Martin Cooper, Los Alamos - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Martin Cooper, Los Alamos

Description:

... Redemption, '...crawled through 500 yards of unspeakably vile mire to freedom... Many things in this talk depend on the resolution of the FY'07 budget ... – PowerPoint PPT presentation

Number of Views:600
Avg rating:3.0/5.0
Slides: 19
Provided by: p25ex
Learn more at: https://p25ext.lanl.gov
Category:
Tags: alamos | cooper | los | martin | vile

less

Transcript and Presenter's Notes

Title: Martin Cooper, Los Alamos


1
The Path to CD-2
Martin Cooper, Los Alamos Co-spokesperson and
Contract Project Manager for the EDM Project for
presentation to The EDM Collaboration Pasadena,
CA February 14, 2007
2
Outline
  • CD-2 schedule
  • RD schedule
  • Upgrading the schedule and work packages
  • Monitoring progress
  • Documenting costs
  • Specifications for Integrated Tests
  • Memoranda of Understanding
  • Engineering approach (Jan Boissevain)

3
Perspective
  • To paraphrase the narrator from the Shawshank
    Redemption, crawled through 500 yards of
    unspeakably vile mire to freedom
  • Unfortunately, there is another mile long pipe to
    reach CD-2

4
Caveats
  • Many things in this talk depend on the resolution
    of the FY07 budget
  • There is Jehannes way or the highway

5
New Phase for nEDM
  • The nEDM Project has entered a new phase The
    detailed planning/baseline development phase
  • Involves refining the scope, schedule and cost
    plan to a single baseline (not a range).
  • The baseline becomes the contract with DOE
    (customer) at CD-2.
  • CD-2 approval is dependent on a valid baseline.
  • Schedule and cost status must now be reported to
    DOE at a lower level of detail.

6
Performance Baseline
The Project Performance Baseline is Developed
on A mature design (RD and engineering
effort) A well defined and documented scope
(work packages) A resource loaded detailed
schedule (MS Project schedule) A definitive
cost estimate (basis of estimate) Defined key
performance parameters Source DOE Order 413.3A
7
CD-2 Schedule
Completion of RD End December 2007 CD-2
Review Beginning May 2008
8
RD Schedule
9
RD Schedule
10
Updating the Schedule and Workpackages
  • The current full-project schedule is not
    manageable
  • It violates the DOE order in places
  • It is not uniformly detailed
  • It needs to have costs and resources assigned at
    the lowest level
  • The intersystem logic is sometimes illogical
  • It is reasonable to correct it in the next 3
    months or so
  • Kim and Martin will work directly with each
    subsystem manager
  • The level of effort will vary from a few hours to
    a few days
  • Martin will rework the intersystem logic in
    consultation with the subsystem managers
  • Once again, it is necessary to go over the labor
    rates at each institution

11
Funding and Schedule Distribution
  • Kim and Martin will keep two sets of books
  • The DOE set that has the milestones and costs
    including contingency
  • The nEDM set, to be used by the subsystem and
    work package managers, that allocates the base
    costs and schedule
  • The total cost contingency is 4.2M and the
    schedule contingency is 1 year
  • Contingency allocations will be made under change
    control guidelines
  • Each fiscal year, Martin plans to distribute base
    funds as soon as possible and contingency funds
    as few times as possible later in the year.
  • Practice schedule updating on the RD

12
Change Control Limits
13
Preliminary Level 2 Milestones
There will be level 3 milestones too, about 2/Qtr
14
Monitoring Progress
15
Documenting Costs
  • nEDM must prepare for a fairly rigorous review,
    the Independent Cost Estimate (ICE)
  • Prepare a cost/resource estimate notebook by
    lowest WBS element that contains
  • the rationale and approach for estimating work
    package costs, e.g. vendor quote, catalog price,
    parametric scaling, etc
  • vendor quotes for procured items over 25k and
    maybe 5k
  • estimates via other methods
  • Another workshop for subsystem and work package
    managers, perhaps associated with the next or
    following collaboration meeting
  • Internal reviews

16
Specifications for Integrated Tests
  • Paul Huffman will chair a committee to determine
    what consists of adequate performance from the
    cryogenic subsystems to allow them to be
    installed into the main cryostat at ORNL
  • The committee should include David Haase,
    Takeyasu Ito, Brad Filippone and Steve Williamson
  • Anyone else can contribute
  • Preliminary proposal by next collaboration
    meeting
  • Refined proposal by the following collaboration
    meeting

17
Memoranda of Understanding
Will use examples from other nuclear physics
projects
18
Engineering Approach