Title: Status of HPD Testing
1Status of HPD Testing
- Status of Test Stations
- Test Results
- Summaries on DEP visit 15.12.2005
- Conclusions
Stephan Eisenhardt University of Edinburgh
RICH meeting, CERN, 18.01.2006
2Status of Test Stations
- HPD qualification testing cross-checks
re-tests - done on 3 test stations Edi1, Edi2, Gla1
- in operation since Nov. 2005
- station Gla2 progress set-back
- hardware commissioned
- software installed
- HPD tested up to few kV (cautious for possible
light leaks) - cross-calibration started (comparison with Gla1)
- ? this week disk crash of system disk
- still running with DAQ SW released in 11/05
- upgrade planned for 02/06
- two updates of the analysis SW and the summary
sheets since 11/05
3Visual Inspection I
- anodized holes
- few HPD without anodization removed
- taped holes
- dowel holes
- scratches on windows
- 5x 1-2cm scratches found
- (H516020, H518003, H524004 (2x), H539007,
H540005) - 3x surface damage found (H518001, H518006,
H518007)
0.5cm
2cm
H516020
H518007
4Visual Inspection II
- 2cm gap in Silicon
- H530001, H527007, H541013
- hole at cathode cable
- H539003, H542001, H540005, H540006, H540009,
H546003 - gap in indium seal
- H530010
- side hole
- H518003
5DEP Visit Summary I
- visit at DEP on 15.12.2005, attending FM, AP,
TG, NH - visual inspection and mechanical precision
- scratches and damages on windows
- ? DEP to check procedures to avoid
- window chamfers
- ? all in Scotland polished, DEP polishes frosted
edged - anodized holes
- ? DEP checks procedures to remove anodization,
LHCb fixes existing anodization - silicone holes from potting
- ? DEP gives reference to material, LHCb fills
holes - hole in indium seal
- ? DEP watches/improves indium homogeneity
6New Tower of Pisa Issue
- found end of last week (in last shipment of 9
HPD) - 2 HPD which failed the mechanical test in the jig
- both lean by approx. 0.4mm towards 3 oclock
- (i.e. in same direction)
- ? not mountable in RICH (jigs cannot be closed)
- DEP is informed we request the HPDs to be
re-potted
H541004
H542020
7Quantum Efficiency
- for all results minimum and typical as defined
- in technical specifications of contract
maximum dark count rate 5 kHz/cm2
ltQEgt 26.2
minimum QE 20
typical QE 23.3
PDTF
PDTF dark counts vs DEP red sensitivity
DEP - QE at 270 nm blue sensitivity
minimum QE 20
QE blue vs red sensitivity
DEP - QE at 800 nm red sensitivity
8DEP Visit Summary II
- quantum efficiency
- QE in the blue (370nm) is excellent
- there are a few HPD with a large red sensitivity
(2-4_at_800nm) - there is a negative correlation between red and
blue sensitivity ( -2 blue for 3 red) and a
positive between the red sensitivity and the
dark-count - ? DEP to try to keep the red sensitivity low
without compromising the blue sensitivity
9Anode Leakage Current _at_ 80V
PDTF Bias I nA
Bias current PDTF vs DEP
5 HPDs tested OK 16,15,14,13,12mA 1 HPD
rejected 25mA
Typical 1 uA
PDTF Bias I nA
T difference PDTF chip on DEP chip off
DEP Bias I nA
DEP Bias I nA
PDTF Bias IV scans
normalised
Typical 1 uA
6 HPDs with I 10 mA
low I class
PDTF Bias I ?uA
medium I class
10High Anode Leakage Current
H530001
H539001
H539012
of bake outs 3
of bake outs 3
of bake outs 1
16.4 uA at (80 216.4) V 47 V
13.7 uA at (80 213.7) V 53 V
25.1 uA at (80 225.1) V 30 V
light level increased by factor 100 !!
