Bond Construction Update Facilities Advisory Committee - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Bond Construction Update Facilities Advisory Committee

Description:

Bond Construction Update. Facilities Advisory Committee. Long ... Marlene Imirzian & Associates Architects received Board Approval as the Architect of Record ... – PowerPoint PPT presentation

Number of Views:46
Avg rating:3.0/5.0
Slides: 33
Provided by: BillA91
Category:

less

Transcript and Presenter's Notes

Title: Bond Construction Update Facilities Advisory Committee


1
Bond Construction UpdateFacilities Advisory
Committee
  • Long Beach Community College District
  • September 2, 2008

BUILDING ? TOMORROW ? TODAY
2
Agenda
  • Completed Construction Projects
  • Current Upcoming Construction Projects
  • LAC South Quad Complex
  • LAC Central Plant
  • LAC Learning Resources Center
  • LAC Building A, Student Services
  • LAC Math Technology Building
  • PCC Central Plant
  • PCC Learning Resources Center
  • PCC Industrial Tech Phase 1
  • PCC MDAB (Multi-Disciplinary Academic Building)
  • LAC/PCC Building Needs Assessment Project
  • Toilet Improvement Projects
  • Quick-Start Projects
  • ADA Projects
  • Lighting Projects
  • Classroom Improvement Projects
  • Infrastructure Projects
  • Facilities Improvements

3
Current and UpcomingConstruction Projects
LAC Central Plant
  • Central Plant equipment, Public Safety, Field
    house for Athletics
  • Installed (2) 600 ton Chillers and (1) 300 ton
    chiller with room for expansion
  • Installed 4 cooling towers with additional
    expansion space

4
Current and UpcomingConstruction Projects
LAC Central Plant
  • Plant ready for operation and awaiting completion
    of SQC
  • Construction 99 Complete
  • Awaiting completion of punch list
  • Completion Anticipated Summer 2008

5
Current and UpcomingConstruction Projects
LAC/Learning Resources Center
  • Construction 75 Complete
  • Adds 10,000 ASF to existing building
  • Substantial Completion anticipated December 2008

6
Current and UpcomingConstruction Projects
South Quad Complex
  • Construction Approx. 70 Complete
  • Space includes
  • Approx. 68,000 ASF
  • 32 modern classrooms and labs
  • 38 faculty offices
  • Executive office suites
  • Multipurpose room
  • State of the art Board Room
  • Substantial Completion Anticipated December 2008

7
Current and UpcomingConstruction Projects
LAC Building A Student Services Retrofit
  • Martinez Architects received Board Approval as
    the Architect of Record
  • Programming work began on April 10, 2008
  • Schematic Design scheduled completion June 30,
    2008
  • Adds 4000 ASF to existing building
  • Will house AR, Counseling, Health Services,
    Cashier, Transfer Ctr., etc.

8
Current and UpcomingConstruction Projects
LAC Math Technology Building
  • Marlene Imirzian Associates Architects received
    Board Approval as the Architect of Record
  • Will house Math and Culinary Arts instructional
    program as well as Reprographics

9
Current and UpcomingConstruction Projects
LAC Math Technology Building
  • Programming work began in May 2008
  • Schematic Design scheduled completion June 30,
    2008

10
Current and UpcomingConstruction Projects
LAC Math Technology Building
  • Currently completing Design Development Phase

11
Current and UpcomingConstruction Projects
PCC Central Plant
  • Houses Central Plant equipment and Maintenance
    and Operations facility
  • Installed (3) 300 ton Chillers
  • Installed 3 cooling towers
  • Will support LRC
  • Construction Approximately 57 Complete
  • Completion Anticipated late Summer 2008

12
Current and UpcomingConstruction Projects
PCC Learning Resources Center
  • Construction 94 Complete
  • Modern Facility with Computer Lab and Multimedia
  • Stand alone Data Center. Provides District IT
    redundancy
  • Bridge to Bldg. EE
  • Design elements move towards energy efficiencies
  • Opened August 2008

13
Current and UpcomingConstruction Projects
PCC Industrial Technology Center Phase 1
  • Replaces Existing Antiquated Structures
  • Construction is 20 Complete
  • Modern Facility Houses Machine Tool and Welding
    Departments
  • New Northern Face of the Campus
  • Completion Anticipated Spring 2009

14
Current and UpcomingConstruction Projects
PCC Multi-Disciplinary Academic Building (MDAB)
  • Programming is completed and submitted to the
    State for Approval
  • Schematic Design and Design Development to be
    completed by June 2008
  • Anticipated start of construction Summer 2009
  • Completed in Two phases

15
Current and UpcomingConstruction Projects
LAC/PCC Building Needs Assessment Project
  • Restroom Improvement Projects
  • Quick-Start Projects
  • ADA Projects

16
Current and UpcomingConstruction Projects
LAC/PCC Building Needs Assessment Project
  • Lighting Projects
  • Classroom Improvement Projects
  • Infrastructure Projects

17
  • Recently Completed Facilities Improvements
  • Long Beach Community College District

