Title: Chapter 2: Line Balancing
1Chapter 2 Line Balancing
- IE 5511 Human Factors
- Professor Hayes
2Line Balancing
- Goals
- To meet production goals,
- Maximize output.
- Common Approaches to Line Balancing
- Estimating the number of operators for a given
number of stations, - Work element sharing grouping activities pr
work elements into stations or jobs performed
by a single person (some times multiple people
work in concert at a single station or machine)
3Estimating the number of operators
- In a perfectly balanced line, all operations at
all station would take identical time. - Efficiency would be 100
- However, this rarely happens!!
- 100 efficiency is rarely achievable,
- A more reasonable goal is 95 efficiency.
(However, even that may not be achievable
depending on the nature of the operations).
4Estimating the number of Operators
- To achieve a given rate of production, R,
- N operators are needed (total).
- (1) N R x S AM R x S SM
- E
Standard Minutes Time it actually takes to
complete an operation on average
Number of Operators Needed
Desired Rate of Production
Efficiency (expressed as fraction)
Allowed Minutes total time between pieces (e.g.
AM time of slowest operation)
5Procedure for Determining the Number of
Operators needed to meet production goals.
- Assumptions. You have already determined
- the number of workstations,
- their sequence
- the operations that will be performed at each
one. - Goals. To
- Meet production goals given to you by your
management, - Balance the workload between stations by putting
more workers at the slower stations, - Reduce idle time
6Procedure Estimating the Number of Operators
- Givens Production goal, operation sequence.
- Step 0 (Prior to the analysis) Perform time
studies for each operation using experienced
operators in order to obtain standard times (SM). - Step 1 Convert the production rate, R, into the
same time units as your standard times. - Step 2 (optional) Estimate the total number of
operators for the line using Equation (1) (see
previous slides) - Step 3 Estimate the number of operators needed
for each operation, - Step 4 Identify the slowest operation given the
number of operators computed in previous step, - Step 5 Test have you met the production goal?
- Step 6 Adjust. Add more operators, negotiate to
reduce the production goal, or try additional
methods.
7Example Estimating the Number of Operators
- Givens
- Production goal 700 units/day where day 8
hours. - Operation sequence Op1, Op2, Op3, Op4, Op5,
Op6, Op7, Op8. - Step 0 (Prior to the analysis) Perform time
studies for each operation using experienced
operators in order to obtain standard times in
minutes (SM).
8Example Estimating the Number of Operators
- Step 1 Convert the production rate, R, into the
same time units as your standard times. - The standard times, SM, have been expressed in
minutes, while R is in days, so - R 700 units/day 1.458 units/min
- 480 min/day
- Also compute the desired cycle time (rate at
which units exit line) - cycle time 1 0.685 min/unit
- R
9Example Estimating the Number of Operators
- Step 2 (optional) Estimate the total number of
operators, N, required to meet production goal,
using Equation (1)
10Example Estimating the Number of Operators
- Step 3 Estimate the number of operators needed
for each operation, - Step 4 Identify the slowest operation given the
number of operators computed in previous step, - Step 5 Test have you met the production goal?
11Work Element Sharing
- A line can sometimes be balanced with less cost
by rearranging the sub-work elements (e.g.
activities composing a work element) - For example, by giving activities from the
busiest element to elements with idle time.
12Properties of Work Elements
- What is a work element?
- How big should a work element be?
Assemble items in box
Work Element
Load Styrofoam block
Load book
Sub-work elements
Grasp block
Move block to box
Orient Block
Release Block
Sub-sub work elements
13Work Element Properties
- Work elements can be represented at various
levels of abstraction or detail - Work elements can almost always be sub-divided
into smaller elements. - The appropriate representation depends on the
task and situation.
14Work Element Sharing GEs Line Balancing A
Procedure for Assigning Work Elements to
Stations
- Given
- Precedence graph
- Production goal (e.g. 300 units per shift)
- Shift duration (e.g. 450 minutes)
- Number of workstations (e.g. 6 workstations)
- Decided how to assign elements to workstations so
as to meet production goals without violating
precedence constraints!
15Precedence relations 1 y is before x
16Compute positional weighs, Record immediate
predecessors,Sort from biggest positional weight
17The Final Assembly Line
A streamlined version
Station 3
Station 1
(05) (06)
(00) (02) (01) (03)
(07) (09)
(08)
(10)
Station 2
Station 6
Station 4
Station 5
(04)