Title: Bucket Eradication
1- Bucket Eradication
- Status Action Plans
- Presentation to Select Committee on Land
Environmental Affairs - Dated the 23rd of February 2007
Presented by MEC Mafereka
2Definition of a Bucket System to be Eradicated
- Elimination of a historic plastic or any other
form of bucket system in formalized areas and
replacing it with a suitable approved alternative.
3Current Status on Eradication of Buckets in the
Free State
- Total buckets 2004 ? 160 000
- Current Backlog Jan 2007 ? 88 791
- Buckets eradicated to date Jan 2007 ? 71 209
- Funding required to eradicate current backlog _at_
R9000/bucket as per Policy 2006 ? R799.1
million - Funding required to eradicate current backlog _at_
an average unit cost in the FS _at_ R12 534/bucket
? R1 113 billion - Funding available currently ? R 679.9 m
- Shortfall ? R 566.1m
4Current Status on Eradication of Buckets in the
Free State
PROVINCE Progress 1st quarter (Apr06-Jun06) Progress 2nd quarter (July06-Sep06) Progress 3rd quarter (Oct06-Dec06) Buckets removed Jan07 Total Removed Apr06-Jan07 Backlog at end Jan 07
FREE STATE
SETSOTO 0 350 150 500 1,000 14,000
NKETOANE 330 300 90 0 720 9,060
DIHLABENG 234 1,170 100 0 1,504 3,213
LETSIMENG 0 120 180 220 520 1,349
MANGAUNG 0 0 0 0 0 9,500
MANTSOPA 0 0 0 549 549 5,069
MATJHABENG 1,156 0 100 2,851 4,107 8,279
MOHOKARE 0 294 0 0 294 1,537
NALEDI 0 293 15 755 1,063 -584
MOQHAKA 2,580 290 60 0 2,930 2,859
METSIMAHOLO 2,067 0 0 0 2,067 156
MAFUBE 52 60 0 0 112 1,256
MASILONYANA 200 100 60 0 360 7,130
NALA 0 0 0 0 0 9,026
TSWELOPELE 0 80 0 0 80 3,547
TIKOLOGO 0 0 0 0 0 3,718
KOPANONG 0 0 0 0 0 3,244
PHUMELELA 0 110 338 1,588 2,036 685
MAL A PHOFUNG 0 0 0 0 0 300
NGWATHE 2,212 2,601 27 0 4,840 5,447
FS TOTAL 8,831 5,768 1,120 6,463 22,182 88,791
5Delivery Hot Spot Areas in the Free State
- The Free State has challenges of Water Resources
in the following Municipal areas - Dihlabeng
- Sterkfontein-Qwaqwa
- Nketoane
- Ngwathe
- Jagersfontien-Fauresmith
- Rouxville-Smithfield
- Tokologo
- As a result, it becomes extremely difficult to
eradicate buckets with waterborne sanitation.
6Delivery Hot Spot Areas in the Free State (Cont
)
- Most municipalities have capacity problems with
their sewer treatment plants, they will require
upgrading and the province has a short fall of
R500 million. - Few existing sewer treatment plants have spare
capacity. - Some municipalities are currently not eradicating
buckets until they have DoRA allocations in the
new financial year (see slide on current status
on eradication)
7Potential Problem Areas in WSAs
- Most municipalities experience shortage of
technical skills, the department of LGH together
with DWAF have made available engineers to assist
with technical supervision at the WSAs. - A water supply master plan has been developed and
it should be implemented as soon as funding is
available - A decision making tool to guide municipalities
for the choice of sanitation of technology,
referred to as the sanitation strategy document,
has been developed municipalities to adhere to
it.
8Potential Problem Areas in WSAs (Cont)
- Enforce implementation role-out plan as
presented, through continuous monitoring - Review unit cost to meet current average in FS
- Obtain additional R 566 million to enable the
eradication of 45 000 units not yet funded - Ensure that detail action plans, focused on
sustainability are being implemented
9Expenditure Performance To Jan 2007
10Budget Constraints
- Current Backlog Jan 2007 ? 88 791
- Buckets eradicated to date Jan 2007 ? 71 209
- Funding required to eradicate current backlog _at_
R9000/bucket as per Policy 2006 ? R799.1
million - Funding required to eradicate current backlog _at_
an average unit cost in the FS _at_ R12 534/bucket
? R1 113 billion - Funding available currently ? R 679.9 m
- Shortfall ? R 566.1m
11Provincial Delivery Constraints
- Shortage of funding to eliminate all buckets by
October 2007 - Ceiling cost per bucket currently of R9000 is not
adequate vs. the current average cost of R12 534 - Poor attendance by municipal key staff and
politicians in most meetings - No proper roll out plans were available at
municipalities during the bucket eradication
workshops - Shortage of water in certain municipalities
- Insufficient capacity on the existing bulk
infrastructure - Some LMs are extending their Programmes to
2008/09
12Implementation Plan Mantsopa
13Implementation Plan Mohakare
14Implementation Plan Naledi
15Implementation Plan Letsemeng
16Implementation Plan Kopanong
17Implementation Plan Mangaung
18Implementation Plan Nala
19Implementation Plan Masilonyana
20Implementation Plan Tokologo
21Implementation Plan Tswelopele
22Implementation Plan Matjhabeng
23Implementation Plan Metsimaholo
24Implementation Plan Ngwathe
25Implementation Plan Mafube
26Implementation Plan Moqhaka
27Implementation Plan Phumelela
28Implementation Plan Maluti
29Implementation Plan Nketoana
30Implementation Plan Setsoto
31Implementation Plan Dihlabeng
32Detail funding per LM
33Establish Capacity Constraints
- Most rural municipalities are not able to attract
the right caliber of skill/expertise they require - No sufficient monitoring of water services
delivery at municipal level - Low expenditure of project implementation
- Lack of capacity in engaging communities in
service delivery issues - Lack of capacity at municipal level to facilitate
revenue collection and credit control - Lack of technical expertise mostly in Water
sewer treatment plants, hence water quality
problems