Status of HPD Testing - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Status of HPD Testing

Description:

two updates of the analysis SW and the summary sheets since 11/05 ... New: 'Tower of Pisa' Issue. H541004. RICH meeting, CERN, 18.01.2006. Stephan Eisenhardt ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 24
Provided by: stephanei
Category:
Tags: hpd | of | pisa | status | testing | tower

less

Transcript and Presenter's Notes

Title: Status of HPD Testing


1
Status of HPD Testing
  • Status of Test Stations
  • Test Results
  • Summaries on DEP visit 15.12.2005
  • Conclusions

Stephan Eisenhardt University of Edinburgh
RICH meeting, CERN, 18.01.2006
2
Status of Test Stations
  • HPD qualification testing cross-checks
    re-tests
  • done on 3 test stations Edi1, Edi2, Gla1
  • in operation since Nov. 2005
  • station Gla2 progress set-back
  • hardware commissioned
  • software installed
  • HPD tested up to few kV (cautious for possible
    light leaks)
  • cross-calibration started (comparison with Gla1)
  • ? this week disk crash of system disk
  • still running with DAQ SW released in 11/05
  • upgrade planned for 02/06
  • two updates of the analysis SW and the summary
    sheets since 11/05

3
Visual Inspection I
  • anodized holes
  • few HPD without anodization removed
  • taped holes
  • dowel holes
  • scratches on windows
  • 5x 1-2cm scratches found
  • (H516020, H518003, H524004 (2x), H539007,
    H540005)
  • 3x surface damage found (H518001, H518006,
    H518007)

0.5cm
2cm
H516020
H518007
4
Visual Inspection II
  • 2cm gap in Silicon
  • H530001, H527007, H541013
  • hole at cathode cable
  • H539003, H542001, H540005, H540006, H540009,
    H546003
  • gap in indium seal
  • H530010
  • side hole
  • H518003

5
DEP Visit Summary I
  • visit at DEP on 15.12.2005, attending FM, AP,
    TG, NH
  • visual inspection and mechanical precision
  • scratches and damages on windows
  • ? DEP to check procedures to avoid
  • window chamfers
  • ? all in Scotland polished, DEP polishes frosted
    edged
  • anodized holes
  • ? DEP checks procedures to remove anodization,
    LHCb fixes existing anodization
  • silicone holes from potting
  • ? DEP gives reference to material, LHCb fills
    holes
  • hole in indium seal
  • ? DEP watches/improves indium homogeneity

6
New Tower of Pisa Issue
  • found end of last week (in last shipment of 9
    HPD)
  • 2 HPD which failed the mechanical test in the jig
  • both lean by approx. 0.4mm towards 3 oclock
  • (i.e. in same direction)
  • ? not mountable in RICH (jigs cannot be closed)
  • DEP is informed we request the HPDs to be
    re-potted

H541004
H542020
7
Quantum Efficiency
  • for all results minimum and typical as defined
  • in technical specifications of contract

maximum dark count rate 5 kHz/cm2
ltQEgt 26.2
minimum QE 20
typical QE 23.3
PDTF
PDTF dark counts vs DEP red sensitivity
DEP - QE at 270 nm blue sensitivity
minimum QE 20
QE blue vs red sensitivity
DEP - QE at 800 nm red sensitivity
8
DEP Visit Summary II
  • quantum efficiency
  • QE in the blue (370nm) is excellent
  • there are a few HPD with a large red sensitivity
    (2-4_at_800nm)
  • there is a negative correlation between red and
    blue sensitivity ( -2 blue for 3 red) and a
    positive between the red sensitivity and the
    dark-count
  • ? DEP to try to keep the red sensitivity low
    without compromising the blue sensitivity

9
Anode Leakage Current _at_ 80V
PDTF Bias I nA
Bias current PDTF vs DEP
5 HPDs tested OK 16,15,14,13,12mA 1 HPD
rejected 25mA
Typical 1 uA
PDTF Bias I nA
T difference PDTF chip on DEP chip off
DEP Bias I nA
DEP Bias I nA
PDTF Bias IV scans
normalised
Typical 1 uA
6 HPDs with I 10 mA
low I class
PDTF Bias I ?uA
medium I class
10
High Anode Leakage Current
H530001
H539001
H539012
of bake outs 3
of bake outs 3
of bake outs 1
16.4 uA at (80 216.4) V 47 V
13.7 uA at (80 213.7) V 53 V
25.1 uA at (80 225.1) V 30 V
light level increased by factor 100 !!
provisionally accepted
provisionally accepted
rejected
11
DEP Visit Summary III
  • anode leakage current
  • measurements at Scotland give larger values
    likely due to temperature (chip off at DEP)
  • 6 HPD at Scotland have very high (gt10mA) leakage
    current
  • 5 have lt20mA, get fully depleted and operate
    normally
  • (bake outs 2x three times, 2x two times, 1x one
    times)
  • 1 has 25mA, does not get fully depleted and has
    a very small electron detection efficiency
  • ? rejected (three times baked out)
  • all (3) HPDs which are three times baked out have
    large or very large leakage current
  • DEP stops after two bake outs and puts anode to
    the side
  • whenever possible DEP measures leakage currents
    between bake-out cycles

