Title: Bond Construction Update Citizen
1Bond Construction UpdateCitizens Oversight
Committee
- Long Beach Community College District July 21,
2008
BUILDING ? TOMORROW ? TODAY
2Agenda
- Completed Construction Projects
- Current Upcoming Construction Projects
- LAC South Quad Complex
- LAC Central Plant
- LAC Learning Resources Center
- LAC Building A, Student Services
- LAC Math Technology Building
- PCC Central Plant
- PCC Learning Resources Center
- PCC Industrial Tech Phase 1
- PCC MDAB (Multi-Disciplinary Academic Building)
- LAC/PCC Building Needs Assessment Project
- Toilet Improvement Projects
- Quick-Start Projects
- ADA Projects
- Lighting Projects
- Classroom Improvement Projects
- Infrastructure Projects
- Facilities Improvements
3Current and UpcomingConstruction Projects
LAC Central Plant
- Central Plant equipment, Public Safety, Field
house for Athletics - Installed (2) 600 ton Chillers and (1) 300 ton
chiller with room for expansion - Installed 4 cooling towers with additional
expansion space
4Current and UpcomingConstruction Projects
LAC Central Plant
- Plant ready for operation and awaiting completion
of SQC - Construction 96 Complete
- Completion Anticipated Summer 2008
5Current and UpcomingConstruction Projects
LAC/Learning Resources Center
- Construction 70 Complete
- Adds 10,000 ASF to existing building
- Substantial Completion anticipated December 2008
6Current and UpcomingConstruction Projects
South Quad Complex
- Construction Approx. 62 Complete
- Space includes
- Approx. 68,000 ASF
- 32 modern classrooms and labs
- 38 faculty offices
- Executive office suites
- Multipurpose room
- State of the art Board Room
- Substantial Completion Anticipated December 2008
7Current and UpcomingConstruction Projects
LAC Building A Student Services Retrofit
- Martinez Architects received Board Approval as
the Architect of Record - Programming work began on April 10, 2008
- Completed Schematic Design (June 2008)
- Currently in Design Development phase
- Adds 4000 ASF to existing building
- Will house AR, Counseling, Health Services,
Cashier, Transfer Ctr., etc.
8Current and UpcomingConstruction Projects
LAC Math Technology Building
- Marlene Imirzian Associates Architects received
Board Approval as the Architect of Record - Will house Math and Culinary Arts instructional
program as well as Reprographics
9Current and UpcomingConstruction Projects
LAC Math Technology Building
- Programming work began in May 2008
- Completed Schematic Design (June 2008)
- Currently in Design Development phase
- FPP was approved by Board of Trustees and sent to
state
10Current and UpcomingConstruction Projects
LAC Math Technology Building
- Currently completing Design Development Phase
11Current and UpcomingConstruction Projects
PCC Central Plant
- Houses Central Plant equipment and Maintenance
and Operations facility - Installed (3) 300 ton Chillers
- Installed 3 cooling towers
- Will support LRC
- Construction Approximately 67 Complete
- Completion Anticipated late Summer 2008
12Current and UpcomingConstruction Projects
PCC Learning Resources Center
- Construction 97 Complete
- Modern Facility with Computer Lab and Multimedia
- Stand alone Data Center. Provides District IT
redundancy - Bridge to Bldg. EE
- Design elements move towards energy efficiencies
- Substantial Completion July 2008
13Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1
- Replaces Existing Antiquated Structures
- Construction is 25 Complete
- Modern Facility Houses Machine Tool and Welding
Departments - New Northern Face of the Campus
- Completion Anticipated Spring 2009
14Current and UpcomingConstruction Projects
PCC Multi-Disciplinary Academic Building (MDAB)
- Programming is completed and submitted to the
State for Approval - Completed Schematic Design and Design Development
phase (June 2008) - Currently working on Construction Documents and
Furniture Layouts - Anticipated start of construction Summer 2009
- Completed in Two phases
15PCC - LRC and MDAB (Fly-By)
p a c i f i c c o a s t
16Current and UpcomingConstruction Projects
LAC/PCC Building Needs Assessment Project
- Restroom Improvement Projects
- Quick-Start Projects
- ADA Projects
17Current and UpcomingConstruction Projects
LAC/PCC Building Needs Assessment Project
- Lighting Projects
- Classroom Improvement Projects
- Infrastructure Projects
18- Recently Completed Facilities Improvements
- Long Beach Community College District
19Facilities ImprovementsLBCC
Building D Planetarium Improvements
- With the help of LBCC Foundation, funds were
available to do the following - carpet replacement
- carpet added to the walls to ensure light-control
for observational needs. - AC unit independent from the building HVAC system
was added to serve the server room, for proper
load ventilation. - New observation seats were installed.
- entire room painted
- new lighting installed.
- Â Completed 06/2008
20Facilities ImprovementsLBCC
Building J Boiler Replacement
- Replace existing boilers, pumps, expansion tanks
and common flue with new equipment. - A newly upgraded design reflecting a mechanical
engineered system was installed improving the
efficiency of the boilers. This system is the
main heating source serving the Auditorium. - Completed 06/2008
21Facilities ImprovementsLBCC
Building B, C, and D Roof Replacement
- Replacement of roofs with a 30-year Garland roof
materials - Removal of radio tower on Bldg B
- Expected Completion 07/2008
22Facilities ImprovementsLBCC
ERD Tenant Improvements and Relocation
- Economic Resource Development
- Complete build out of two-hard walled offices, a
kitchenette, and a server room - Relocation of a 4,000sq. ft. office space into
the newly re-designed 3,000sq ft. office space - New modular cubicle work stations were adapted
and installed - Completed 05/2008
23Facilities ImprovementsLBCC
Important Ongoing Initiatives
- Building Needs Assessment Project
- Parking Structure/Traffic Study
- Master Landscape Project
- District Wide Energy Efficiency Improvements
- Electronic Signage
- Wayfaring and Building Signage
- Facilities Website
- Facilities Work Order System
- Buildings M N Replacement at LAC
- Building G at PCC
- Modernization of Building P at LAC (IPP)
- Replacement of Building M (Construction Trades)
at PCC (IPP)
24QUESTIONS ANSWERS
BUILDING ? TOMORROW ? TODAY