BOND PROGRAM UPDATE Building Tomorrow Today - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

BOND PROGRAM UPDATE Building Tomorrow Today

Description:

Building Tomorrow Today. Long Beach Community College District ... Modern Facility Houses Machine Tools and Welding Depts. New Campus 'Bookend' ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 17
Provided by: BillA91
Category:

less

Transcript and Presenter's Notes

Title: BOND PROGRAM UPDATE Building Tomorrow Today


1
BOND PROGRAM UPDATEBuilding Tomorrow Today
  • Long Beach Community College District
  • Student Support Services Road Trip 2007

Flex Day, March 28, 2007
2
AGENDA
  • Completed Construction Projects
  • Current Upcoming Construction Projects
  • South Quad Complex Bid 2
  • LAC Central Plant Structure
  • LAC Learning Resources Center Interim
  • LAC Learning Resources Center - Structure
  • South Quad Complex Structure
  • PCC Central Plant Utilities
  • PCC Learning Resources Center
  • PCC Industrial Tech Phase 1
  • PCC Industrial Tech Phase 2
  • Whats Next?
  • Q A

3
COMPLETED CONSTRUCTION PROJECTS
Various Projects
  • PCC CDC 4/06
  • District Facilities Warehouse Complex Opened
    1/17/06
  • Mens Gym Boiler Replacement 4/06
  • PCC MM/NN Lighting Upgrade 4/05
  • LAC Athletic Field 3/06
  • South Quad Complex
  • Bid Pkg. 1 12/05
  • LAC/LRC Utilities6/06
  • LAC Mens Gym Façade Replacement (FEMA
    Insurance Funded)
  • East Campus Demolition

4
LAC Construction Phasing
5
CURRENT UPCOMINGCONSTRUCTION PROJECTS
South Quad Complex Bid Package 2
  • Construction 98.5 Complete
  • Relocation of Water Main and Reclaimed Water
    Lines
  • Coordinated with Central Plant
  • Relocates Major Utilities Out of
  • Golf Mall
  • Clears Way for Structures

6
CURRENT UPCOMINGCONSTRUCTION PROJECTS
LAC Central Plant Structure
  • Part of Infrastructure Master Plan Improvements
  • Early Utility Package Under Construction
  • Awarded to Siemens on DBOM Contract
  • Construction Starts April Contractor Mobilizing
  • Completion Anticipated Summer 2008

7
CURRENT UPCOMINGCONSTRUCTION PROJECTS
LAC/Learning Resources Center Interim Facilities
  • Construction 50 Complete
  • Anticipate Completion June 2007
  • Modular Buildings to be Installed Saturday
    3/31/07
  • Utility Installation Complete Under Previous
    Phase (Bid Pkg. 1)
  • Includes Retrofit of Building E Basement

8
CURRENT UPCOMINGCONSTRUCTION PROJECTS
LAC/Learning Resources Center Structure
  • Re-Bid Opening 3/29/07
  • First Bids Rejected Move Planning Underway
  • Utility Installation Complete Under Previous
    Phase (Bid Pkg. 1)
  • Anticipate Start in June 2007 Completion in
    December 2008

9
CURRENT UPCOMINGCONSTRUCTION PROJECTS
South Quad Complex Structure (Bid Pkg. 3)
  • Construction Begun Approx. 35 Complete
  • Overlaps Central Plant Early Piping Due to
    Utility Conflicts
  • Additional Modern Classrooms, Multi-purpose Rm.,
    Offices, etc.
  • Shifts Campus Center South of Carson off Lew Davis

10
PCC Construction Phasing
11
CURRENT UPCOMINGCONSTRUCTION PROJECTS
PCC Central Plant Utilities
  • Part of Infrastructure Master Plan Improvements
  • Early Utility Package Under Construction Approx.
    98.5 Complete.
  • Allows Utility Installation while Structure is in
    Plan Check
  • Clears Way for Structure
  • Structure in Plan Check
  • DBOM Contract Awarded to Siemens Anticipate NTP
    April (NOI Issued)

12
CURRENT UPCOMINGCONSTRUCTION PROJECTS
PCC Learning Resources Center
  • Awarded to Soltek Pacific
  • Construction Start in April Pending State
    Authorization
  • Modern Facility with Computer Lab and Multimedia
  • Expanded Facility
  • Bridge to Bldg. EE
  • Art Deco Style

13
CURRENT UPCOMINGCONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 1
  • Replaces Existing Antiquated Structures
  • DSA Reviewing Changes Out to Bid Start in July
    2007
  • Modern Facility Houses Machine Tools and Welding
    Depts.
  • New Campus Bookend
  • S.E. Interim Bungalow Construction In Close Out
    Phase to Clear Tech 1 Site

14
CURRENT UPCOMINGCONSTRUCTION PROJECTS
PCC Industrial Technology Center Phase 2
  • Replaces Existing Antiquated Structures
  • Construction Underway Approx. 53 Complete
  • Modern Facility Houses Aviation and Automotive
    Depts.
  • Impacted by DFWC
  • Completion in Summer 2007

15
WHATS NEXT?
Secondary Projects LAC PCC
  • Multi-Disciplinary Academic Buildings (AA, BB,
    DD, EE)
  • Awaiting State Approval to Start Design Antic.
    August 2007
  • Construction 2009
  • Retrofits Most of Existing Occupants in More
    Efficient Facility
  • Classrooms and Offices
  • Labs Including Computer, Art, Foreign Language,
    English, and Science Labs
  • Absorbs Some Portable Occupants
  • Student Services Centers
  • LAC Planning Underway Construction to Start at
    End of South Quad Complex
  • PCC Awaiting State Funding Will Start
    Construction in 2009/2010
  • Centralizes Student Support Services (Admissions,
    Financial Aid, Cashier, Counseling, Job
    Placement, etc.)
  • New Building M
  • Gym (Q R) Projects
  • Building E F

16
QUESTIONS ANSWERS
Prepared By
Bond Management Team
March 28, 2007
BUILDING ? TOMORROW ? TODAY
Write a Comment
User Comments (0)
About PowerShow.com