Assembly Line Balancing - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Assembly Line Balancing

Description:

Assembly Line Balancing The assembly line is a production line where material moves continuously through a series of workstations where assembly work is performed. – PowerPoint PPT presentation

Number of Views:590
Avg rating:3.0/5.0
Slides: 29
Provided by: Charle790
Category:

less

Transcript and Presenter's Notes

Title: Assembly Line Balancing


1
Assembly Line Balancing
  • The assembly line is a production line where
    material moves continuously through a series of
    workstations where assembly work is performed.

2
Assembly Lines
  • Principle of Interchangeability
  • individual components that make up a finished
    product should be interchangeable between product
    units
  • Division of Labor complex activities divided
    into elemental tasks
  • work simplification
  • standardization
  • specialization
  • Mass Production

3
Production Systems
  • Project Shop
  • Job Shop
  • Flow Shop
  • Assembly Line
  • Continuous Flow
  • project networks
  • job shop scheduling
  • flow shop scheduling
  • assembly line balancing
  • e.g. cyclic scheduling
  • single facility EOQ model

4
The Problem
Assign work elements (tasks) to workstations to
minimize unit assembly costs (e.g. labor cost).
flow of the line
station 3
station 1
station 2
Tasks
precedence requirements
precedence requirements
5
Cycle Time
The time between the completion of two successive
products, assumed constant for all products for
a given production line speed. The minimum
value of the cycle time must be greater than or
equal to the longest station time.
A group of engineering management students
discussing cycle times.
6
Problem Formulation
Assume production rate of P with m parallel
lines. Then each line must produce a unit every
m / P time units. Set Cycle time C lt m / P
the time between completion of two successive
units.
Example Planned order release requires a
production rate of 80 units per hours. Four (4)
assembly lines are available. Therefore cycle
time C ? 4/80 .05 hr. 3 minutes
7
Station Time
Sj lt C
8
Performance Measures
let k number of workstations 1 lt k lt n
dj C Sj delay (idle) time at station j
9
Minimizing Idle Timeminimizes assembly time per
unit
10
Precedence Relationships
  • Precedence constraints
  • some tasks may have to be completed in a
    particular sequence task i task j
  • Zoning restrictions
  • some tasks cannot be performed at the same
    workstation (divorces)
  • some tasks may be required to be performed at the
    same workstation (marriages)

11
Our Very First Example
S5
S1
S2
S3
S4
1 5 min
2 7 min
3 10 min
4 6 min
5 8 min
k 5 C 10 min. P 6 per hr.
Performance Measures IT 5(10) 36 14 min. LE
36/50 72 SI 7.35
12
Our Very First Example
S1
S2
S3
S4
1 5 min
2 7 min
3 10 min
4 6 min
5 8 min
k 4 C 12 min. P 5 per hr.
Performance Measures IT 4(12) 36 12 min. LE
36/48 75 SI 7.48
13
Our Very First Example
S1
S3
S2
1 5 min
2 7 min
3 10 min
4 6 min
5 8 min
k 3 C 14 min. P 4.286 per hr.
Performance Measures IT 3(14) 36 6 min. LE
36/42 85.7 SI 4.47
14
Our Very First Example
S1
S2
1 5 min
2 7 min
3 10 min
4 6 min
5 8 min
k 2 C 22 min. P 2.72 per hr.
Performance Measures IT 2(22) 36 8 min. LE
36/44 81.8 SI 8
15
Our Very First Example
S1
1 5 min
2 7 min
3 10 min
4 6 min
5 8 min
k 1 C 36 min. P 1.67 per hr.
Look, a perfectly balanced line.
Performance Measures IT 1(36) 36 0 min. LE
36/36 100 SI 0
16
Chuck. Could you summarize all this for me?
Just tell me what I need to know!
17
Our Very Next Example Problem
Task 1 2 3 4 5 6 7 ti 5 3 4 3 6 5 2 Task 8 9 10
11 12 ti 6 1 4 4 7
precedence relationships
18
Trial and Error Approach
  • Find minimum number of stations for a given cycle
    time
  • Repeat for various cycle times
  • Select solution that minimizes idle time

cycle times feasible? min k 50 yes 1
25 yes 2 10 yes 5 5 no 10 tmax
7 2 no 25
19
I II III IV V VI VII
station task ti column sum cumulative
sum I 1 5 5 5 II 2 3 4 3 6 11 III 3 4 5 6 10
21 IV 6 5 5 26 V 7 2 9 1 10 4 7 33 VI 8 6 11
4 10 43 VII 12 7 7 50
C 10 IT 7(10) 50 20 LE 50/70 71 SI
9.16
20
Heuristic
  • place each task as far to the left as possible
  • no restriction of movement within a column
  • can move tasks further to the right
  • assign tasks to work stations such that the sum
    of the times does not exceed C
  • always select task with longest time when forming
    a workstation