12
Bump Bonding Degradation
  • only one example H518005
  • 2 bake outs
  • O(200) pixels detached lt 95 limit (400 pixels)

Long LED run 200k triggers
Long LED run, LHCb mode 200k triggers
13
DEP Visit Summary IV
  • bump bonding
  • H518005 shows detached bump bonds, gone while
    bake-out, likely due to non-flat assembly
  • two bake-outs ? LHCb responsibility
  • ? DEP from now on to test HPD with LED light
    source

14
New Dark Count Status
  • Dark Count problem was due to a light leak
  • diameter of Lemo cable smaller that Lemo plug
  • after fix all (12) HPD with Dark Count above
    5kHz/cm2 were re-measured
  • two classes
  • homogeneous
  • ? high red sensitivity
  • central IFB
  • ? micro-discharges?

15
Dark Count Rates
PDTF Dark Counts kHz/cm2
Dark Counts PDTF vs DEP
maximum - 5 kHz/cm2
PDTF
DEP
  • 15 out of 72 HPDs above limit
  • 6 above 10 kHz/cm2
  • two patterns
  • homogeneous
  • centre ion feedback (micro-discharges)

light leak in DEP box
16
Ion Feedback
PDTF Ion feedback strobe scans
PDTF Ion feedback 5M trig
max. 1 _at_200C
max. 1 _at_200C
micro-discharges suspected


DEP Ion feedback
max. 1 _at_200C
note scale (signal x 100) usually very low

17
DEP Visit Summary V
  • dark-count and ion feedback rates
  • 50 of the DEP dark-count rates above 5kHz/cm2
    spec due to light leaking test box
  • ? light tight box delivered by CERN in November,
    now installed and in operation
  • 15 out of 72 HPD show dark-count rates gt5kHz/cm2
    (5x gt10kHz/cm2, max. 17.9kHz/cm2)
  • ion-feedback rate with LED typically below 0.1
    ? good vacuum
  • ion-feedback rate due to dark-count typically 1
    ? points to micro-discharges
  • DEP to strive to deliver HPD within specs
  • DEP to additionally measure dark-count with LED

18
Status of HPD Test Program
  • as of Fri 13.01.2006
  • to be retested 4 high leakage current minor
    technical fault (for last two deliveries)
  • 3 QE study of high leakage current HPD (on
    provisionally accepted HPDs)
  • rejected 1 insufficient depletion (three
    bake-outs) caused insensitive chip
  • 1 indium blob on window caused huge noise
  • 10 point (50HPD tested) reached on 20.12.2005

19
HPD Test - Time Profile
20
Plans for HPDs
  • maximum HPD test rate
  • we can test 30 HPDs/month, i.e. 15
    HPDs/month/site
  • if we need to test at a higher rate
  • planning and additional resources are required
  • time required for HPD testing
  • mandatory tests one day is sufficient
  • 6 hours or less if all goes according to plan
  • re-testing will occupy 2nd test station when
    required
  • QE and Backpulse measurement only at one site
  • HPD delivery to CERN (for system test)
  • this week 38 provisionally accepted fully
    tested
  • remaining at Scotland (for QE backpulse
    measurement retest LC)
  • 10 of HPD 6 provisionally accepted, i.e.
    1/delivery
  • 3 provisionally accepted, but to be retested
  • (high leakage)
  • expect next delivery from DEP early next week
    (26 HPD)

21
DEP Visit Summary VI
  • logistics
  • 27 HPD delivered on 31.10.2005 provisionally
    accepted on 21.12.2005
  • 1 HPD delivered on 31.10.2005 rejected on
    21.12.2005 (depletion problem)
  • 14 HPD delivered on 9.11.2005 provisionally
    accepted on 11.1.2006
  • batch 4 completed with shipment of 9 HPD arrived
    on 16.12.2005
  • expect shipment of 26 HPD in 3rd week of January
  • ? DEP to try to provide electronic versions of
    the data sheets

22
Summary Sheets Data Base
  • summary sheets
  • two updates since 11/05
  • off-line suppression of noisy pixels
  • analysis plot updates
  • re-analysed old data
  • ASCII output file for DB under way (1 week)
  • database
  • waits for ASCII input file
  • then test submissions
  • first query implementation recreate summary
    sheet from DB
  • subsequent implementation of further standard
    queries

23
Conclusions
  • despite of the issues reported
  • default test result is an excellent performance
    of HPD
  • our issues are well addressed by DEP
  • iron out some start-up problems
Write a Comment
User Comments (0)
About PowerShow.com