18
Facilities ImprovementsLBCC
Building P Exterior Renovation
  • Complete exterior renovation.
  • Entire roof replacement with a Spanish tile
    design, covering approximately 21,000 square
    feet.
  • Architectural features added to the new doors.
  • Windows replaced.
  • French doors were installed entering into main
    meeting areas.
  • Exterior painted
  • Added new copper gutters.
  • Completed 02/2006

19
Facilities ImprovementsLBCC
Building P Teachers Lounge Renovations
  • Complete renovations were made to the teachers
    lounge.
  • Existing floor was removed and a new wood floor
    installed.
  • New track lighting and French doors were also
    installed.
  • Outside the French doors are exterior drains so
    no overflow of water can penetrate into this
    room.
  • Completed 01/2008

20
Facilities ImprovementsLBCC
Building E Upgrades
  • Replaced broken tile with new non-skid tile at
    the entrance of the cafeteria to match existing
  • Completed 01/2008
  • Structural evaluation and Repair cracks in
    ceiling, walls, and flooring due to earthquake
  • Completed 07/2008

21
Facilities ImprovementsLBCC
Building D Planetarium Improvements
  • With the help of LBCC Foundation, funds were
    available to do the following
  • carpet replacement
  • carpet added to the walls to ensure light-control
    for observational needs.
  • AC unit independent from the building HVAC system
    was added to serve the server room, for proper
    load ventilation.
  • New observation seats were installed.
  • entire room painted
  • new lighting installed.
  •  Completed 06/2008

22
Facilities ImprovementsLBCC
Building J Boiler Replacement
  • Replace existing boilers, pumps, expansion tanks
    and common flue with new equipment.
  • A newly upgraded design reflecting a mechanical
    engineered system was installed improving the
    efficiency of the boilers. This system is the
    main heating source serving the Auditorium.
  • Completed 06/2008

23
Facilities ImprovementsLBCC
Building F Upgrades
  • New stadium seating installed
  • New carpet installed.
  • New vertical blinds installed throughout
    building.
  • Completed 12/2007
  • Upcoming advancements include exterior door
    replacement

24
Facilities ImprovementsLBCC
Building Q Small Gymnasium Improvements
  • Refinished wood flooring. A five coat finish
    system was applied to the floor for durability
    and long term wear. Additional decal of LBCC
    game lines were applied on flooring
  • Interior walls were repainted and decals were
    re-applied with paint
  • New retractable bleacher system was installed
  • Completed 02/2008
  • Upcoming advancement includes room Q113 dance
    floor replacement

25
Facilities ImprovementsLBCC
Building Q Health Center Office Remodel
  • Two-new office spaces added
  • Added an HVAC system
  • Repainted all interior walls
  • Installed new carpet
  • Completed 01/2008

26
Facilities ImprovementsLBCC
Building B, C, and D Roof Replacement
  • Replacement of roofs with a 30-year Garland roof
    materials
  • Removal of radio tower on Bldg B
  • Completed 07/2008

27
Facilities ImprovementsLBCC
ERD Tenant Improvements and Relocation
  • Economic Resource Development
  • Complete build out of two-hard walled offices, a
    kitchenette, and a server room
  • Relocation of a 4,000sq. ft. office space into
    the newly re-designed 3,000sq ft. office space
  • New modular cubicle work stations were adapted
    and installed
  • Completed 05/2008

28
Facilities ImprovementsLBCC
Building P Boiler Replacement
  • Replaced boiler for a more efficient system
  • Completed 07/2007

29
Facilities ImprovementsLBCC
Building Q and R Exterior Renovations
  • Repainting of all exterior walls, windows, and
    doors
  • Re-paint trim and detail work
  • Replaced all broken windows
  • Installed front landscape
  • Completed 8/2008
  • Upcoming advancements
  • include complete roof
  • replacement, sky light
  • upgrades, and exterior clock
  • repair

30
Facilities ImprovementsLBCC
Recently Completed Advancements
  • Veterans Stadium scoreboard and PA system
    upgrade
  • Building K upgrades Exterior door paint, room
    111 floor refinishing
  • PCC upgrades
  • Building AA Built wall for information desk,
    installed carpet, and power upgrades
  • Building BB Carpet and window blind
    installation
  • Building CC Installed fans in gym
  • Building DD Carpet and window blind
    installation
  • Building EE Window blind installation
  • Building MM Exterior paint, replaced doors and
    awnings, re-glazed windows, and replaced fascia
    boards

31
Facilities ImprovementsLBCC
Important Ongoing Initiatives
  • Building Needs Assessment Project
  • Design/Build Parking Structure
  • Master Landscape Project
  • District Wide Energy Efficiency Improvements
  • Phase IIA
  • Lighting Upgrades, HVAC Upgrades, Control
    upgrades, Pool Cover, Roof replacement, etc
  • Phase IIB
  • Upcoming advancements include connecting current
    buildings to Central Plant infrastructure
  • Design Electronic Marquee Signage
  • Wayfaring and Building Signage
  • Facilities Website
  • Facilities Work Order System
  • Building P Theatre Room renovations
  • Building P Faculty Restroom ADA upgrades

32
QUESTIONS ANSWERS
BUILDING ? TOMORROW ? TODAY
Write a Comment
User Comments (0)
About PowerShow.com