Title: Thursday Summary of Working Group I
1Thursday Summary of Working Group I
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 1
2Thursday Summary of Working Group I
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 2
3Thursday Summary of Working Group I
-create a repository for different layout
configurations and optics solutions ? common
data base for future studies ? common reference
for future discussions ? will be discussed on
Friday -interesting modular proposal for
maximizing F by additional dipole inside
experiment ? all insertion scenarios benefit ?
should be pursued independently of final IR
design -NiTi is not a viable solution for IR
upgrade ? is this true for all IR layout and
optics proposals (e.g. low gradient triplet
solution)? ? will be discussed on Friday
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 3
4Thursday Summary of Working Group I
-two options for dealing with the increased heat
load inside the triplet magnets 1) construct
more robust triplet magnets that can tolerate
the increased peak heat load 2) reduce the
peak heat load with an upgrade of the TAS
absorber
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 4
5Thursday Summary of Working Group I
- 1) construct more robust triplet magnets that
can tolerate - the increased peak heat load
- ? structured cable design with Ni3Sn and Inconel
718 jacket - Iron less quadrupoles for Q1 with 340 T/m 40mm
aperture - and expected heat tolerances of gt 50 W/m
- Strong mechanical support and low inductance for
large - quench induced voltages
- Confidence that Ni3Sn is matured technology by
2010? - Disuccion Inconel jacket could also be used
with NiTi?
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 5
6Design Q1 using structured cable
6-on-1 cabling of Nb3Sn strand around thin-wall
inconel X750 spring tube Draw within a thicker
inconel 718 jacket Interior is not impregnated
only region between cables in winding Volumetric
cooling to handle volumetric heating from
particle losses
7Thursday Summary of Working Group I
- 2) reduce the peak heat load with an upgrade of
the TAS - absorber
- ? levitated dipole coil design with opening at
room temperature - B 8.7 T at 4.5 K Ni3Sn only at inner coil NiTi
otherwise - interesting magnet design for a magnetic TAS
option
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 7
8D1 levitated-pole dipole
8.7 T 4.5 K
Cold iron pole piece, warm iron flux
return. Cancel Lorentz forces on coils, pole
steel.
9Thursday Summary of Working Group I
- -compensate Lorentz force on the coils by using
two race - track coils ? 15 T field for Ni3Sn and 8T for
NiTi - -open mid plane and possibility of installing
dedicated - absorber material
- Interesting option for magnetic TAS design
- Who is following this research up? US-LARP has
decided - to suspend dipole RD and to concentrate on
quadrupoles!
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 9
10OMD Design Challenges
- Counteracting large vertical forces between the
coils without any structure appears to be a
challenge. - Good field quality maybe a challenging task due
to large midplane gap. - Large Bpeak/Bcenter ratio in magnets with large
midplane gap may reduce operating field. - The optimum design may look totally different.
11A True Open Midplane Design
In earlier OMD designs, absorbers were placed
between the the coils. Secondary showers from the
absorber deposited a large amount of radiation
and heat load on the coils. This problem is fixed
in the new design.
12Thursday Summary of Working Group I
-geometric reduction factor can be reduced with
the help of CRAB cavities (transverse kick ?
alternative to JPK dipole) -LHC parameters
requires between 4MV (small crossing angle) and
100 MV voltage for f 400MHz ?? 800 MHz -small
emittance blowup requires turn-by-turn phase
control of better than 0.01 degrees -CRAB
cavities require sufficient large beam
separation (? installation after D2 plus dog leg
separation?)
LHC LUMI 2005 2.9.2005 Arcidosso
Oliver Brüning 12
13Super-KEKB crab cavity scheme
2 crab cavities / beam / IP
14voltage required for Super-LHC