provisionally accepted
provisionally accepted
rejected
11DEP Visit Summary III
- anode leakage current
- measurements at Scotland give larger values
likely due to temperature (chip off at DEP) - 6 HPD at Scotland have very high (gt10mA) leakage
current - 5 have lt20mA, get fully depleted and operate
normally - (bake outs 2x three times, 2x two times, 1x one
times) - 1 has 25mA, does not get fully depleted and has
a very small electron detection efficiency - ? rejected (three times baked out)
- all (3) HPDs which are three times baked out have
large or very large leakage current - DEP stops after two bake outs and puts anode to
the side - whenever possible DEP measures leakage currents
between bake-out cycles
12Bump Bonding Degradation
- only one example H518005
- 2 bake outs
- O(200) pixels detached lt 95 limit (400 pixels)
Long LED run 200k triggers
Long LED run, LHCb mode 200k triggers
13DEP Visit Summary IV
- bump bonding
- H518005 shows detached bump bonds, gone while
bake-out, likely due to non-flat assembly - two bake-outs ? LHCb responsibility
- ? DEP from now on to test HPD with LED light
source
14New Dark Count Status
- Dark Count problem was due to a light leak
- diameter of Lemo cable smaller that Lemo plug
- after fix all (12) HPD with Dark Count above
5kHz/cm2 were re-measured - two classes
- homogeneous
- ? high red sensitivity
- central IFB
- ? micro-discharges?
15Dark Count Rates
PDTF Dark Counts kHz/cm2
Dark Counts PDTF vs DEP
maximum - 5 kHz/cm2
PDTF
DEP
- 15 out of 72 HPDs above limit
- 6 above 10 kHz/cm2
- two patterns
- homogeneous
- centre ion feedback (micro-discharges)
light leak in DEP box
16Ion Feedback
PDTF Ion feedback strobe scans
PDTF Ion feedback 5M trig
max. 1 _at_200C
max. 1 _at_200C
micro-discharges suspected
DEP Ion feedback
max. 1 _at_200C
note scale (signal x 100) usually very low
17DEP Visit Summary V
- dark-count and ion feedback rates
- 50 of the DEP dark-count rates above 5kHz/cm2
spec due to light leaking test box - ? light tight box delivered by CERN in November,
now installed and in operation - 15 out of 72 HPD show dark-count rates gt5kHz/cm2
(5x gt10kHz/cm2, max. 17.9kHz/cm2) - ion-feedback rate with LED typically below 0.1
? good vacuum - ion-feedback rate due to dark-count typically 1
? points to micro-discharges - DEP to strive to deliver HPD within specs
- DEP to additionally measure dark-count with LED
18Status of HPD Test Program
- as of Fri 13.01.2006
- to be retested 4 high leakage current minor
technical fault (for last two deliveries) - 3 QE study of high leakage current HPD (on
provisionally accepted HPDs) - rejected 1 insufficient depletion (three
bake-outs) caused insensitive chip - 1 indium blob on window caused huge noise
- 10 point (50HPD tested) reached on 20.12.2005
19HPD Test - Time Profile
20Plans for HPDs
- maximum HPD test rate
- we can test 30 HPDs/month, i.e. 15
HPDs/month/site - if we need to test at a higher rate
- planning and additional resources are required
- time required for HPD testing
- mandatory tests one day is sufficient
- 6 hours or less if all goes according to plan
- re-testing will occupy 2nd test station when
required - QE and Backpulse measurement only at one site
- HPD delivery to CERN (for system test)
- this week 38 provisionally accepted fully
tested - remaining at Scotland (for QE backpulse
measurement retest LC) - 10 of HPD 6 provisionally accepted, i.e.
1/delivery - 3 provisionally accepted, but to be retested
- (high leakage)
- expect next delivery from DEP early next week
(26 HPD)
21DEP Visit Summary VI
- logistics
- 27 HPD delivered on 31.10.2005 provisionally
accepted on 21.12.2005 - 1 HPD delivered on 31.10.2005 rejected on
21.12.2005 (depletion problem) - 14 HPD delivered on 9.11.2005 provisionally
accepted on 11.1.2006 - batch 4 completed with shipment of 9 HPD arrived
on 16.12.2005 - expect shipment of 26 HPD in 3rd week of January
- ? DEP to try to provide electronic versions of
the data sheets
22Summary Sheets Data Base
- summary sheets
- two updates since 11/05
- off-line suppression of noisy pixels
- analysis plot updates
- re-analysed old data
- ASCII output file for DB under way (1 week)
- database
- waits for ASCII input file
- then test submissions
- first query implementation recreate summary
sheet from DB - subsequent implementation of further standard
queries
23Conclusions
- despite of the issues reported
- default test result is an excellent performance
of HPD - our issues are well addressed by DEP
- iron out some start-up problems