Title: Bond Construction Update Citizens Oversight Committee
1Bond Construction UpdateCitizens Oversight
Committee
Cordoba Corporation
- Long Beach Community College District
- April 21, 2008
BUILDING ? TOMORROW ? TODAY
2Agenda
- Completed Construction Projects
- Current Upcoming Construction Projects
- South Quad Complex Structure
- LAC Central Plant Structure
- LAC Learning Resources Center Structure
- LAC Building A, Student Services Retrofit
- PCC Central Plant
- PCC Learning Resources Center
- PCC Industrial Tech Phase 1
- PCC MDAB (Multi-Disciplinary Administration
Building) - Q A
3Construction Progress
4Completed Construction Projects
Various Projects Completed in 2006 2007
- PCC Industrial Technology Center Phase 2 7/07
- PCC Central Plant Utilities, LAC Central Plant
SQC Utilities 6/07 - LAC/LRC Interim 5/07
- East Campus Demo 12/06
- LAC Mens Gym Façade Replacement (FEMA
Insurance Funded) 8/06 - LAC/LRC Utilities 6/06
- PCC CDC 4/06
- Mens Gym Boiler Replacement 4/06
- LAC Athletic Field 3/06
- District Facilities Warehouse Complex 1/06
5LAC Facility Site Plan
l i b e r a l a r t s
6Current and UpcomingConstruction Projects
LAC Central Plant Structure
- Part of Infrastructure Master Plan Improvements
- Awarded to Siemens on DBOM Contract
- Construction 82 Complete
- Completion Anticipated Summer 2008
7Current and UpcomingConstruction Projects
LAC/Learning Resources Center Structure
- Construction 55 Complete
- Combined into Single Construction Phase
- Completion Anticipated December 2008
8Current and UpcomingConstruction Projects
South Quad Complex Structure (Bid Pkg. 3)
- Construction Approx. 52 Complete
- Additional Modern Classrooms, Multi-purpose Rm.,
Offices, etc. - Shifts Campus Center South of Carson off Lew
Davis - Completion Anticipated December 2008
9Current and UpcomingConstruction Projects
LAC Building A Student Services Retrofit
- Martinez Architects received Board Approval as
the Architect of Record - Contract was negotiated/signed and Notice to
Proceed was issued - Programming work began on April 10, 2008
10PCC Facility Site Plan
p a c i f i c c o a s t
11Current and UpcomingConstruction Projects
PCC Central Plant
- Part of Infrastructure Master Plan Improvements
- Early Utility Package Construction Complete
- DBOM Contract Awarded to Siemens Finalizing
Value Engineering Negotiations - Construction Approximately 36 Complete
- Completion Anticipated Summer 2008
12Current and UpcomingConstruction Projects
PCC Learning Resources Center
- Construction 78 Complete
- Modern Facility with Computer Lab and Multimedia
- New Facility
- Bridge to Bldg. EE
- Completion Anticipated July/August 2008
13Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1
- Replaces Existing Antiquated Structures
- Construction is 12 Complete
- Modern Facility Houses Machine Tool and Welding
Departments - New Northern Face of the Campus
- Completion Anticipated Spring 2009
14Current and UpcomingConstruction Projects
PCC MDAB (Multi-Disciplinary Academic Building)
- Programming is completed and submitted to the
State for Approval - Schematic Design was completed in February 2008
15QUESTIONS ANSWERS
Cordoba Corporation
- Prepared by
- Bond Management Team
- April 21, 2008
BUILDING ? TOMORROW ? TODAY