21
I II III IV V VI
  • task ti pred
  • 1 5 0
  • 2 3 1
  • 3 4 2
  • 4 3 1
  • 6 2
  • 6 5 5
  • 7 2 6
  • 8 6 7
  • 9 1 6
  • 10 4 6
  • 11 4 7
  • 12 7 11

X
station task ti column sum cumulative
sum I 1 5 2 3 8 8 II 4 3 5 6 9 17 III 3
4 6 5 9 26 IV 7 2 9 1 10 4 7 33 V 8 6 11 4
10 43 VI 12 7 7 50
C 10 IT 6(10) 50 10 LE 50/60 83 SI
4.89
22
I II III IV V VI
Can move tasks to the right.
station task ti column sum cumulative
sum I 1 5 2 3 8 8 II 4 3 5 6 9 17 III 3
4 6 5 9 26 IV 7 2 8 6 8 34 V 10 4 11 4 8 4
2 VI 9 1 12 7 8 50
C 9 IT 6(9) 50 4 LE 50/54 92.6 SI 2
23
Positional Weight Method
  • Find positional Weight (PW) for each task
  • Rank tasks based upon PW
  • highest first
  • Assign tasks to stations with highest rank first
  • Continue to assign tasks as long as time remains
  • task does not violate precedence relationship
  • station time does not exceed cycle time
  • Repeat until all tasks are assigned
  • Each task is assigned to the first feasible
    station
  • greedy algorithm

24
Positional Weight
PWi time of the longest path from beginning of
task i through the remainder of network.
2
6
3
4
5
5
7
1
3
6
4
4
Task 1 2 3 4 5 6 7 PWi 34 27 24 29 26 20 15 Tas
k 8 9 10 11 12 PWi 13 8 15 11 7
25
Task 1 2 3 4 5 6 7 PWi 34 27 24 29 26 20 15 Tas
k 8 9 10 11 12 PWi 13 8 15 11 7
  • task ti pred
  • 1 5 0
  • 2 3 1
  • 3 4 2
  • 4 3 1
  • 6 2
  • 6 5 5
  • 7 2 6
  • 8 6 7
  • 9 1 6
  • 10 4 6
  • 11 4 7
  • 12 7 11
  • Rank Task PW
  • 1 34
  • 4 29
  • 2 27
  • 5 26
  • 3 24
  • 6 20
  • 7 15
  • 10 15
  • 8 13
  • 11 11
  • 9 8
  • 12 7

Assume CT 10
26
station task ti column sum cumulative I 1 5
4 3 8 8 II 2 3 5 6 9 17 III 3 4 6 5 9 26 IV 7
2 10 4 6 32 V 8 6 11 4 10 42 VI 9 1 12 7 8 50
  • task ti pred
  • 1 5 0
  • 2 3 1
  • 3 4 2
  • 4 3 1
  • 6 2
  • 6 5 5
  • 7 2 6
  • 8 6 7
  • 9 1 6
  • 10 4 6
  • 11 4 7
  • 12 7 11
  • Rank Task PW
  • 1 34
  • 4 29
  • 2 27
  • 5 25
  • 3 24
  • 6 20
  • 7 15
  • 10 15
  • 8 13
  • 11 11
  • 9 8
  • 12 7

I have long advocated the positional weight
method in order to achieve the best balance.
C 10 IT 6(10) 50 10 LE 50/60 83.3 SI
5.09
27
An Integer Programming Approach
let xik 1 if task i assigned to station k 0
otherwise ci,k cost coefficient of xi,k where
cik lt ci,k1
precedence relationship when task j precedes task
i
28
Some Final Considerations
  • If significant idle time remains
  • consider parallel lines with larger cycle times
  • use more than one worker per station (group
    stations)
  • task variability
  • max station time ESi 2.33 STDSi lt C
  • probability all stations complete on time .99k
  • provide rework area
  • add buffers
  • use unpaced (asynchronous) lines
  • Max profit rather then minimize idle time

These are some very good final considerations.
Write a Comment
User Comments (0)
About PowerShow.com