Dragados-Eiffage) and
Ferromed (RFF-GIF the two State-owned
companies) are invited to negociate with the two
governments
19The Tender Process (Contd)
- December 26, after ameeting of the Council of
Ministers in Spain, the two governments announce
they are about to conclude with TP Ferro
Concession contract signed in Madrid February
17th for a 50-year duration
- Construction costs 952 M (Jan 03). 32 of
costs related to tunnel - Planning 60 months delivery starting Feb. 17th
2004 - Tolling scheme in the contract, with first 3
years of operations limited fee to allow for
build-up of traffic (as set in terms of
reference) - State Subsidy 540 M (57 of construction
costs), shared by France Spain (50/50) EU,
paid during construction - Sponsor equity 102,9 M, closing had 1 year to
take place - No guarantees concesionaire will operate the
concession at its own risk - Penalty system for construction, performance,
termination, etc. - Contract is made public (integrally published in
French official journal)
Debt financial closing took place Feb 10th 2005
with a project finance scheme, 520 M with
limited recourse on the sponsors
20The Concession (Contd)
Inter-government Commission (CIG)
Security commitee (tunnel)
Contractual relationship
States
Train Operating Companies
Toll Payments
Subsidies
European Union
Concessionaire
99.8 regularity
Sponsors
Equity
RFF (France)
Route definition Interfaces
Banks
Debt
Construction company
GIF (Spain)
Insurances
21Lessons Learned
- Excellent collaboration between the
administrations of the 2 countries on a
cross-border project - Technically, a major project within the
pan-european rail network - A breakthrough project for the rail sector
- Application of the highway concession model to
rail, a success so far for a project that was
found difficult from the very beginning - New player private between two public Infra
managers - Interaction with incumbent train operating
companies (SNCF, RENFE) for both train operation
and infrastructure management - Proof that PPP in the rail sector is feasible,
with effective full transfer of risks to a
private operator - Construction/completion risks
- Operational/traffic risk maintenance risk
- Tender procedure was long and difficult but
- Administrations learned (so did the candidates)
- Major innovations have been successfully
introduced - Challenges still ahead traffic, operation,
completion of national connecting lines
22Project on Track for Opening in 2009
23- Introduction
- Objectives of the PPP in the Rail Sector
- The Perpignan-Figueras Project
- Future Developments
24Tours Bordeaux HSL Project
- LGV Sud-Europe-Atlantique, a High-Speed line
project linking Paris to Bordeaux in 2 h is the
next infrastructure project to be launched as a
concession - Challenges
- Size of the project, over 300 km, 4,5 BN
- Project economics are they strong enough to
make the project bankable? - Interfaces with existing network (several
connexions) and future projects - Project divided into two phases, long period of
civil works, risks - Co-financing with regional authorities needs
solidarity on the long run, way over polical
rythms - Concession prequalification launched in February
Paris
Existing High-Speed Line
Bordeaux
Toulouse
Spain
TGV SEA Will Be a Test on How Innovative Schemes
Can Be Put in Place in France For Very Large
Scale Projects
25 Nîmes Montpellier Bypass
- Existing line crossing Nîmes and Montpellier is
saturating progressively - The new 70 km line will create a pair of lines
allowing freight trains to run out of cities - Mix High-Speed Freight trains
- TEN-T top priority project (along with Perpignan
- Figueras
- Cost of 1,2 billion
- Project ready, land control under way
- Will be launched as a PPP (contrat de
partenariat, DBFO) where RFF will pay an
availability fee to the project owner - Preparation of the tender underway
Will Be a Test of The PPP (DBFO) Model on Linear
And Costly Infrastructure
26About DIF
- An independant, continental Europe-based, Equity
investment fund focusing on PPP projects in
Europe - 150 MM closed in March 2006 (investors
individuals, Dutch pension funds, Helaba,
Sumitomo Mitsui Bank, European investment bank) - An experienced team of professionals with a
background in Project Financing and PPPs
- Todays focus on Western Europe, primarily
Benelux, France, UK, Germany - New markets, especially Eastern Europe, to be
considered in the future - A flexible, aggressive, independant fund,
acquiring majority/minority positions in both
Greenfield and Brownfield projects in the PPP
sector - 7 projects already acquired in France, UK
(including Frances first PPP project) - Participating in several tenders across Europe
- Core team in Amsterdam branch just set up in
Paris
27Thank you for your attention
Thomas VIEILLESCAZES Director France Southern
Europe DIF (Dutch Infrastructure Fund) Mobile
(France) 33 6 87 96 66 61 Phone (Holland) 31
mailto t.vieillescazes_at_dif.eu www.dif.eu