Bond Construction Update Citizens Oversight Committee - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Bond Construction Update Citizens Oversight Committee

Description:

Completed Construction Projects. PCC Industrial Technology Center Phase 2 7/07 ... Programming is completed and submitted to the State for Approval ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 16
Provided by: BillA91
Category:

less

Transcript and Presenter's Notes

Title: Bond Construction Update Citizens Oversight Committee


1
Bond Construction UpdateCitizens Oversight
Committee
Cordoba Corporation
  • Long Beach Community College District
  • April 21, 2008

BUILDING ? TOMORROW ? TODAY
2
Agenda
  • Completed Construction Projects
  • Current Upcoming Construction Projects
  • South Quad Complex Structure
  • LAC Central Plant Structure
  • LAC Learning Resources Center Structure
  • LAC Building A, Student Services Retrofit
  • PCC Central Plant
  • PCC Learning Resources Center
  • PCC Industrial Tech Phase 1
  • PCC MDAB (Multi-Disciplinary Administration
    Building)
  • Q A

3
Construction Progress
4
Completed Construction Projects
Various Projects Completed in 2006 2007
  • PCC Industrial Technology Center Phase 2 7/07
  • PCC Central Plant Utilities, LAC Central Plant
    SQC Utilities 6/07
  • LAC/LRC Interim 5/07
  • East Campus Demo 12/06
  • LAC Mens Gym Façade Replacement (FEMA
    Insurance Funded) 8/06
  • LAC/LRC Utilities 6/06
  • PCC CDC 4/06
  • Mens Gym Boiler Replacement 4/06
  • LAC Athletic Field 3/06
  • District Facilities Warehouse Complex 1/06

5
LAC Facility Site Plan
l i b e r a l a r t s
6
Current and UpcomingConstruction Projects
LAC Central Plant Structure
  • Part of Infrastructure Master Plan Improvements
  • Awarded to Siemens on DBOM Contract
  • Construction 82 Complete
  • Completion Anticipated Summer 2008

7
Current and UpcomingConstruction Projects
LAC/Learning Resources Center Structure
  • Construction 55 Complete
  • Combined into Single Construction Phase
  • Completion Anticipated December 2008

8
Current and UpcomingConstruction Projects
South Quad Complex Structure (Bid Pkg. 3)
  • Construction Approx. 52 Complete
  • Additional Modern Classrooms, Multi-purpose Rm.,
    Offices, etc.
  • Shifts Campus Center South of Carson off Lew
    Davis
  • Completion Anticipated December 2008

9
Current and UpcomingConstruction Projects
LAC Building A Student Services Retrofit
  • Martinez Architects received Board Approval as
    the Architect of Record
  • Contract was negotiated/signed and Notice to
    Proceed was issued
  • Programming work began on April 10, 2008

10
PCC Facility Site Plan
p a c i f i c c o a s t
11
Current and UpcomingConstruction Projects
PCC Central Plant
  • Part of Infrastructure Master Plan Improvements
  • Early Utility Package Construction Complete
  • DBOM Contract Awarded to Siemens Finalizing
    Value Engineering Negotiations
  • Construction Approximately 36 Complete
  • Completion Anticipated Summer 2008

12
Current and UpcomingConstruction Projects
PCC Learning Resources Center
  • Construction 78 Complete
  • Modern Facility with Computer Lab and Multimedia
  • New Facility
  • Bridge to Bldg. EE
  • Completion Anticipated July/August 2008

13
Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1
  • Replaces Existing Antiquated Structures
  • Construction is 12 Complete
  • Modern Facility Houses Machine Tool and Welding
    Departments
  • New Northern Face of the Campus
  • Completion Anticipated Spring 2009

14
Current and UpcomingConstruction Projects
PCC MDAB (Multi-Disciplinary Academic Building)
  • Programming is completed and submitted to the
    State for Approval
  • Schematic Design was completed in February 2008

15
QUESTIONS ANSWERS
Cordoba Corporation
  • Prepared by
  • Bond Management Team
  • April 21, 2008

BUILDING ? TOMORROW ? TODAY
Write a Comment
User Comments (0)
About PowerShow.com