Bond Construction Update Citizen - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Bond Construction Update Citizen

Description:

Current and UpcomingConstruction Projects. Central Plant equipment, Public Safety, & Field house for Athletics. Installed (2) 600 ton Chillers and (1) 300 ton chiller ... – PowerPoint PPT presentation

Number of Views:175
Avg rating:3.0/5.0
Slides: 25
Provided by: BillA288
Category:

less

Transcript and Presenter's Notes

Title: Bond Construction Update Citizen


1
Bond Construction UpdateCitizens Oversight
Committee
  • Long Beach Community College District July 21,
    2008

BUILDING ? TOMORROW ? TODAY
2
Agenda
  • Completed Construction Projects
  • Current Upcoming Construction Projects
  • LAC South Quad Complex
  • LAC Central Plant
  • LAC Learning Resources Center
  • LAC Building A, Student Services
  • LAC Math Technology Building
  • PCC Central Plant
  • PCC Learning Resources Center
  • PCC Industrial Tech Phase 1
  • PCC MDAB (Multi-Disciplinary Academic Building)
  • LAC/PCC Building Needs Assessment Project
  • Toilet Improvement Projects
  • Quick-Start Projects
  • ADA Projects
  • Lighting Projects
  • Classroom Improvement Projects
  • Infrastructure Projects
  • Facilities Improvements

3
Current and UpcomingConstruction Projects
LAC Central Plant
  • Central Plant equipment, Public Safety, Field
    house for Athletics
  • Installed (2) 600 ton Chillers and (1) 300 ton
    chiller with room for expansion
  • Installed 4 cooling towers with additional
    expansion space

4
Current and UpcomingConstruction Projects
LAC Central Plant
  • Plant ready for operation and awaiting completion
    of SQC
  • Construction 96 Complete
  • Completion Anticipated Summer 2008

5
Current and UpcomingConstruction Projects
LAC/Learning Resources Center
  • Construction 70 Complete
  • Adds 10,000 ASF to existing building
  • Substantial Completion anticipated December 2008

6
Current and UpcomingConstruction Projects
South Quad Complex
  • Construction Approx. 62 Complete
  • Space includes
  • Approx. 68,000 ASF
  • 32 modern classrooms and labs
  • 38 faculty offices
  • Executive office suites
  • Multipurpose room
  • State of the art Board Room
  • Substantial Completion Anticipated December 2008

7
Current and UpcomingConstruction Projects
LAC Building A Student Services Retrofit
  • Martinez Architects received Board Approval as
    the Architect of Record
  • Programming work began on April 10, 2008
  • Completed Schematic Design (June 2008)
  • Currently in Design Development phase
  • Adds 4000 ASF to existing building
  • Will house AR, Counseling, Health Services,
    Cashier, Transfer Ctr., etc.

8
Current and UpcomingConstruction Projects
LAC Math Technology Building
  • Marlene Imirzian Associates Architects received
    Board Approval as the Architect of Record
  • Will house Math and Culinary Arts instructional
    program as well as Reprographics

9
Current and UpcomingConstruction Projects
LAC Math Technology Building
  • Programming work began in May 2008
  • Completed Schematic Design (June 2008)
  • Currently in Design Development phase
  • FPP was approved by Board of Trustees and sent to
    state

10
Current and UpcomingConstruction Projects
LAC Math Technology Building
  • Currently completing Design Development Phase

11
Current and UpcomingConstruction Projects
PCC Central Plant
  • Houses Central Plant equipment and Maintenance
    and Operations facility
  • Installed (3) 300 ton Chillers
  • Installed 3 cooling towers
  • Will support LRC
  • Construction Approximately 67 Complete
  • Completion Anticipated late Summer 2008

12
Current and UpcomingConstruction Projects
PCC Learning Resources Center
  • Construction 97 Complete
  • Modern Facility with Computer Lab and Multimedia
  • Stand alone Data Center. Provides District IT
    redundancy
  • Bridge to Bldg. EE
  • Design elements move towards energy efficiencies
  • Substantial Completion July 2008

13
Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1
  • Replaces Existing Antiquated Structures
  • Construction is 25 Complete
  • Modern Facility Houses Machine Tool and Welding
    Departments
  • New Northern Face of the Campus
  • Completion Anticipated Spring 2009

14
Current and UpcomingConstruction Projects
PCC Multi-Disciplinary Academic Building (MDAB)
  • Programming is completed and submitted to the
    State for Approval
  • Completed Schematic Design and Design Development
    phase (June 2008)
  • Currently working on Construction Documents and
    Furniture Layouts
  • Anticipated start of construction Summer 2009
  • Completed in Two phases

15
PCC - LRC and MDAB (Fly-By)
p a c i f i c c o a s t
16
Current and UpcomingConstruction Projects
LAC/PCC Building Needs Assessment Project
  • Restroom Improvement Projects
  • Quick-Start Projects
  • ADA Projects

17
Current and UpcomingConstruction Projects
LAC/PCC Building Needs Assessment Project
  • Lighting Projects
  • Classroom Improvement Projects
  • Infrastructure Projects

18
  • Recently Completed Facilities Improvements
  • Long Beach Community College District

19
Facilities ImprovementsLBCC
Building D Planetarium Improvements
  • With the help of LBCC Foundation, funds were
    available to do the following
  • carpet replacement
  • carpet added to the walls to ensure light-control
    for observational needs.
  • AC unit independent from the building HVAC system
    was added to serve the server room, for proper
    load ventilation.
  • New observation seats were installed.
  • entire room painted
  • new lighting installed.
  •  Completed 06/2008

20
Facilities ImprovementsLBCC
Building J Boiler Replacement
  • Replace existing boilers, pumps, expansion tanks
    and common flue with new equipment.
  • A newly upgraded design reflecting a mechanical
    engineered system was installed improving the
    efficiency of the boilers. This system is the
    main heating source serving the Auditorium.
  • Completed 06/2008

21
Facilities ImprovementsLBCC
Building B, C, and D Roof Replacement
  • Replacement of roofs with a 30-year Garland roof
    materials
  • Removal of radio tower on Bldg B
  • Expected Completion 07/2008

22
Facilities ImprovementsLBCC
ERD Tenant Improvements and Relocation
  • Economic Resource Development
  • Complete build out of two-hard walled offices, a
    kitchenette, and a server room
  • Relocation of a 4,000sq. ft. office space into
    the newly re-designed 3,000sq ft. office space
  • New modular cubicle work stations were adapted
    and installed
  • Completed 05/2008

23
Facilities ImprovementsLBCC
Important Ongoing Initiatives
  • Building Needs Assessment Project
  • Parking Structure/Traffic Study
  • Master Landscape Project
  • District Wide Energy Efficiency Improvements
  • Electronic Signage
  • Wayfaring and Building Signage
  • Facilities Website
  • Facilities Work Order System
  • Buildings M N Replacement at LAC
  • Building G at PCC
  • Modernization of Building P at LAC (IPP)
  • Replacement of Building M (Construction Trades)
    at PCC (IPP)

24
QUESTIONS ANSWERS
BUILDING ? TOMORROW ? TODAY