Title: BUCKET ERADICATION PROGRAMME
1BUCKET ERADICATION PROGRAMME
PROGRES REPORT TO DATEDATE 26 September
2007VENUE Committee Room
PRESENTED BY Mr. Sam Masisi Director
Infrastructure Utilities
2TOTAL FIGURES
TOTAL NUMBER OF TOILETS 11 416
TOTAL NUMBER CONSULTANTS 5
TOTAL NUMBER CONTRACTORS 26 (ALL ESTABLISHED)
TOTAL SCHEDULED QUANTIIES R69, 312, 639.80
Expenditure To Date R386, 732.46 Expen 0.6
TOTAL PROGRESS TODATE
Total of Slabs Completed 1740
Total of Structures Completed 1124
Total of Connections Completed 695
Total of Base Preparations 523
Total of Structures with Wash Trough 192
Total of Toilets 100 Complete 87
TOTAL STAFF COMPLIMENT Woman 132 Man 231 Youth 259 Disabled 4 Total Staff 919
3TYPICAL EXISTING STRUCTURES
4TYPICAL EXISTING STRUCTURES