Chapter 2: Line Balancing - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

Chapter 2: Line Balancing

Description:

To meet production goals, Maximize output. Common Approaches to Line Balancing: ... Meet production goals given to you by your management, ... – PowerPoint PPT presentation

Number of Views:496
Avg rating:3.0/5.0
Slides: 18
Provided by: hay45
Category:
Tags: balancing | chapter | line | meet

less

Transcript and Presenter's Notes

Title: Chapter 2: Line Balancing


1
Chapter 2 Line Balancing
  • IE 5511 Human Factors
  • Professor Hayes

2
Line Balancing
  • Goals
  • To meet production goals,
  • Maximize output.
  • Common Approaches to Line Balancing
  • Estimating the number of operators for a given
    number of stations,
  • Work element sharing grouping activities pr
    work elements into stations or jobs performed
    by a single person (some times multiple people
    work in concert at a single station or machine)

3
Estimating the number of operators
  • In a perfectly balanced line, all operations at
    all station would take identical time.
  • Efficiency would be 100
  • However, this rarely happens!!
  • 100 efficiency is rarely achievable,
  • A more reasonable goal is 95 efficiency.
    (However, even that may not be achievable
    depending on the nature of the operations).

4
Estimating the number of Operators
  • To achieve a given rate of production, R,
  • N operators are needed (total).
  • (1) N R x S AM R x S SM
  • E

Standard Minutes Time it actually takes to
complete an operation on average
Number of Operators Needed
Desired Rate of Production
Efficiency (expressed as fraction)
Allowed Minutes total time between pieces (e.g.
AM time of slowest operation)
5
Procedure for Determining the Number of
Operators needed to meet production goals.
  • Assumptions. You have already determined
  • the number of workstations,
  • their sequence
  • the operations that will be performed at each
    one.
  • Goals. To
  • Meet production goals given to you by your
    management,
  • Balance the workload between stations by putting
    more workers at the slower stations,
  • Reduce idle time

6
Procedure Estimating the Number of Operators
  • Givens Production goal, operation sequence.
  • Step 0 (Prior to the analysis) Perform time
    studies for each operation using experienced
    operators in order to obtain standard times (SM).
  • Step 1 Convert the production rate, R, into the
    same time units as your standard times.
  • Step 2 (optional) Estimate the total number of
    operators for the line using Equation (1) (see
    previous slides)
  • Step 3 Estimate the number of operators needed
    for each operation,
  • Step 4 Identify the slowest operation given the
    number of operators computed in previous step,
  • Step 5 Test have you met the production goal?
  • Step 6 Adjust. Add more operators, negotiate to
    reduce the production goal, or try additional
    methods.

7
Example Estimating the Number of Operators
  • Givens
  • Production goal 700 units/day where day 8
    hours.
  • Operation sequence Op1, Op2, Op3, Op4, Op5,
    Op6, Op7, Op8.
  • Step 0 (Prior to the analysis) Perform time
    studies for each operation using experienced
    operators in order to obtain standard times in
    minutes (SM).

8
Example Estimating the Number of Operators
  • Step 1 Convert the production rate, R, into the
    same time units as your standard times.
  • The standard times, SM, have been expressed in
    minutes, while R is in days, so
  • R 700 units/day 1.458 units/min
  • 480 min/day
  • Also compute the desired cycle time (rate at
    which units exit line)
  • cycle time 1 0.685 min/unit
  • R

9
Example Estimating the Number of Operators
  • Step 2 (optional) Estimate the total number of
    operators, N, required to meet production goal,
    using Equation (1)

10
Example Estimating the Number of Operators
  • Step 3 Estimate the number of operators needed
    for each operation,
  • Step 4 Identify the slowest operation given the
    number of operators computed in previous step,
  • Step 5 Test have you met the production goal?

11
Work Element Sharing
  • A line can sometimes be balanced with less cost
    by rearranging the sub-work elements (e.g.
    activities composing a work element)
  • For example, by giving activities from the
    busiest element to elements with idle time.

12
Properties of Work Elements
  • What is a work element?
  • How big should a work element be?

Assemble items in box
Work Element
Load Styrofoam block
Load book
Sub-work elements
Grasp block
Move block to box
Orient Block
Release Block
Sub-sub work elements
13
Work Element Properties
  • Work elements can be represented at various
    levels of abstraction or detail
  • Work elements can almost always be sub-divided
    into smaller elements.
  • The appropriate representation depends on the
    task and situation.

14
Work Element Sharing GEs Line Balancing A
Procedure for Assigning Work Elements to
Stations
  • Given
  • Precedence graph
  • Production goal (e.g. 300 units per shift)
  • Shift duration (e.g. 450 minutes)
  • Number of workstations (e.g. 6 workstations)
  • Decided how to assign elements to workstations so
    as to meet production goals without violating
    precedence constraints!

15
Precedence relations 1 y is before x
16
Compute positional weighs, Record immediate
predecessors,Sort from biggest positional weight
17
The Final Assembly Line
A streamlined version
Station 3
Station 1
(05) (06)
(00) (02) (01) (03)
(07) (09)
(08)
(10)
Station 2
Station 6
Station 4
Station 5
(04)
Write a Comment
User Comments (0)
About PowerShow.com