Title: Martin Cooper, Los Alamos
1The Path to CD-2
Martin Cooper, Los Alamos Co-spokesperson and
Contract Project Manager for the EDM Project for
presentation to The EDM Collaboration Pasadena,
CA February 14, 2007
2Outline
- CD-2 schedule
- RD schedule
- Upgrading the schedule and work packages
- Monitoring progress
- Documenting costs
- Specifications for Integrated Tests
- Memoranda of Understanding
- Engineering approach (Jan Boissevain)
3Perspective
- To paraphrase the narrator from the Shawshank
Redemption, crawled through 500 yards of
unspeakably vile mire to freedom - Unfortunately, there is another mile long pipe to
reach CD-2
4Caveats
- Many things in this talk depend on the resolution
of the FY07 budget - There is Jehannes way or the highway
5New Phase for nEDM
- The nEDM Project has entered a new phase The
detailed planning/baseline development phase - Involves refining the scope, schedule and cost
plan to a single baseline (not a range). - The baseline becomes the contract with DOE
(customer) at CD-2. - CD-2 approval is dependent on a valid baseline.
- Schedule and cost status must now be reported to
DOE at a lower level of detail.
6Performance Baseline
The Project Performance Baseline is Developed
on A mature design (RD and engineering
effort) A well defined and documented scope
(work packages) A resource loaded detailed
schedule (MS Project schedule) A definitive
cost estimate (basis of estimate) Defined key
performance parameters Source DOE Order 413.3A
7CD-2 Schedule
Completion of RD End December 2007 CD-2
Review Beginning May 2008
8RD Schedule
9RD Schedule
10Updating the Schedule and Workpackages
- The current full-project schedule is not
manageable - It violates the DOE order in places
- It is not uniformly detailed
- It needs to have costs and resources assigned at
the lowest level - The intersystem logic is sometimes illogical
- It is reasonable to correct it in the next 3
months or so - Kim and Martin will work directly with each
subsystem manager - The level of effort will vary from a few hours to
a few days - Martin will rework the intersystem logic in
consultation with the subsystem managers - Once again, it is necessary to go over the labor
rates at each institution
11Funding and Schedule Distribution
- Kim and Martin will keep two sets of books
- The DOE set that has the milestones and costs
including contingency - The nEDM set, to be used by the subsystem and
work package managers, that allocates the base
costs and schedule - The total cost contingency is 4.2M and the
schedule contingency is 1 year - Contingency allocations will be made under change
control guidelines - Each fiscal year, Martin plans to distribute base
funds as soon as possible and contingency funds
as few times as possible later in the year. - Practice schedule updating on the RD
12Change Control Limits
13Preliminary Level 2 Milestones
There will be level 3 milestones too, about 2/Qtr
14Monitoring Progress
15Documenting Costs
- nEDM must prepare for a fairly rigorous review,
the Independent Cost Estimate (ICE) - Prepare a cost/resource estimate notebook by
lowest WBS element that contains - the rationale and approach for estimating work
package costs, e.g. vendor quote, catalog price,
parametric scaling, etc - vendor quotes for procured items over 25k and
maybe 5k - estimates via other methods
- Another workshop for subsystem and work package
managers, perhaps associated with the next or
following collaboration meeting - Internal reviews
16Specifications for Integrated Tests
- Paul Huffman will chair a committee to determine
what consists of adequate performance from the
cryogenic subsystems to allow them to be
installed into the main cryostat at ORNL - The committee should include David Haase,
Takeyasu Ito, Brad Filippone and Steve Williamson - Anyone else can contribute
- Preliminary proposal by next collaboration
meeting - Refined proposal by the following collaboration
meeting
17Memoranda of Understanding
Will use examples from other nuclear physics
projects
18Engineering Approach